Check which permit and plant the rule covers
Get the issued conditional use permit, amendments and the local record showing the issuance date. Utah Code §54-17-1204(1) applies to a covered plant for which a conditional use permit was issued after May 6, 2026. Check the issued permit date rather than the application date, lease date or commercial operation date.
Under §54-17-1201, the rule covers a utility-scale commercial facility with more than one megawatt of nameplate generating capacity that converts sunlight into electricity primarily for wholesale or retail sale. Ask the project owner for records showing the facility’s capacity and purpose. Identify the entity responsible for seeking the permits or extension, especially if the facility and land have different owners.

Ask for records of approvals or a granted extension
If the project owner seeks to repower at the end of the plant’s useful life, §54-17-1204(1)(e) says to complete necessary local permitting and approval requirements “within 18 months before decommissioning requirements or penalties are incurred,” or obtain an extension from the local permitting authority. Ask the authority which event and date it uses for this project and which approvals it requires. Bring the current permit, its conditions and the approved decommissioning plan to that discussion.
Ask for the approval records and any remaining conditions. If the owner relies on an extension, request the authority’s decision and confirm the new date, what it covers and any conditions. A request or an application receipt only shows that someone asked. The same statute has a separate provision for curing deficiencies following notice about cessation, abandonment or damage. Have the authority identify which provision it is applying.
Compare the public decision with the signed lease
Check what the lease says about exercising a repower option, requesting your consent, entering the land to do the work and changing the end date. Compare the lease notice and renewal dates with the local schedule, and ask who handles approvals, provides copies and pays for equipment removal or land restoration if repowering falls through.
For a lease negotiation, sale or assignment, ask counsel to review what happens if local approvals remain pending when a private deadline arrives. If an amendment is proposed, review which dates and obligations it changes, when any additional rent starts, and who carries out removal and restoration if the project owner cannot proceed.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDescribe your repowering question
Sunland welcomes nationwide inquiries from landowners and authorized representatives about solar land sales, leases and assignments of existing agreements. Share the general location, your role and whether the project owner is negotiating repower terms or has asked for more time. Keep signed agreements and detailed project records for private review.
Questions landowners ask
Which permit date should I check?
Check when the conditional use permit was issued. Section 54-17-1204(1) specifies issuance after May 6, 2026, for a plant within the statutory definition.
Does a pending extension request establish a new date?
Ask the local permitting authority for its decision. If an extension was granted, confirm the date, scope and conditions in the decision.
Does the local extension give the project owner a longer lease?
The local decision addresses the permitting timeline. Check the signed lease and any amendments to determine the project owner’s right to continue occupying the property.
Sources & further reading
The Utah Code and enrolled H.B. 16 were checked November 21, 2026. Confirm dates, approvals and any extension conditions for the specific project with the local permitting authority. Local rules and program details can change. Check the requirements for the actual project.