Match the signed agreement to the land and proposal
Start with the effective date, legal description and defined project. Compare them with the land in the buyer’s offer and ask the city whether a changed proposal or additional property falls within the agreement. Request any amendments and written notices that affect the answer.
Norwalk’s City Council approved the development agreement with IALCO Warren County Two on March 5, 2026. The signed agreement gives April 29, 2026 as its effective date. Section 1.4 describes development rights for the project subject to the agreement, applicable rules and required approvals.

Check who adopted the later rule and when
Norwalk’s Section 1.4 addresses changes to applicable rules enacted after the effective date by the council sitting at the time of the agreement. It says those changes do not apply to the project under that provision unless the developer elects in writing to apply them to all or part of the project, subject to the exceptions in the agreement.
The agreement preserves generally applicable citywide ordinances the city reasonably finds necessary for public health and safety. It also calls for modifying or suspending affected provisions as needed to comply with applicable state or federal law. Ask counsel and planning staff to check the text and adoption date of the rule in question, which council adopted it, and whether an exception or written election applies.
Verify the site plan and permits before committing to a deadline
Norwalk’s agreement calls for a master site plan to go to the City Council for approval. It also contemplates later site plans and permits as required. Exhibit C sets review timeframes after specified submissions and allows extensions while the city waits for revisions or other necessary information requested in writing.
Ask for the latest approved plan, any modifications and a list of outstanding approvals for the proposed work. Put each approval on the sale or option schedule with the application owner, target date and written decision needed. Agree what happens if the approving authority asks for changes or needs more time.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a sale, lease or existing development agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the transaction or approval decision you’re facing and your next deadline. Keep signed agreements, site plans and permit records for private follow-up.
Questions landowners ask
Can a later local rule apply under the Norwalk agreement?
The answer depends on who adopted the rule, when it was adopted and whether it falls within the agreement’s exceptions. Ask for any developer election delivered in writing and have counsel review the specific rule.
Does approval of the development agreement also approve the site plan?
The Norwalk agreement calls for the master site plan to be submitted for its own City Council approval. Ask the city for that decision and any required permit records.
Sources & further reading
Sources checked November 21, 2026. The signed agreement describes how the project is to be reviewed. The documents reviewed leave any later election, site-plan approval and permit status unverified. Local rules and program details can change. Check the requirements for the actual project.