Texas landowner guide

What does a Municipal Setting Designation mean for Texas battery storage land?

An old industrial yard may have enough space for a battery energy storage system and still have a groundwater restriction that affects the work. An existing Texas Municipal Setting Designation (MSD) matters if trenches might encounter groundwater, the developer expects to pump water during construction, or the plan assumes an existing well can supply the project.

Could my land work?

Get the issued Texas Commission on Environmental Quality (TCEQ) MSD certificate, the city ordinance or recorded restrictive covenant, and any separate cleanup decision for the site. Compare their boundaries and groundwater description with the proposed excavation depths, pumping locations and water sources. Before authorizing intrusive work, ask the project team who will confirm any required permissions, where extracted water can go and what water source the fire authority can accept if one is needed.

Find the state certificate and the local restriction

Search the TCEQ certificate directory by address or project name. Use the issued certificate and its legal description to locate the designated area, then get the adopted ordinance or city-enforceable covenant from the city or the county property records. Ask for all exhibits and later changes. A city vote supporting an application, an entry marked under review, and an issued state certificate represent different steps.

Texas Health and Safety Code sections 361.801 and 361.8065 distinguish potable use from other uses and contact. The statute includes drinking, showering, bathing, cooking and irrigation of crops intended for human consumption in potable use. The ordinance or covenant must prohibit potable use of the designated groundwater and appropriately restrict other uses and contact. Read the local instrument for the exact groundwater and restrictions that apply.

Fort Worth’s Brennan Avenue industrial site illustrates how to match the records. TCEQ lists MSD No. 524 as certified and links the certificate packet. The city council minutes record adoption of Ordinance 26695-01-2024. The ordinance text in the city’s agenda file describes the designated shallow groundwater and prohibits both potable and irrigation uses. Use the ordinance and exhibits for your own tract when interpreting its restrictions.

Illustration of a land parcel and surrounding landscape

Ask for the separate cleanup decision

An MSD can narrow the investigation and response required for the potential use of contaminated groundwater as drinking water. Under section 361.808, TCEQ must still require a responsible person to take action when needed to address exposure from other uses, inadvertent contact or harm to ecological resources. Nearby potable wells and off-site migration may also affect the review. Ask the environmental consultant to locate the agency’s current findings for the site and any remaining conditions.

If the property went through the Voluntary Cleanup Program, ask for the issued cleanup certificate, its attachments and any later agency correspondence. TCEQ publishes an example of a final cleanup certificate that relies on a separate MSD for the groundwater ingestion pathway. A designation by itself gives you no basis to conclude that the soil, proposed excavations or other exposure pathways have been addressed.

Compare excavation depths and water sources

Ask the developer for a plan and excavation depths for foundations, cable trenches, utility crossings and drainage work, including temporary work outside the fenced compound. Ask the environmental consultant to locate the area and groundwater interval described in the restriction, using the site’s water-level and cleanup records. If the pad can stay in place but a trench intersects affected groundwater, ask whether the route or depth can change and what review the alternative would require.

Ask what happens if a trench or foundation excavation fills with water. Identify any restrictions on pumping or contact and who will review the expected water quality, handling and destination before discharge or removal. Texas Local Government Code section 551.005 authorizes municipalities to regulate pumping, extraction or use for MSD purposes. TCEQ’s construction stormwater general permit lists uncontaminated groundwater as an eligible non-stormwater discharge and sets conditions for dewatering discharges. Have the project team confirm the applicable authorization and receiving party for the actual water before relying on any outlet.

Ask separately what water the construction and operating plans would use for dust control, any occupied facilities and any required fire-water supply. If the plan assumes an existing well, identify which groundwater it draws from and what its authorized uses are. Confirm availability with the water provider and acceptance with the local fire authority for any required fire-water source. Public water availability at the time of designation does not establish that the project can obtain a particular connection or water supply.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Tie site access and closing to the water plan

Give the developer the exact area offered and the known restrictions before drafting site-entry rights. Have the agreement identify who obtains records, pays for investigation and any required water handling, and proposes a revised plan if groundwater changes the schedule or footprint. Define which activities may start under an initial access agreement and what written confirmations are required before boring, pumping or excavation. Preserve any monitoring access the cleanup records require.

For a land sale or lease discussion, share the approximate location, acreage if known, the MSD number and the proposed area with Sunland. Owners and authorized representatives can inquire nationwide. If you have received an offer, point out any existing well, contemplated excavation or missing cleanup records. Provide site documents privately when requested. Sunland may contract for an opportunity and later assign it to a specialist, subject to the agreement.

Questions landowners ask

Does an MSD certificate mean cleanup is complete?

The certificate confirms the state designation. Request the separate cleanup decision and any continuing conditions to see how other exposure pathways and the proposed work were addressed.

Can the developer pump a trench just because the water will not be used for drinking?

Check the ordinance or covenant for extraction and contact restrictions. Ask the project team to confirm what authorization and handling are needed for the water and its proposed destination.

Can an existing well supply water for the battery project?

Identify the groundwater the well draws from and the applicable restrictions. Confirm the proposed use and reliable supply with the relevant water provider or authority and, for any required fire-water source, the fire authority.

Sources & further reading

Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.