Find the amendment for the tract you want to transfer
Ask the title company for the recorded deed, the full repurchase exhibit and any amendments or releases. Match the descriptions to your survey and the land you plan to convey or lease. If more than one deed covers the property, check the terms and recording information for each tract.
Each March 2026 Grow Odessa amendment replaces its deed’s repurchase exhibit. The replacement allows a buyback if the qualifying first-phase foundation pour has not started within 24 months after the amendment is recorded. Use the county recording stamp to identify the date that starts the period.

Check whether the work meets the deed’s definition
The signed amendments define the start by reference to pouring the foundation for a qualifying building on usable land within the tract. The text addresses building size, the buyer’s reasonable discretion and reasonable construction or engineering changes.
If the developer says the milestone was met, ask for dated records identifying the work and the land where it occurred. Ask counsel to compare the actual work and its date with the governing exhibit. Ask the title company what it needs to document satisfaction of the milestone or remove a title exception for the repurchase right.
Check the price, notice and return deed
If the milestone is missed, each signed amendment provides for Grow Odessa to buy back the land and improvements for 80 percent of the purchase price stated for that tract. The amendments call for Grow Odessa to send a certified letter to the grantee’s last known address and tender payment at the same time to a title company it chooses. The grantee has 60 days from receiving notice to deliver a special warranty deed.
The amendments provide for title to revert if the repurchase does not close within those 60 days, subject to certain existing mortgages or liens. Keep any notice, proof of receipt and evidence of payment tender. Have counsel and the title company confirm what the documents mean for ownership, any recorded liens and your planned closing.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your land or an existing agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the interest you may transfer and your next decision date. Keep deeds, notices and other private records for follow-up.
Questions landowners ask
Which date starts the 24-month period in the Grow Odessa example?
Each amendment measures the period from its recording date. Ask the title company or county clerk for the recorded copy covering your tract.
Does paying for a deed amendment clear the repurchase right?
Check the signed amendment and any later release. New Era reported repayment of the separate note issued as consideration for the amendments. The amendments each provide for a buyback if the specified construction milestone is missed.
Sources & further reading
Sources checked November 20, 2026. The example uses the signed March amendments. The sources reviewed leave the amendment recording dates, milestone status and any exercise or release of the repurchase rights unverified. Local rules and program details can change. Check the requirements for the actual project.
- Signed Grow Odessa amendment to the first special warranty deed, Exhibit A
- Signed Grow Odessa amendment to the second special warranty deed, Exhibit A
- New Era March 31, 2026 Form 8-K, Item 1.01 and deed exhibits
- New Era November 2026 Form 10-Q, note payable for deed amendment consideration
- Ector County Clerk, land records portal