Retrieve the existing federal record
This guide is for an owner of an existing solar small-power-production QF or an authorized representative considering a sale. Ask for the QF docket number, latest Form 556, amendments or recertifications and any Commission orders. FERC’s QF page explains how to find electronic filings. Compare the record with current project facts before assuming it describes the facility today.
If a previous change appears missing, bring the record and transaction history to qualified energy counsel before relying on the existing certification. Do not assume a new filing automatically resolves an earlier mismatch. The parties can identify the person who will obtain records and provide them securely to the buyer and advisers.

Map what the transaction changes
Distinguish a sale of land subject to a lease from a sale of generating equipment, project-company equity, or an upstream ownership interest. Draw a before-and-after ownership chart and identify the legal entities, interests and other facility facts reported in the current filing. A passive landowner receiving rent is not necessarily the facility owner or the person responsible for a QF filing.
Ask counsel to compare the proposed changes with the reported facts and review materiality and continuing QF eligibility, including relevant affiliations. FERC’s FAQ discusses its treatment of certain ownership changes; other material facts still need review. A private agreement’s label alone does not settle the federal question.
Check the filing exemption
Under 18 CFR 292.203, a facility with net power production capacity of 1 MW or less is exempt from the filing requirement. FERC’s FAQ says such a facility need not recertify even if it previously filed. Confirm the facility’s net power production capacity and the applicable facts with counsel; advertised panel DC capacity is not a substitute for that determination.
The filing exemption does not erase the substantive criteria for QF status or resolve every utility or contract obligation. For a facility outside the exemption, counsel can assess whether a material change requires recertification and which available route applies.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCoordinate the filing with the change
If recertification is required, agree who will prepare and authorize it, what information each party must supply, and how the filing will be coordinated with the actual change and closing. Do not treat the filing as unspecified post-closing housekeeping. If the facts on which a certification was based materially differ from the facility, the prior certification cannot be relied upon under the regulation.
FERC provides self-recertification and Commission recertification routes. A self-recertification is effective upon filing, but that is not a Commission merits approval or a guarantee against a protest or later review. Ask counsel to confirm the appropriate route and monitor the docket.
Serve and retain the evidence
Assign someone to concurrently serve a copy on each electric utility with which the facility expects to interconnect, transmit or sell electricity, or from which it expects to purchase supplementary, standby, backup or maintenance power. Also serve the state regulatory authorities in the states where the facility and each affected utility are located. Confirm the applicable recipients under 18 CFR 292.207(e) and preserve evidence of service.
Keep the submitted Form 556, docket and filing confirmation, service list and delivery evidence with the closing records. Agree who will provide copies to each party and follow up on any issue in the docket. FERC notes that it does not ordinarily issue a separate document for a self-certification, so retain the electronic record.
Keep other approvals on the closing checklist
Review the power purchase agreement, interconnection arrangements, incentives, permits, land lease and financing separately for notices, assignments or consents. A QF filing does not itself transfer those rights or establish utility, agency or private-party approval. Counsel can help allocate outstanding conditions and cooperation in the sale documents.
Sunland welcomes nationwide inquiries from owners and authorized representatives about solar land sales, leases and existing agreements. Share the location, approximate acreage and the interest being considered; provide sensitive agreements and ownership documents privately through an appropriate secure channel. An inquiry does not determine the legal effect of a particular transaction or submit a FERC filing.
Questions landowners ask
Does every solar land sale require Form 556 recertification?
No. Establish whether there is an existing QF, who owns the facility and what facts the transaction changes. A land-only sale is distinct from a facility or ownership-interest transfer.
Must a facility at or below 1 MW file again because it filed before?
FERC says a facility with net power production capacity of 1 MW or less need not recertify even if it previously filed. Confirm the capacity measure and eligibility for the exemption.
Does filing transfer the power purchase agreement?
No. Review the agreement and its notice and consent requirements separately, along with interconnection, incentive and other obligations.
Is self-recertification approval of the project?
Self-recertification is effective upon filing; it is not a Commission merits approval or a guarantee against protest or later review.
Sources & further reading
Federal regulations and FERC guidance checked November 19, 2026. No individual facility record or transaction documents were reviewed. Local rules and program details can change. Check the requirements for the actual project.