California landowner guide

What should I check before battery storage expansion on my Solano County land?

If a battery storage operator wants to add equipment on your Solano County land, ask for the initial approved capacity, the approved site plan and written confirmation of the permit the added work requires. Compare the work area and access dates with the signed lease before agreeing to a change.

Could my land work?

Solano County Code §28.83(J)(5) uses the system’s initial nameplate capacity when setting approval thresholds for augmentation. For covered facilities, augmentation greater than 10% of initial nameplate capacity requires a use permit amendment subject to Planning Commission approval, and augmentation greater than 20% requires a new use permit application. Reused modules have a separate plan requirement. At an operating facility, the owner must give the County at least 90 days’ notice before onsite augmentation and provide an updated site plan. Ask the County which requirements apply to the actual project and which approvals are in hand.

Start with the approved plan and the original capacity

Section 28.83 applies to front-of-the-meter systems in unincorporated Solano County with at least 1,000 kilowatt-hours of rated nameplate capacity. The section excludes the specified behind-the-meter systems. Ask the Department of Resource Management which permitting process applies to your site and whether the County issued the controlling permit.

An initial site plan application can include an augmentation plan for maintaining or modestly increasing capacity. Request the approved drawings, the permit conditions, the initial nameplate rating and any approved augmentation plan. Ask the project team to show the proposed augmentation as a share of initial nameplate capacity and to identify any work already covered by the approved plan.

Illustration of a land parcel and surrounding landscape

Confirm the approval path and the start date

Ask the County to confirm the calculation it will use, especially where the site has changed before or work is proposed in phases. Have the operator supply the amendment, new application or written county determination that applies. Ask what the existing permit allows even if the proposal falls at or below the 10% threshold.

If the work uses reused battery modules, the code requires submission of an augmentation plan and approval by the Director of Resource Management with concurrence from the Office of Emergency Services. For an operating facility, request the dated 90-day notice and updated site plan. Ask the County whether any permit decision or other approval is still outstanding.

Put the new work on the lease map

Overlay the planned equipment, construction access and temporary staging on the signed lease exhibit. If trucks or staging would use acreage you kept, ask the operator for a marked plan showing dates, limits, and how it will restore the land. Have counsel check which access rights the current lease grants and what needs written agreement.

If a project transfer or lease assignment comes with added equipment, ask who will obtain required approvals and supply the records. Agree when the operator can start work and who pays for any additional land use before you sign an amendment.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Describe the proposed change when you inquire

Sunland reviews battery storage property sales, leases and potential assignments of existing agreements nationwide. Share the general location, your role and whether work is proposed on an operating site. Keep signed agreements and detailed project drawings for private review.

Questions landowners ask

What capacity should I compare against the proposal?

Start with the system’s initial nameplate capacity and the initial approved plans. Ask the County to confirm its calculation if earlier work or multiple phases affect the proposal.

Is a notice enough to start augmentation?

For an operating facility, ask for the dated notice and updated site plan, and confirm with the County whether the work also needs a permit decision or reused-module approval. Review site access separately under the private agreement.

What does the updated site plan help me check?

Compare the new equipment and work area with the lease exhibit to identify any staging, roads or other work that affects land outside the existing project area.

Sources & further reading

Solano County’s current code and November 2025 adoption record were checked November 21, 2026 Pacific time. Confirm the initial nameplate figure, approval history and exact requirements for the proposed work with the County. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in California?Tell us about your land