Oregon landowner guide

Which irrigation records should you check before signing an Oregon solar option?

If a developer proposes more than 12 acres of solar on high-value farmland in Oregon’s Columbia Valley wine region, ask the county planner which siting route applies before signing or extending the option. One county route requires the project land to be outside an irrigation district and clear of any qualifying place of use for irrigation at establishment and throughout the 20 years immediately before it. A field that has been farmed dry in recent years can still appear on a qualifying water-right record.

Could my land work?

Get the developer’s dated layout and acreage calculation. Ask county planning how it classifies the land, what date it will use for the facility’s establishment and what evidence it needs for the irrigation review. Compare the complete footprint with the district boundary and with dated water-right records and maps. If the records show overlap, ask the developer what layout or approval route it proposes before you agree to new acreage or deadlines.

Confirm which rule the developer is relying on

Ask whether the proposal relies on ORS 215.447 and OAR 660-033-0130(38)(h)(H). That provision allows a county to consider siting solar on more than 12 acres of the high-value farmland described in ORS 195.300(10)(f)(C) without an exception to the statewide agricultural land-use goal. This farmland category depends on exclusive farm use zoning, location within the Oregon portion of the Columbia Valley viticultural area, and statutory elevation, slope and aspect criteria. Ask the planner which classifications apply to the proposed project land.

Request the latest site plan and the calculation behind its acreage. Ask the developer to show access roads, staging areas, collector lines and related facilities alongside the arrays. The rule’s acreage calculation can include existing or proposed facilities on a single tract and commonly owned facilities on nearby land. Ask the planner which features and acreage count for this layout and whether the county is considering it under a separate siting provision.

Illustration of a land parcel and surrounding landscape

Check the district boundary and the full 20-year record

Ask county planning and the relevant irrigation district for the boundary record they use. Separately, look up the project land in the Oregon Water Resources Department’s Water Right Information System. Use its place-of-use summaries, maps and records vault to locate the underlying permit, certificate, decree, transfer order or groundwater registration authorizing irrigation. The place of use is the area where the record authorizes the use of water.

Have the developer or its water-rights specialist put the dated place-of-use maps and project layout on the same exhibit. Ask the county how it will date the facility’s establishment and whether the records cover that date and the entire preceding 20 years. If a transfer recently moved the authorized place of use to another field, request the transfer order and the earlier map. An earlier authorization can still overlap the proposed layout within the lookback period. Ask the Water Resources Department about missing records or conflicts among maps.

Tie the option to the records you need

The same route requires land in the service area of a utility described in ORS 469A.052(2). The land area must stay within what that utility reasonably expects to need to meet the applicable renewable portfolio standard under subsection (3). The land must also qualify as high-value farmland solely under the specified Columbia Valley provision. Ask the developer for its utility and acreage evidence, and ask the county what it needs to evaluate the site under this route.

If an irrigation record overlaps the layout or the record is incomplete, ask the developer for its updated layout, proposed approval route and revised timeline. Have counsel compare those records with the option exhibit and confirm who pays for records and redesign, what access you are granting, and how the agreement handles a footprint change, a delayed approval or an extension request. Use the layout to identify access you need for any land you will continue farming.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss a solar land opportunity

Sunland welcomes inquiries from landowners and authorized representatives nationwide about solar land sales, leases and existing agreements. Share the property’s general location, your role and the option or layout decision you face. Keep signed agreements, parcel drawings and water-right records for private follow-up.

Questions landowners ask

Does a dry field satisfy the 20-year irrigation test?

The test follows the authorized place of use, including historical authorizations. Ask for the underlying records and dated maps, then check the project footprint against the period the county identifies.

What if the irrigation right was moved to another field?

Get the transfer order and maps for both the old and new places of use. Ask the county whether the old authorization overlaps the project footprint during the 20 years immediately before establishment.

What if the panel rows avoid the old place of use?

Give the planner a drawing that also shows associated features such as roads, collector lines and staging areas. Ask which portions and acreage count under the rule the county will apply.

Sources & further reading

Sources checked 2026-11-22. Local rules and program details can change. Check the requirements for the actual project.