Identify the grower and the land at risk
The landowner may be negotiating the solar lease while a tenant owns the standing crop and holds the policy. A crop-share owner may have a separate insured interest. Identify each grower and policyholder, their shares, the farm lease and harvest rights, and who can authorize access. Obtain the crop, field and unit information from the policyholder with their permission; the solar lease alone does not establish their insurance rights.
Overlay the construction plan on the planted fields. Include survey crews, temporary roads, laydown areas, fencing, cable trenches and drainage work as well as panel sites. Mark entry dates and routes and distinguish a proposed start date from an enforceable right to enter. Consider a harvest-first schedule and a written standstill on affected acreage while the parties resolve insurance and crop compensation.

Contact the insurance provider before changing the crop
The Common Crop Insurance Policy (CCIP) Basic Provisions require the policyholder to obtain the AIP’s consent before destroying unharvested insured crop, putting the crop to an alternative use, putting acreage to another use or abandoning any portion of the crop, and to notify the provider afterward. The provisions say the provider will not consent if replanting is practical or until it has appraised potential production. Failure to obtain consent results in production or value assigned to count under the applicable crop provisions, which can affect a claim.
The policyholder should give the agent and AIP the proposed map, dates and activities, and ask whether an inspection, appraisal, representative samples or written release is required. Preserve the crop and follow the provider’s instructions until the required consent is documented. If damage or a loss is discovered, report it promptly under the applicable policy; notice and consent are separate steps. RMA’s general claims guidance describes a 72-hour notice period, subject to the individual crop policy. Do not assume a call to the landowner or developer is notice to the AIP.
Separate insurance from construction compensation
Federal crop insurance covers specified risks and policy terms govern any claim. A planned construction entry is not automatically an insured cause of loss, and consent to change acreage does not turn construction damage into a covered loss or guarantee an indemnity. Ask the AIP how it will treat the particular facts, any production counted and the effect on a claim or future records. Do not rely on an estimated insurance payment to establish the developer’s payment.
Have the owner, grower and developer document who bears crop loss, delayed harvest, access disruption and any associated costs. Specify how acreage and crop value will be measured, who pays and when, and how disputes will be resolved. Preserve dated field photos, maps, yields, invoices and correspondence. An agreement to compensate the grower is separate from insurance consent and any rights under the farm lease.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck the actual crop year and policy version
Ask the policyholder and agent for the applicable Basic Provisions, crop and special provisions, endorsements, acreage report and relevant notices. Not every crop insurance product uses CCIP, and crop-specific terms can change the result. RMA lists 26-BR and newer 27-BR and 27.1-BR versions; the applicable version depends on the crop year and contract change date, not just the calendar year of construction.
For example, RMA says the July 2026 changes including 27.1-BR begin in the 2027 crop year for crops with a June 30, 2026 contract change date and in 2028 for crops with an earlier date. Other releases have different effective-date rules. Ask the agent to identify the version in force for this crop and field and any special or emergency provisions, rather than assuming the newest document applies.
Make the entry schedule workable
Put the agreed harvest deadline, access routes, notice to the grower, insurance steps, payment terms and any release conditions into the project documents before entry. Provide a process for weather delays and changes to the construction footprint. If the developer needs an earlier start, allow time for the AIP’s appraisal and decision; neither a private deadline nor a restoration promise substitutes for required consent.
Sunland welcomes solar land sale, lease and existing project inquiries nationwide. Share the approximate acreage, location and proposed timing. Keep insurance numbers and financial records private until needed for a secure review.
Questions landowners ask
Can the landlord authorize construction over a tenant’s insured crop?
The landowner’s authority depends on the farm lease and other rights. The tenant policyholder should contact the AIP before crop destruction or another use of insured acreage, and the parties should resolve compensation and access separately.
Does insurance pay for a crop removed for solar construction?
Do not assume so. Coverage depends on the insured cause of loss and policy terms. AIP consent to change the acreage is not a guarantee of payment; address construction compensation separately.
Which Basic Provisions apply?
The applicable policy depends on the crop, crop year and contract change date. Ask the agent for the actual policy and endorsements; the newest RMA version does not necessarily govern every crop in that year.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.