Find the effective certificate and the company named in it
This process applies to projects with an Oregon Energy Facility Siting Council site certificate, including a solar project with storage when both are in that certificate. Search the Oregon Department of Energy's facility list by project name and check any former names and the site map. Ask the Department contact for the transfer request, final order and latest effective certificate. Have the contact confirm whether a temporary amended certificate is in effect if the buyer says it can start before the regular amendment is signed.
OAR 345-027-0400 covers a transaction that changes ownership, possession or control of the facility or its certificate holder. The transferor's certificate duties continue until the Council approves the transfer and issues an amended certificate. The new owner can construct or operate only once an amended or temporary amended certificate is effective. The regular amended certificate takes effect when the Council chair and new owner sign it. Check any separate preconstruction conditions before agreeing to a work date.
The Department sends the transfer notice to property owners on the updated list submitted with the request, as well as other recipients specified in the rule. If a transfer is pending and you expected notice, give the Department the facility name, parcel identification and your contact information. Ask for the notice and comment deadline. Put private lease questions directly to the parties and your adviser.

Put the state and land-agreement dates side by side
In the Morrow County Sunstone Solar Project, the Council's final order records a February 27, 2026 acquisition by Oregon Solar 1, LLC after the previous developer's bankruptcy proceedings. The Council approved the certificate transfer and issued an amended certificate on June 26, 2026. The transfer request proposed no change to the facility design or site boundary. The Department's project record lists Oregon Solar 1, LLC as certificate holder. Those records show two distinct milestones for the project.
Make a short record with the project acquisition date, when the amended certificate took effect, when the private assignment or other contract change takes effect, and the first agreed date for access or work. If the company named in the certificate differs from the company on your agreement or the entity sending a rent notice, ask for their full legal names and which company holds the parcel rights, pays you and responds to notices. Check the parcel exhibit and the existing authority for each requested activity, including entry on retained land.
Ask counsel to review the original option, lease and easements, later amendments, the proposed assignment and assumption, and any guaranty or court order relevant to the transaction. Confirm whether consent or notice is required, whether the outgoing company remains responsible under your contract, and which party will cure any open payment or restoration obligation. Use the contact information you already have to verify new payment or notice instructions independently.
Check the financial assurance that applies to your parcel
In Sunstone's transfer order, the Council found the successor reasonably likely to obtain the required retirement assurance. The amended certificate's PRE-RF-01 condition calls for an actual bond or letter of credit before construction of the facility or applicable phase and names the State of Oregon as beneficiary or payee. Ask the Department which condition applies to your phase and what has been filed. Have counsel review any separate lease guaranty, removal security or restoration promise, including whose benefit it serves and how you could enforce it.
If the successor asks you to acknowledge the transfer or sign an estoppel, match the document to the actual rent, deposits, deadlines, outstanding notices and restoration obligations. Ask your adviser which items you can confirm now and which need the buyer's signature or more evidence before you sign. If you would consider a sale, lease or assignment of an existing project agreement, share the parcel's general location, your role and the next deadline with Sunland. Inquiries are open nationwide. Keep signed agreements and financial records private until requested.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landQuestions landowners ask
Where can I verify the Oregon certificate holder?
Find the project and the Department contact in the Oregon Department of Energy's facility records. Request the latest effective site certificate, any temporary instrument and the transfer order. Use the effective certificate and your signed land agreement to verify each company's role.
Does a project purchase mean the buyer can begin construction?
Under OAR 345-027-0400, a new owner must wait for an amended or temporary amended certificate to become effective before constructing or operating the facility. Check any preconstruction conditions and the access rights and dates in your agreement as well.
Whom should I ask about rent after a transfer?
Ask the current and incoming contract parties to confirm who owes accrued and future rent, where notices go, and when any assignment takes effect. Have your adviser reconcile that answer with the signed agreement, amendments and any guaranty.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.
- Oregon Secretary of State, OAR 345-027-0400 site certificate transfer rule
- Oregon Energy Facility Siting Council, Sunstone Solar transfer final order and amended site certificate
- Oregon Department of Energy, Sunstone Solar Project facility record
- Oregon Department of Energy, facilities under the Energy Facility Siting Council