Find the approved plan and mark the road you want to keep
Give the Township Zoning Administrator the project name and parcel number. Ask for the approval and its conditions, the dated site plan and the latest approved decommissioning plan. Section 713 applies to stand-alone battery storage and storage paired with another use under Reno Township’s zoning ordinance. Michigan Public Act 233 also provides a state siting route under specified conditions for qualifying storage projects. If that route applies, ask for the Michigan Public Service Commission docket and any certificate and conditions governing removal.
The local site plan must show temporary and permanent access drives under § 713.M.1(h). Section 713.H calls for removing the geotextile and gravel used for temporary construction roads once the system is operating. Identify the permanent segment by plan sheet, revision date and endpoints. If only the stretch from the driveway entrance to a field gate would serve your farm, mark where the retained section ends and where the operator would remove the rest.

Put the retention request and road condition in writing
Section 713.N.3 generally requires the battery system owner to remove, clear and grade the access roads unless the property owner requests retention in writing. Section 713.H also describes a Planning Commission determination that a drive should remain. Ask the Township Zoning Administrator how the two provisions apply to your segment, who should receive the request and when it should arrive. Raise the request before removal crews are scheduled. If the plan needs an amendment, § 713.N.5(h) provides for Planning Commission approval. Keep a copy of the request, proof of delivery and the applicable approved plan or decision.
Section 713.M.2(a) calls for the decommissioning plan to describe which improvements will be removed, retained or restored. Use the lease restoration exhibit to specify the surface and drainage you expect at handback and who will maintain the road and culverts afterward. If reaching the retained segment depends on crossing another parcel, have counsel check whether the needed easement will survive decommissioning. Township ownership requires official Township Board action under § 713.N.3. If anyone proposes that the township take over the road, ask the clerk for the Board record.
Get the recorded map of any foundations that remain
Under § 713.N.2, foundations must be removed to a depth of at least 60 inches below grade, or down to bedrock where it is shallower. After removal, the location of any remaining foundation must be mapped and recorded with the deed at the County Register of Deeds. Ask the project company to supply the final map showing what remains, identify the affected deed and give you the recording reference. In the lease, agree who will prepare and submit the map and when you will receive the recorded copy.
Use the Iosco County Register of Deeds’ document search to check the reference and keep the recorded copy in the property file. If you sell, give the buyer the recorded map and the road and easement records. When planning a new use that requires excavation, give the map to the surveyor or engineer and ask what field checks are needed to locate the remnants.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss battery storage land or an existing agreement
Sunland America welcomes inquiries nationwide from owners and authorized representatives considering a battery storage land sale, lease or assignment of an existing agreement. Share the general location, your role and the transaction you are considering. Keep signed agreements, detailed maps and title records private during initial contact.
Questions landowners ask
When should I ask to keep the road?
Ask the township while the removal plan can still be coordinated with the project company. Section 713.N.3 requires a written request from the property owner. Confirm the submission timing and any approval steps for your project.
What if the current plan shows the whole road being removed?
Mark the part you want to keep and ask the Township Zoning Administrator whether the Planning Commission needs to approve a revised decommissioning plan. Get the plan or decision that covers the segment before authorizing a change under the lease.
Where can I find the map if the land changes hands?
Ask the project company or seller for the recorded copy and its reference, then use the Iosco County Register of Deeds’ document search to find the recorded document.
Sources & further reading
Checked November 22, 2026 against the adopted Reno Township zoning ordinance, effective January 24, 2024, and current township, county and state resources. Confirm the controlling approval and recorded documents for your property. Local rules and program details can change. Check the requirements for the actual project.
- Reno Township, adopted zoning ordinance index
- Reno Township Zoning Ordinance, § 713.A, H, M.1(h), M.2 and N.2–5, printed pp. 7-30 to 7-38
- Northeast Michigan Council of Governments, zoning ordinance index
- Reno Township Clerk, township and Planning Commission records
- Iosco County Register of Deeds, recorded document search
- Michigan Public Service Commission, renewable energy and storage facility siting