Check whether the project meets Utah’s definition
Ask for the planned operations date, the engineer’s estimate of annual water withdrawals and the total area of the buildings. Utah Code § 73-5-8.3 defines a new large data center by operations beginning on or after July 1, 2026. The large data center definition includes withdrawals of at least 75 acre-feet per year and buildings totaling at least 10,000 square feet. It also specifies the primary server use at one location, supporting infrastructure and who owns or leases the facility and the land.
Get the names of the project company, the prospective facility operator and the local water provider. The statute’s operator definition includes a facility owner or operator and others with comparable rights to use the facility. Ask the project team to identify who will send the notice and report. Bring unclear arrangements, phased projects or early starts to the Division of Water Rights for a project-specific answer.

Count back from the first covered construction activity
For the preconstruction requirement that applies on or after July 1, 2026, count back 360 days and 90 days from the proposed start. Those dates bracket the filing window. Utah defines construction activity by the physical work needed to build the facility and authorizes the Division to define it by rule. Give the Division a dated phase plan showing any proposed early clearing, grading or site access work. Ask which activity starts the clock before relying on a later building start date.
Ask for the operator’s written notice of anticipated water consumption to the provider serving the area, along with the report to the Division. The report identifies the county and municipality if applicable, estimated annual withdrawals, discharge treatment plans where applicable, any planned temperature adjustments and plans to reuse water or replace water used. Get a copy and dated delivery evidence for each. If the schedule leaves only 60 days before covered work starts and the filings are still outstanding, ask the operator for a revised schedule before authorizing that work.
Get the city or county’s separate notice record
Before approving a land use application for a new large data center, the city or county land use authority must notify the Division of Water Rights, the Division of Water Quality and the relevant water provider, if any, by mail or email. Ask the planning office for the applicable application record, the recipients and dates of the notices and any approval decision. The Division’s public reports page includes land use notifications and preconstruction reports. Use it to locate entries and ask the sending party for the complete record.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMatch the filing dates to the land agreement
Put the work schedule, filing dates, local approval record and the relevant option or lease clause side by side. Have counsel check what starts rent, what allows site entry and what proof the developer must deliver before either happens. If the project moves a phase or changes the first work date, ask the Division how the timing applies and have counsel check whether an extension or revised access date is needed.
If your terms depend on water being available, ask the provider separately what it can commit to for the phase. Get the actual permits or written service terms the agreement calls for. The statutory notice and report give the provider and state the operator’s estimates and plans.
Discuss your data center property or agreement
Sunland accepts sale, lease and existing agreement assignment inquiries from property owners and authorized representatives across the United States. Share the general location, your role, the proposed transaction and the date of your next decision. Keep copies of filings, plans and agreements for private follow-up.
Questions landowners ask
Does the filing window apply to both documents?
Yes. Section 73-5-8.3(3) places both the operator’s written notice to the area water provider and the report to the Division of Water Rights in the 90- to 360-day window before covered construction starts.
What if the project is exactly 10,000 square feet?
Buildings totaling exactly 10,000 square feet meet the statutory size threshold. Check the withdrawal threshold and the other elements of the definition with the Division.
What if the construction date moves after a report is filed?
Compare both filing dates with the revised date of the first covered activity. Ask the Division whether the existing documents suffice or whether updated filings are needed, and check any affected dates in your agreement.
Sources & further reading
Sources checked November 22, 2026. HB 76 took effect May 6, 2026. See Utah Code § 73-5-8.3 for the separate July 1, 2026 thresholds tied to operations and the preconstruction requirement. Local rules and program details can change. Check the requirements for the actual project.