Map the facilities each project would keep using
Ask the project companies for a marked site plan and the applicable certificate conditions. Identify the location, owner and users of each shared road, line, substation or staging area on your property. Ask for the shared-use agreement or written evidence identifying who can use each facility and who maintains it.
The Oregon Trail Solar Facility’s second amended site certificate lists shared facilities that include access roads, transmission infrastructure and a collector substation. The Oregon Energy Facility Siting Council’s September 2026 order approved a split that placed the battery storage facility under a separate site certificate. The shared-facility conditions show what the named certificate holders must document when their use changes.

Check the filing when one facility stops operating
Under Condition 118(c) of the Oregon Trail Solar certificate, each certificate holder must submit an amendment determination request or a request to amend its site certificate before facility decommissioning or if operations cease. When facilities decommission at different times, the filing documents continued ownership and full responsibility for the shared facilities that the operating facility retains.
Ask each project company which filing it submitted or plans to submit. Request the filing and any written Department determination or site certificate amendment. Check the exact facility, date and responsibilities those records cover before relying on a plan to remove or keep equipment.
Request proof that eventual removal is covered
Condition 118(c) calls for coverage of the full cost of decommissioning the shared facilities in the operating facility’s bond or letter of credit under Condition 32 when the facilities decommission at different times. Ask the Department what instrument is on file and which shared assets the current cost estimate covers.
Condition 32 names the State of Oregon, acting through the Council, as beneficiary or payee. Ask counsel to review your lease and any separate landowner security to see who can enforce restoration obligations, what work it covers and when any private protection can be released.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landConfirm access and handback in the private agreements
Compare the proposed surrender or release with the signed leases, easements and amendments. Identify any continuing entry, maintenance or restoration rights and who can exercise them. If part of the site will be returned while a shared road stays open, mark those areas on the agreed exhibit. Ask counsel and the title company what must be signed or recorded and what will document the condition of the land at handback.
Sunland welcomes nationwide inquiries from landowners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the general location, your role and which shared facility affects the transaction. Keep maps, signed agreements and financial assurance records for private review.
Questions landowners ask
Does the certificate show who can cross my property after one project closes?
Check the current certificate, any amendment and the shared-use agreement. Have counsel compare them with your recorded easements and lease to identify who can use the route and for what purpose.
Who files if an Oregon Trail Solar shared facility stays in use?
If Condition 118(c) is triggered, each certificate holder submits an amendment determination request or a request for a site certificate amendment. Ask the Department which filing and conditions apply to the actual facility.
What security should I ask to see?
Ask for evidence of the bond or letter of credit for the operating facility and how it accounts for the full removal cost of the shared facilities under Condition 118(c). Review any separate lease security with counsel.
Sources & further reading
The executed certificate, final order and state project record were checked November 21, 2026. The certificate illustrates what the holders would have to document if the condition is triggered. Local rules and program details can change. Check the requirements for the actual project.