Measure each setback from the right feature
For solar facility applications subject to Ohio Administrative Code rule 4906-4-09(G)(4), the design uses three minimum distances to the solar modules. Measure 50 feet from a nonparticipating parcel line and 300 feet from a nonparticipating home that existed when the application was filed. On a state, county or township road in or next to the project area, measure 150 feet from the pavement edge. Ask the project engineer to show which distances apply on each side of the proposed array. A fence line or road centerline can give a different measurement.
The current rule took effect May 30, 2024, and says amendments apply only to applications filed after the effective date. Ask for the filing date and case number. Ohio generally treats a solar plant with a single grid interconnection and capacity of at least 50 megawatts as a large solar facility under section 4906.01, subject to the statutory definition and exclusions. For a filed project, check the applicable rule, case drawings and any certificate conditions in the board's public docket.

Draw the farmhouse and retained parcel before committing acreage
Give the developer and surveyor your deed, available survey and proposed split drawing. Mark the farmhouse, drive, farm buildings and any road frontage you want to keep. Ask the developer to identify the parcel boundary and house it used, how it classified each for setback purposes, and what project document supports that classification. If you plan to keep the farmhouse on a separate parcel, ask for a second drawing that shows the proposed parcel boundary and runs the layout with the house and parcel treated as nonparticipating. Ask your adviser how any proposed signature or retained-land easement would affect that analysis.
For example, suppose a proposed row sits 240 feet from a farmhouse that qualifies as an existing nonparticipating residence and 120 feet from the pavement edge of an adjacent county road. If the rule applies, both measurements fall short of their respective minimums. Have the designer redraw the rows and calculate the resulting change in usable area. Ask for a dimensioned drawing at the affected edge. The broader application maps and distance table under rule 4906-4-08(C)(1) can help you find the relevant features and compare them with the version used in the offer.
Price the acres and preserve farm access
Ask for an acreage schedule that separates the option area, the proposed lease or sale area, the area available for modules and any separate easements. Compare the first layout with the version that protects the retained land. For a lease, confirm whether the stated rent uses surveyed lease acres, fenced or occupied acres, or a different measure. For a partial sale, ask how the price and minimum acceptable acreage would change if the boundary moves. Have counsel address when acreage is fixed, any minimum payment and when unused land is released.
Show the farm entrance, gates and equipment turning room alongside the proposed fencing, screening, cable routes and project roads. A strip outside the module rows may host screening or be requested for project access. Check the relevant plans and agreements before counting it as a farm route. If your retained fields depend on a lane through the site, have the agreement and drawing identify the route, its usable width and who maintains it after construction.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMatch the agreement to the layout the project can use
Put a date or revision number on the drawing used to negotiate the deal. If the project is already in the board's docket, compare your copy with the filed layout and any certificate conditions, amendments or later filings affecting your edge of the site. If the developer needs a different layout to preserve the farmhouse or road frontage, ask what regulatory review is needed and how the parties will approve changes to the agreement, payment acreage and reserved access.
Sunland welcomes solar land sale and lease inquiries nationwide. Share the property location, approximate acreage and what you plan to keep. Arrange to provide surveys and draft agreements privately if needed.
Questions landowners ask
Does the 300-foot distance apply to a house I plan to build?
The rule ties the 300-foot minimum to nonparticipating residences that existed when the application was filed. If you are keeping a future homesite, identify it on the drawing and discuss any separate protections in the agreement. Check the project's certificate conditions as well.
Where does the 150-foot road setback start?
Under this rule, the measurement runs from the pavement edge of a state, county or township road in or next to the project area to the solar modules. Ask the designer to show the road edge and measurement on the layout.
Will I be paid for land within a setback?
Payment depends on how your agreement defines the acres it pays for. Ask for a side-by-side acreage schedule and specify how the setback strip, access lanes and any separate easements are treated.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.