Confirm which rules apply to the parcel
Give the planning office the parcel identification number and the date of the latest project plan. Ask whether § 6-29-1220 applies and request the adopted text and effective date for any rural zoning or solar design and development ordinance that the county says governs the property. Section 8.B of Act 41 makes the state provision effective for projects approved by a county on or after January 1, 2026. If the developer says the county has already acted, request the dated approval and the plan it covers.
The acreage test concerns the footprint required by the solar energy system. Compare the footprint shown on the site plan with the acreage in your option or lease exhibit. For example, an option on 50 acres could cover a proposed system with an 11-acre footprint. Ask the county what it counts toward the footprint, especially if the layout or acreage is changing.

Request the plan, the hearing notice and the mailing record
Ask the county what it accepted as a completed plan and when it received that version. The fallback calls for a sealed site plan prepared by a land surveyor, landscape architect or engineer licensed in South Carolina. The plan also gives you a way to check the proposed fence and setbacks. The fallback measures 50 feet from adjoining property lines and road rights of way and 200 feet from the nearest residence, church or school to the fence, including the vegetative buffer.
| Record to request | What to check |
|---|---|
| Sealed site plan and county receipt record | The date the county received the completed plan, the plan revision and the footprint the county reviewed. |
| First-class application notice and mailing area | The projected hearing date in the notice and where the county started measuring 2,640 feet from the proposed system. |
| Resident mailing record and local newspaper notice | The postmark for the resident mailing and when and where the newspaper notice appeared. |
| County decision and any conditions | The decision date, the plan revision it covers and any conditions that affect the proposed agreement. |
Check the dates before using them in an option or lease
The developer may have a target date for filing while the county is still waiting for a completed plan. If your agreement uses a county milestone, ask counsel to specify which event counts and what record shows it happened. For example, an option extension could turn on the county receiving the completed plan. A lease condition could instead require a written county approval that identifies the plan and any conditions. Review who supplies the record and what happens to the deadline if the hearing moves or the plan changes.
The county handles its hearing and local decision. Section 6-29-1220(C) assigns enforcement of the state fallback to the South Carolina Department of Environmental Services. The department recommends that developers on covered projects send it documentation of the hearing and notice procedures along with the county approval.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a solar property or existing agreement
Owners and authorized representatives anywhere in the United States can contact Sunland about a solar land sale, lease or existing agreement. Share the general property location, your role and the transaction you are considering. Save detailed plan sets and proposed agreements for private follow-up.
Questions landowners ask
What should I ask for if I get a notice about a neighboring solar project?
Keep the notice and envelope. Use the hearing date and project name to request the sealed plan and ask the county how to submit comments. Check the proposed fence against the shared property line, nearby road right of way and any nearby residence, church or school shown on the plan.
What happens to the notice area if the developer moves the project boundary?
Give the planning office the dates of both plan revisions. Ask which version it used to identify property owners within 2,640 feet of the proposed system and whether it will update the mailing area, notices or hearing date for the revised plan.
Sources & further reading
The statute, enacted bill and agency guidance were checked November 22, 2026. Ask the county which ordinance and review procedure apply to your parcel and plan. Local rules and program details can change. Check the requirements for the actual project.