Start with the building permit and the project’s coverage
Ask the City for the applicable building permit and confirm its issuance date and the next proof deadline. Section 112-4 addresses which projects are covered. It treats systems built or installed before the ordinance took effect differently and covers certain retrofits or other changes that increase designed discharge duration or power rating. If the system predates the ordinance or has multiple permits, ask the City which rules and permit date govern your site.
For a covered project, use the permit issuance anniversary to count back 60 days. Write that due date beside your proposed closing or lease renewal date. If the filing is due before closing, ask for the filed proof and the City’s record of receipt before you sign. If it is due shortly afterward, identify who will gather and provide it and when they will deliver the records to you.

Check the amount as well as the renewal
The ordinance calls for an irrevocable bond or another form of surety the City accepts, such as a letter of credit, to back removal. The City is the designated assignee or beneficiary, and the Planning Board approves security equal to 150% of the estimated removal cost. The security must provide for an annual increase to account for inflation or other anticipated increases in removal costs.
Ask for the full current instrument and amendments, its amount and expiry or renewal terms, the latest removal estimate and the basis for the adjustment. Compare those records with the written proof the project owner or permit holder sent and any City response. If the packet is missing, appears late or shows a renewal with no documented amount adjustment, ask the City what it received and what remains outstanding.
Review what the recorded agreement leaves with the landowner
Before the building permit and as a condition of a special use permit, the applicant and initial landowner must enter a decommissioning agreement with the City. The ordinance requires the agreement to make the initial landowner or its successors or assigns responsible for the agreement’s obligations if the applicant or successor project owner fails to perform them. It calls for recording with the St. Lawrence County Clerk and indexing as deed restrictions against the project property for the City’s benefit.
Ask your title company for the recorded agreement and any recorded amendments. Have counsel match the parties and parcel description to the deed, lease and permit. In the sale or renewal documents, identify who pays for the surety and required increases, who gives you copies each year and when you receive notice of a lapse or filing problem. Ask counsel how those private promises work alongside the recorded agreement.
If the property or system changes owners, § 112-7(L) makes continuation of the special use permit conditional on the successor owner or operator assuming the permit, site plan approval and decommissioning plan obligations in writing. Ask the City and your counsel who will sign that assumption and what separate ownership-change filings apply to your closing.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your Ogdensburg land or existing lease
Sunland reviews battery storage land sale and lease opportunities and potential assignments of existing agreements nationwide. Share your role, the general location and the closing or renewal milestone you are checking. Keep permits, surety instruments and signed agreements for private review.
Questions landowners ask
Which date starts the annual deadline calculation?
Use the anniversary of the City’s issuance of the applicable building permit and count back 60 days. Confirm the controlling permit and date with the City if the project has been altered or has several permit records.
What should the annual proof show?
It should show that the required bond or other City-accepted surety is still valid and usable and that the amount has been increased as required. Request the copy provided to the City and evidence of when the City received it.
Why does a buyer of the land need the decommissioning agreement?
The ordinance requires a recorded agreement that addresses the original landowner’s and successors’ responsibilities if the applicant or its successor fails to perform. Have your title company and counsel check the actual recorded terms for the property.
Sources & further reading
The ordinance and Council minutes were checked November 21, 2026 Pacific time. Confirm the governing permit, filing record and recorded agreement with the City and title company for your parcel. Local rules and program details can change. Check the requirements for the actual project.