Check whether the agreement is covered
Tennessee Code §66-9-207 addresses leases and easements for facilities generating electricity primarily for use off the premises. The grantee is the party that leases the property or holds the easement under the agreement, and the definition excludes a public utility. Ask for the grantee’s legal name, the facility capacity and the location of the point where it connects to the grid.
Under the law as amended effective July 1, 2024, the size threshold is 5 megawatts AC measured at the grid interconnection point. Parties can expressly apply the law to a smaller installation in the agreement. If you are reviewing an older agreement, an amendment or a project transfer, give Tennessee counsel the original signing date and the later documents and ask what filing steps apply.

Ask for evidence of the state filing and each notice
The grantee files a copy of the agreement with the Office of Energy Programs at the Tennessee Department of Environment and Conservation (TDEC). Under §66-9-207(h), the grantee also tells the county mayor, and the municipal mayor where applicable, that it filed the agreement. Ask the grantee to confirm which jurisdictions apply and to give you the notices and the dates it sent them.
If you are offered a recorded memorandum or local recording receipt, ask for the separate state filing record as well. Compare it with the signed agreement and any exhibits you expect to see in the filing. Have counsel review the timing and documentation you want the grantee to provide under your agreement.
| Record | What to check |
|---|---|
| Signed lease or easement | Grantee’s legal name, signed version, exhibits and any terms on required disclosures. |
| State submission | Copy sent to the Office of Energy Programs, submission date and any acknowledgment available. |
| Local notice of filing | County mayor, municipal mayor if applicable, and copies and dates of the notices. |
Identify information for the state’s confidentiality review
TDEC says information submitted to the office may be subject to public disclosure under state law. Tennessee Code §4-3-514 and the office’s public records rule protect information that qualifies as proprietary. That can include trade secrets or qualifying commercial or financial information. TDEC directs the filer to identify proprietary material in the submission. The agency reviews the material and removes information it determines is proprietary from copies it releases.
Before filing, ask counsel and the grantee to review the exact document and exhibits, identify any material to flag and confirm the office’s submission instructions. Have counsel check how your lease and any separate confidentiality agreement handle disclosures required by law and notice to the parties.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a solar land opportunity
Sunland welcomes inquiries from landowners and authorized representatives across the United States about sales, leases and assignments of existing solar agreements. Share the general location and whether you are reviewing a new agreement or an existing filing. Keep signed agreements, exhibits and notices for private review.
Questions landowners ask
Does the local mayor get a copy of the agreement?
Section 66-9-207(h) requires the grantee to file the copy with the state office and notify the applicable mayors of that filing. Ask the grantee what it sent to each recipient.
Will the state keep my whole lease confidential?
The state reviews the submitted material under its public records rules and protects information that qualifies. Ask the grantee and counsel which material they plan to identify to TDEC and how the office handles it.
What if the grantee already recorded a memorandum locally?
Ask for the state submission record and copies of the mayor notices. Keep the local recording reference with those records so you can verify each step.
Sources & further reading
Tennessee law, the public records rule and the state filing instructions were checked November 21, 2026. Confirm the applicable filing steps and timing with Tennessee counsel and the Office of Energy Programs. Local rules and program details can change. Check the requirements for the actual project.