Can solar construction restart after a lender waiver?

A solar developer says its lender has waived a permit-related default and asks you to confirm a new construction date or give contractors access. Before responding, get the proposed work and its location in writing. You will need the financing waiver, the agency’s authorization and the agreement that governs use of your land.

The short answer

Ask which financing default was waived and whether any conditions remain open. Confirm with the permitting office that the current issued documents authorize the specific work and phase on your land. Have counsel compare those records with the signed option, lease or easement before you acknowledge a restart date, consent to access or sign a release.

Find out what the lender waived

Ask for the signed waiver or a written confirmation identifying who granted it, which events it covers, when it takes effect and what the developer still has to deliver. A financing party can waive specified defaults under a loan agreement. Work authorization comes from the permitting agency and the applicable land documents.

In Kern County, California, the May 2025 Pelicans Jaw solar project financing amendment says a contractor began limited construction before obtaining the necessary photovoltaic building permit. The administrative agent, with lender consent, agreed to waive specified financing defaults arising from the permit issue, a loan borrowing representation and the timing of notice to the agent. The amendment preserves financing rights and obligations beyond the matters it expressly addresses.

The amended Pelicans Jaw financing agreement also required the borrower to deliver the issued county permit and written confirmation from the independent engineer about the construction schedule, budget and expected completion. Delivery was due to the administrative agent within 30 days after the tax-equity documentation effective date defined in that deal. That clause gives the borrower a financing deadline. Check the issued permit itself for the date and scope of public authorization.

Illustration of a land parcel and surrounding landscape

Verify what the agency has authorized

Request the issued permit, approved plans and conditions for the activity the developer wants to start or resume. Compare the permit number, issue date, parcel or project area and phase with the current work plan. A request for access could cover survey work, staging, grading or installation. Ask the issuing office which of those activities its approval covers and whether any additional approval or written clearance applies.

Pelicans Jaw’s final county land-use conditions required the necessary building permits and specified documentation before building or grading permits could be issued. Those included showing compliance with applicable mitigation measures and addressing fire protection and access. A land-use approval and a construction permit answer different questions about when work can proceed. If the developer points to a planning decision, ask the agency which issued document and conditions govern the proposed work.

Check what the signature would change

Read the proposed acknowledgment alongside your executed agreement, amendments and easements. Identify who can enter, where contractors can work and what notices or approvals the agreement requires. If the developer asks to expand a work area or use a different road, compare its revised plan with the rights in the signed exhibits.

Ask counsel whether the requested wording confirms a date, gives new permission, changes rent or releases a claim. If work has already occurred, keep dated records and identify open items such as road damage, drainage repairs or restoration. Check who must correct them and how the agreement treats any delay, notice or cure. Confirm which items must be resolved before the date you are asked to acknowledge.

Sunland welcomes nationwide inquiries about land sales, leases and existing solar agreements. Share the general location, your role and the next decision date. Keep signed agreements and confidential financing records out of the initial inquiry.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Questions landowners ask

What should I ask for if the developer says the permit issue is resolved?

Ask for the current issued permit, the approved plans and any agency correspondence stating what can proceed. Check the scope and any open conditions directly with the issuing office.

Can a lender waiver change my construction rent date?

Check the rent trigger in your signed agreement and whether the proposed acknowledgment would change it. Ask counsel to distinguish the financing deadline, permit date and contractual rent milestone.

Does a building permit give the contractor access to my land?

Check the lease, option or easement for the contractor’s authority, any notice requirements and the activities allowed in each specific area.

Sources & further reading

The executed Pelicans Jaw financing amendment and final Kern County land-use conditions were checked November 20, 2026. The deadlines and conditions in the example apply to that project. Local rules and program details can change. Check the requirements for the actual project.