Check the facility and the agreement date first
Chapter 43 excludes facilities with a nameplate capacity of 2 megawatts AC or less, customer-generators as defined in Pennsylvania law, and an owner or operator of a normal agricultural operation who owns and operates a solar facility on that operation’s premises. A lease to a separate solar company on farmland does not by itself establish the agricultural exclusion. Obtain the proposed AC nameplate capacity and the identities and roles of the landowner, facility owner and operator; ask counsel to apply the definitions to the actual structure.
Section 4302 addresses solar facility agreements executed after its effective date; section 4303(a), on proof of financial assurance, addresses a grantee executing an agreement on or after that subsection’s effective date. Most of the chapter takes effect January 16, 2027. An agreement signed on that date calls for particular care because the two provisions use different wording. Do not assume these provisions automatically apply to a lease signed earlier, or that changing an older lease has a particular effect without legal review. Existing contract terms and applicable local requirements still warrant review.

Understand the staged security and its gap
For an agreement subject to section 4303, the facility owner, called the grantee, must provide a plan and proof of assurance to the county recorder of deeds and notify the surface owner. The law calls for an estimate updated every five years by a third-party professional engineer retained by the grantee from a DEP-compiled list. Construction begins for this schedule when the grantee issues a full notice to proceed to the construction contractor, not necessarily when equipment first arrives.
At least 30 days before that notice, proof must equal 10% of the estimated cost; by the fifth anniversary it is again 10% of the then-estimated cost. By years 10, 15, 20 and 25, the respective amounts are 40%, 60%, 80% and 100% of the estimate less salvage value, subject to floors of 25%, 40%, 60% and 70% of total estimated cost. Statutory salvage is limited to salvageable steel, aluminum and copper. Each anniversary is measured from commencement of construction, and updated plans and proof are due on or before the relevant anniversary.
For example, if the initial estimate is $1 million, the initial statutory amount is $100,000, leaving a substantial potential gap if the project fails early. At year 10, if the updated estimate remains $1 million and eligible salvage is $200,000, the calculation is $400,000 less $200,000, but the $250,000 floor applies. This illustrates the formula, not a project estimate. Ask who funds any shortfall, including costs above an estimate and costs a security instrument does not pay; negotiate additional or earlier security where appropriate.
Inspect the actual instrument, not only the filing
Ask for the engineer’s scope and cost breakdown, salvage assumptions, plan, filed proof and the executed assurance instrument. Section 4303 permits specified forms including escrow, qualifying certificates of deposit or automatically renewable irrevocable letters of credit, licensed surety bonds and certain government bonds. Review the specific issuer, amount, beneficiary, expiration, renewal, replacement, cancellation notice and conditions for a draw with counsel. The statute says assurance is payable to the surface owner if the grantee fails to decommission; check how the instrument makes that workable in practice.
A recorded proof is useful evidence but does not alone establish that funds are available when needed. Agree on delivery of updates, proof of continued coverage and notice of nonrenewal or cancellation, and on remedies and replacement before a lapse. Check the recorder’s records and retain the documents privately with the lease. Ask DEP and the recorder about current regulations, the engineer list, forms and filing procedure; section 4304 directs DEP to develop a provisional standard form and later a final one, but availability should be verified before relying on any form.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAgree on the restoration result
Section 4304 requires specified plan provisions unless the surface owner and grantee mutually agree in writing to an alternative restoration condition. These include removal of non-utility-owned equipment, conduits, structures, fencing and foundations to at least three feet below grade, subject to equipment and materials a public utility requires to remain; removal of gravel areas and access roads unless the owner requests in writing that they remain; restoration reasonably similar to the preconstruction condition, including replacement of removed or eroded topsoil on previously productive agricultural land; and reseeding cleared areas unless the owner requests in writing otherwise because of agricultural planting plans.
Document the baseline with dated photos, soil and drainage information and a map of roads, buried lines and foundations. If a farm lane would be useful after removal, identify it precisely in a written agreement and settle its condition and maintenance; do not rely on a verbal promise to leave all roads. Consider drainage repairs, compaction, weeds, access, verification of completion and items below the statutory removal depth. Have counsel and an engineer compare those choices with the estimate and security.
Plan for an idle site and a change in ownership
For an agreement subject to section 4302, the lease must provide for decommissioning no later than 18 months after production ceases, except when the grantee is actively working to recommence production, including after force majeure or a similar event. Discuss how the owner will receive information about an idle facility, what evidence of active work will be provided and what the lease says about access, maintenance and delays. Have counsel assess any proposed lease terms against the statute.
Before consenting to a project transfer, request the proposed successor’s identity, assumption of obligations, current plan, updated estimate and replacement security. Under section 4303(e), the plan, associated assurance and salvage value used to reduce assurance cannot be separated from the facility through a change in grantee ownership. The new grantee must submit proof; the prior grantee may not release or revoke its assurance until the new proof is filed with the county recorder and notice is provided to the surface owner. Confirm both events and inspect the replacement instrument; a sale agreement alone is not proof of funded, usable security. Discuss any security shortfall and lease consent rights with counsel.
Collect records before deciding
Gather the proposed lease and amendments with execution dates, capacity and ownership information, construction notice and schedule, site plan and baseline, engineer’s estimate and salvage calculation, assurance instrument, recorder submissions, local approvals and any written restoration choices. Ask the municipality and counsel which local requirements apply: the chapter preempts local ordinances or regulations that materially impede its purposes, not necessarily every local rule.
Sunland welcomes nationwide inquiries about selling or leasing land and existing agreements. Share the location, acreage, project stage and decision you face; provide sensitive agreements privately when appropriate. Sunland may contract for an opportunity and assign it to a specialist, subject to the actual agreement. Pennsylvania counsel and an independent engineer can advise on the lease and the particular site.
Questions landowners ask
Does the law require full removal funding before construction?
No. Section 4303 begins with proof equal to 10% of estimated cost at least 30 days before commencement and stages later amounts, with salvage deductions and floors. Negotiate how a shortfall would be covered.
Does the law apply to every solar lease on farmland?
No. Check the capacity, statutory exclusions, facility ownership and operation, and the agreement’s execution date. Farmland alone does not establish the specific normal agricultural operation exclusion.
Can the old project owner cancel its security as soon as it sells?
For a transfer governed by section 4303(e), the prior grantee may not release or revoke its assurance until the new proof is filed with the county recorder and notice is given to the surface owner. Review the replacement instrument and the lease as well.
Must all access roads be removed?
The plan provisions call for removal of gravel areas and roads unless the surface owner requests in writing that they stay, subject to the statute’s provision for a mutually agreed written alternative restoration condition. Describe any retained road and its condition clearly.
Sources & further reading
Chapter 43 and Act 44 were checked November 18, 2026. Most chapter provisions take effect January 16, 2027; section 4304 was immediate. Check current DEP implementation and project-specific applicability before signing. Local rules and program details can change. Check the requirements for the actual project.