Virginia landowner guide

What should I check before taking back part of a Page County solar site?

If the operator plans to return part of your utility-scale solar site in Page County, Virginia, match the acres offered back to the County-approved decommissioning plan and your signed lease map. For a project using escrow under Page County Code § 134-8(J)(3), the County may approve a partial release as portions of the approved plan are performed. Ask for the County’s written consent, the amount it authorizes for release and the security left for the rest of the work before agreeing to take back the land.

Could my land work?

Ask the County Administrator’s office or designee which portion of the approved plan the County considers complete and whether it has given written consent to release any escrow funds. Then review the proposed handback under your lease and easements, including the date you can resume farming or other use and who will repair damage from work that continues elsewhere on the site.

Confirm the approval and escrow that govern your project

Request the special use permit, the approved decommissioning plan and its amendments, the application date and acceptance record, and the executed decommissioning security. Section 134-8 addresses industrial and utility-scale facilities. Virginia Code § 15.2-2241.2 requires a written decommissioning agreement and financial assurance to the locality for projects subject to that statute. Ask the County which local requirements and instrument govern the proposed release.

Virginia’s 2026 solar legislation applies to ground-mounted facilities of at least one megawatt with local approval applications filed on or after July 1, 2026, and displaces inconsistent local ordinances for those projects. Applications received and accepted before that date remain subject to applicable local ordinances in place at initial filing. Use the partial-release steps below when the County confirms that § 134-8(J)(3) governs the project’s escrow.

Illustration of a land parcel and surrounding landscape

Match the area offered back to the approved work

When decommissioning is triggered for part of a facility, § 134-8(O) requires work on that portion to follow the approved plan and the section. Ask the operator to mark the affected fields, equipment and access routes on the same map. Walk the area with the map and request any available completion records or inspection findings. Check the applicable removal and restoration work under § 134-8(K), including roads, buried equipment, grading and revegetation.

If you want to keep an access road as a farm lane, mark its exact limits. Section 134-8(K) requires a written landowner request and Board of Supervisors approval for an exception to site restoration. If the proposed work changes the plan, ask for the Board-approved amendment under § 134-8(M). Compare the approved limits with the handback sketch before signing.

Check the written consent and the remaining security

The escrow agreement must require written County consent before funds are released. Section 134-8(J)(3) calls for consent upon compliance with the approved plan and leaves partial release to the County’s discretion. Ask for the consent covering this stage, the remaining balance and a cost breakdown for the work still due. For example, if one of four fields comes back, removing the substation, access roads and equipment elsewhere may still account for much of the remaining cost.

If the County approved a bond, letter of credit or other alternative under § 134-8(J)(6), ask for that instrument and the County’s written direction on its release conditions. For escrow, check the agreement and release instructions to see who receives the funds authorized for release.

Record to requestWhat to confirm
Approved plan, changes and map of the area offered backThe exact acreage and the removal and restoration work due there.
Completion records and any County inspection findingsThe work performed and any items still open in that area.
Executed escrow agreement, release request and written County consentThe amount authorized for release, the balance and the work it still secures.
Signed lease, easements and proposed handbackThe date you can use the land, access that continues and who pays for remaining work or damage.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Decide what you can accept under the lease

Review the proposed handback with counsel. Have it identify the acreage, the date you regain possession, access the operator still needs, and who will finish any open work or repair later damage. If crews will cross the returned field to reach active equipment, check the route, duration and repair obligations against the easement and lease. Ask counsel to check the County’s default-access instrument under § 134-8(I)(3) as well. Resolve which rights and claims the proposed signature would release before you sign.

Owners and authorized representatives anywhere in the United States can contact Sunland about a solar property sale, lease or existing agreement. Start with the general property location, your role, the type of agreement and whether the project proposes returning part of the land. Keep detailed maps and signed documents for private follow-up.

Questions landowners ask

Can the County release escrow while part of the project remains in place?

For escrow governed by § 134-8(J)(3), the County may approve partial release as portions of the approved plan are performed. Request the written consent for the particular release and verify the balance and the work still covered.

What if the lease requires repairs that the County release does not address?

List the open repairs against the signed lease and the map, then have counsel check whether the handback preserves the repair obligation and any remedies. Agree on who can enter to do the work, when it is due and how you will confirm completion.

Sources & further reading

The Page County Code, adoption record and Virginia law were checked November 22, 2026. Confirm the applicable requirements, approved plan and current security with the County for your project. Local rules and program details can change. Check the requirements for the actual project.