What should you check before consenting to a solar sale with a pending BLM crossing?

A solar developer asks you to consent to a project sale or transfer of your land agreement. A road or electrical line for the project needs a right-of-way from the Bureau of Land Management (BLM). Before deciding, find out whether BLM has issued the grant and which company would hold or pursue it after the sale.

The short answer

Ask for the BLM case number, route map and current application or issued grant. For a pending noncompetitive application, the applicant can continue pursuing it if the same entity becomes a wholly owned subsidiary of the buyer. An assignment of an issued grant requires BLM’s written approval. Confirm the case status and transaction with the field office before relying on either route in a private consent.

Check the federal case and the route it covers

Request the latest BLM correspondence, the application or issued grant, and all current route exhibits. Match the case number, applicant or holder, and authorized or requested use to the road or line the project needs. Compare the federal segment with the adjoining private parcels and access rights shown in your agreement.

Ask the BLM field office to confirm the case status in writing. If a developer gives you a filed application, ask whether the agency has issued a grant and for any conditions or further authorizations affecting the proposed work. If the layout has changed, ask which version of the route the agency is reviewing or has authorized.

Illustration of a land parcel and surrounding landscape

Find out which company stays in the case

Under 43 CFR §2807.21(g), an ordinary noncompetitive pending application creates no property rights or other interest, and the applicant cannot assign it to another entity. The same applicant may continue pursuing its pending application if it becomes a wholly owned subsidiary of a new third party. Ask counsel and the field office to confirm which entity would remain the applicant and whether the transaction requires any updated information.

For example, a buyer might acquire all of the project company that filed the application and keep that company in place. If the buyer instead asks to put the pending application in a different company’s name, ask BLM what that company would need to file. In either case, ask what must happen before the agency can issue a grant and what date is supported by the case record.

If BLM has issued the grant, look for written assignment approval

If the deal assigns an issued grant, §2807.21 calls for an application from the proposed assignee, documentation that the current holder agrees and a signed statement that the assignee will be bound by the grant terms and applicable law. Any outstanding payments due from the current holder must be made before BLM approves the assignment.

BLM recognizes the assignment upon written approval. Ask for the signed grant and amendments, the assigned rights and route, and the written approval when available. If the issued grant stays in the existing company, ask BLM whether the proposed ownership change itself requires approval or another filing.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Use the federal status when reviewing your consent

Have counsel compare the proposed transaction with your signed option, lease or easement and its assignment, change-of-control and notice terms. Check which company can request entry, make payments or give notices. If a deadline in the private agreement depends on the federal crossing, identify whether the parties agreed to use a filing, an issued grant or a written assignment approval as evidence.

Sunland welcomes nationwide inquiries from landowners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the general location, your role and the next agreement date. Keep the signed agreement and detailed route maps for private review.

Questions landowners ask

Can the original company keep pursuing an ordinary pending BLM application after a sale?

Section 2807.21(g) allows the same applicant to continue pursuing the application if it becomes a wholly owned subsidiary of a new third party. Confirm the applicant and case status with BLM.

What shows the assignment of an issued BLM grant has taken effect?

Request BLM’s written approval of the assignment and match it to the issued grant, the parties and the rights being transferred.

What should I check if my agreement calls for consent before closing?

Ask counsel which consent the agreement requires, what event and proof trigger it, and what rights the buyer will have under the private documents. Verify the federal case status separately.

Sources & further reading

The federal rule was checked November 21, 2026. Confirm the actual grant or application status and transaction with the BLM field office. Local rules and program details can change. Check the requirements for the actual project.