Identify the unit and its associated property interests
Michigan law requires an instrument affecting title to a condominium unit to identify the unit number and subdivision plan caption and include the master deed’s county book and page reference. Saline Township’s November 2026 notice identifies Washtenaw County Condominium Subdivision Plan No. 761 and reports that the master deed was recorded April 23, 2026, in Liber 5626, Page 678.
Get the recorded master deed, amendments, bylaws, plan and current title commitment before settling the description. Subject to express statutory exceptions, Michigan generally keeps a unit’s allocated undivided interest in common elements with the unit. Ask counsel to confirm the common interests and any separate recorded rights the buyer would receive.

List the judgment obligations and who would take them on
The Saline consent judgment says its terms bind successors, assigns and transferees. It permits the plaintiffs to assign some or all rights and obligations under the judgment, with assignees bound by its terms. Ask counsel to compare your proposed deed and any assignment and identify which duties would pass and which would remain with the seller.
The judgment directs its own recording and says it runs with the land. It also provides that a tenant or condominium association is liable for the developer’s financial, construction or demolition obligations under the judgment only if that tenant or association expressly assumes them in writing. Review any actual assumption alongside the lease, condominium documents and current court and title records.
Check how a proposed change would be reviewed
The Saline judgment provides for township attorney review of the proposed master deed, bylaws and subdivision plan. It ties changes to consistency with the applicable site plan, judgment and township codes, and calls for further revisions before recording to go to the township attorney for review and comment.
If a buyer asks for a different unit boundary or additional shared rights, have counsel identify which recorded documents, approvals or court terms would need to change. Give the closing team the final description and a list of the deeds, assignments, consents and written assumptions it should receive or record.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a sale or transfer involving a condominium unit
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the interest you may transfer and the next decision date. Keep the title documents and private agreements for follow-up.
Questions landowners ask
Which recording reference belongs in the unit deed?
Identify the unit and subdivision plan caption and use the recorded master deed’s county book and page reference. Ask title counsel to confirm the current description and any amendments.
What should I check if the buyer expects the tenant or association to take over construction duties?
Review the actual agreement and any written assumption. In Saline, the consent judgment expressly limits tenant or association liability for specified developer obligations unless that party assumes them in writing.
Sources & further reading
Sources checked November 20, 2026. The township notice identifies the master deed’s recording reference. The complete recorded master deed and any later amendments were unavailable for review. Local rules and program details can change. Check the requirements for the actual project.
- Court-signed Saline consent judgment, paragraphs 11 and 22–24
- Saline Township November 2026 public notice and condominium unit descriptions in Exhibit B
- Michigan Condominium Act, Section 559.164, unit conveyance and description
- Michigan Condominium Act, Section 559.137, common-element interests
- Washtenaw County Register of Deeds, current land records access