Define which later deal triggers the payment
Ask for a closing statement that shows the amount payable at closing and the amount tied to a later event. In Pyote, the agreement ties the later payment to a defined binding data center lease, colocation agreement or similar contract involving rights conveyed in the sale, or to a qualifying transfer of the property and associated rights for data center use. The closing date of a qualifying transfer counts under the agreement.
Agree what the buyer must provide to show the event occurred, including if a successor or assignee handles the deal. Pyote’s purchase agreement also allows specific reductions for court-determined damages. For a qualifying claim filed on time, the buyer may withhold only the amount claimed in good faith and must pay the balance when due. Ask counsel to check how your agreement determines the amount due if only part is disputed.

Keep the notice and payment deadlines separate
The Pyote agreement calls for quarterly written progress reports and commercially reasonable efforts to meet the first milestone requirement within six months after closing. The buyer must notify the sellers within five business days after the milestone conditions are satisfied. The buyer then must pay within five business days of providing that notice.
For your deal, identify who sends and receives each notice, what evidence must accompany it and how the parties document delivery. Ask counsel what the agreement provides if the buyer fails to report progress or send a required notice. Keep any notice and evidence of its delivery with the payment records.
Agree when the title company may record the deed of trust
The Pyote agreement calls for the buyer to execute a conditional deed of trust at closing. The title company is to hold it under a separate escrow agreement the sellers, buyer and title company are to sign by closing. If the milestone conditions are satisfied and the buyer misses the payment deadline after notice, the seller may instruct the title company in writing to record the deed of trust under those escrow terms.
Compare the purchase agreement, deed of trust and escrow instructions before closing. Ask the title company what documents it needs to hold and what it would require before recording. Pyote’s purchase deposit has its own escrow with the sellers’ counsel. In Pyote, the sellers must execute and deliver a recordable satisfaction and discharge as a condition of receiving the full applicable milestone payment. The milestone provision survives closing until full payment is final and binds the buyer’s successors and assigns.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss an offer with a milestone payment
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the event tied to the proposed payment and your next decision date. Keep private agreements and escrow papers for follow-up.
Questions landowners ask
Does every resale of the property trigger the Pyote milestone payment?
The signed agreement defines a qualifying transfer of the property and associated rights to a third party for the express purpose of constructing or operating a data center. Ask counsel to compare the actual transfer documents with the agreement’s definitions and other conditions.
When could the seller instruct the title company to record the Pyote deed of trust?
The agreement permits a written instruction under the separate escrow terms if the milestone conditions have been satisfied and the buyer misses the five-business-day payment deadline following the satisfaction notice.
Sources & further reading
Sources checked November 20, 2026. The court approved the transactions October 2. Hut 8’s November 4 filing reported a planned December closing subject to seller extension rights and remaining conditions. Later closing confirmation, the final separate security escrow agreement, the executed conditional deed of trust and any recording were unavailable for review. Local rules and program details can change. Check the requirements for the actual project.