Identify the holders and their rights
Ask the title company for the recorded easement and amendments, assignments, releases and legal descriptions. Compare them with the signed solar lease or easement and the proposed development map. Confirm the current utility and solar parties, who can approve changes and what right each party already holds. Include access and working areas the documents grant for maintenance and replacement.
SDCL §43-13-20 requires holders of wind or solar easements, wind or solar leases, or essential-service easements to accommodate reasonable development by another holder of one of those rights. Essential services include electric transmission and distribution lines and related facilities, telecommunications facilities and rural water systems. Ask counsel whether the parties hold covered rights, especially if a developer has only proposed an agreement. The statute makes an exception for competing wind or solar developers.

Check the recorded solar easement filing
Section 43-13-17 requires a covered solar easement or memorandum to be recorded and indexed with the county register of deeds. Section 43-13-20.3 also requires a separately filed and recorded document containing information about the easement, including any restrictions on the property for essential services. Ask the title company for both records and the complete easement terms.
Confirm whether the solar instrument is an easement covered by those filing rules. The statute defines a solar easement by the rights it grants, which can include protecting a photovoltaic system’s access to sunlight or agreeing to refrain from developing one. Have counsel compare the actual instrument, its recorded documents and the proposed layout.
Make room for construction and future maintenance
Ask the project team and utility holder to mark their work areas and access on the same drawing. For example, a rural water line may remain outside the panel rows while the fence crosses the route a crew would need to excavate and replace it. Ask about gates, staging space, emergency entry, service interruptions and restoration. Confirm the dimensions with the teams that would do the work.
Use the instruments and design to identify what each holder needs and which changes they can agree to. Ask counsel how the reasonable-development rule applies to those facts. If the teams discuss a reroute or different gate, confirm who can authorize it, how the change affects either set of rights and who would bear the cost under the actual agreements.
| Record to check | Decision to resolve |
|---|---|
| Recorded rights and assignments | Which parties can agree to changes, and which rights already cover this work? |
| Surveyed solar and utility layout | Where will crews enter and work during construction, ordinary service and emergencies? |
| Solar easement filing and recorded restrictions | What essential-service restrictions must be accounted for in the layout and transaction? |
| Proposed sale, lease or assignment | Which signed documents and approvals are needed, and by when? |
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the agreed layout into the transaction documents
If the parties agree how to share the site, have counsel and the title team review the final route and any amendment, access agreement or approval. Specify who handles the work, costs, notice and repair. If an issue remains open when you sell, lease or assign an agreement, document the condition that must be met and what happens if the parties cannot agree.
Sunland welcomes nationwide inquiries from landowners and authorized representatives about solar land sales, leases and assignments of existing solar agreements. Share the approximate location, the proposed transaction and the type of utility right involved. Keep signed agreements, title records and detailed plans for private review.
Questions landowners ask
Does the South Dakota rule give a proposed solar developer access?
The rule applies to qualifying holders. Check what each party has already been granted and which additional rights or approvals the proposed work requires.
How do I find restrictions for essential services?
Ask the title team for the solar easement or recorded memorandum and the separate document required for a covered easement filing. Compare those records with the full agreements and surveyed layout.
Can I require the utility to move its line or pay for a change?
Review the existing grant, the proposed work and any agreed amendment with counsel. The reasonable-development provision does not specify a relocation, a payment amount or which holder pays.
Sources & further reading
South Dakota’s current statutes and the 2017 enactment were checked November 20, 2026. The rural water example is hypothetical. Review the actual grants and applicable law for your property. Local rules and program details can change. Check the requirements for the actual project.