Solar developers can elect state certification under chapter 80.50 RCW. Confirm that the project is using EFSEC and obtain its docket number and current site map. Look up the facility, then check its land-use and adjudication records. Ask EFSEC's site specialist to identify the order and the site layout it addresses if the docket has several versions.
After the informational public hearing, EFSEC holds a public hearing on whether the proposed site is consistent with and complies with city, county or regional land-use plans or zoning ordinances as of the application date. Ask for the Council's determination and check the project name, parcel numbers and layout. If the Council finds all or part of a project inconsistent, it schedules an adjudicative proceeding to consider whether it should recommend state preemption. Ask for the docket notice and any applicable comment deadline if you intend to participate.

Read the expedited-processing order separately
Expedited processing requires both a favorable land-use finding and a finding that environmental impacts are nonsignificant or can be mitigated to that level. Ask for the current environmental determination and the Council's order granting expedited processing. That order changes the review procedure by removing the requirement to hold an adjudicative proceeding on the application. EFSEC still holds a public comment meeting before sending its recommendation to the Governor.
In Yakima County, EFSEC granted a land-use consistency finding for High Top and Ostrea Solar in Order 884 on October 18, 2022. It separately granted expedited processing in Order 885 on November 15, 2022. EFSEC later sent its recommendation to the Governor, who signed the High Top site certification agreement on April 6, 2023. The signed agreement has a separate article for plans, approvals and actions required before construction.
Match the signed certification and work plans to your agreement
EFSEC sends the Governor a draft site certification agreement with a recommendation to approve. The Governor can approve and execute it, reject the application or return aspects to the Council for reconsideration. The certification agreement becomes binding when both the Governor and the applicant execute it. Get the signed agreement and any amendments, then ask EFSEC which approved plans or preconstruction conditions apply to the work the developer proposes.
Put the signed land agreement and the current site plan side by side. Check parcel IDs, access roads, temporary work areas and any phase limits against your exhibits. Ask the developer to describe the activity, dates and area it wants to use. Have your attorney identify what evidence your agreement calls for, whether it distinguishes testing or survey entry from construction access, and when any related payment or deadline starts. If the developer seeks an extension, ask which dates it proposes to change and how the option payment and access terms would apply during the added time.
Sunland welcomes nationwide inquiries from landowners and authorized representatives considering a solar sale, lease or existing agreement. Share the property's general location, your role and the milestone or deadline you are facing. Save signed agreements for private follow-up.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landQuestions landowners ask
Does a land-use consistency finding grant expedited processing?
EFSEC issues a separate expedited-processing order after the required land-use and environmental findings. Ask for that order and check which application it covers.
Do I have to give construction access after the Governor signs?
Ask EFSEC which conditions and plans apply to the proposed work, and check that both parties signed the certification agreement. Your attorney can review whether the access clause in your own agreement permits the stated work on that parcel and date.
Where can I find the documents for my project?
Search EFSEC's facilities list using the project name. Use the docket number when contacting the site specialist for the land-use order, environmental determination, any expedited order, signed certification agreement and approved plans for the proposed work.
Sources & further reading
Sources checked 2026-11-22. Local rules and program details can change. Check the requirements for the actual project.
- Washington Legislature, RCW 80.50.020, definitions
- Washington Legislature, RCW 80.50.060, applicability and certification election
- Washington Legislature, RCW 80.50.090, public hearings and comment
- Washington Legislature, WAC 463-28-060, preemption proceeding
- Washington Legislature, RCW 80.50.075, expedited processing
- Washington Legislature, WAC 463-43-050, expedited-processing determination
- Washington Legislature, RCW 80.50.100, recommendation and Governor action
- Washington EFSEC, High Top and Ostrea Solar land-use consistency order
- Washington EFSEC, High Top and Ostrea Solar expedited-processing order
- Washington EFSEC, signed High Top Solar site certification agreement
- Washington EFSEC, facilities and site contacts