Put plat preparation and approvals on the closing schedule
Under Section 12.2, the seller was to use commercially reasonable efforts to complete the agreed parcel combination and subdivision and pay the costs of the plats and necessary approvals. The seller had to submit its proposed subdivision plats and plans to the buyer for approval before filing them. The agreement limited the buyer’s ability to withhold, condition or delay approval unreasonably.
Final signed and approved subdivision plats were a condition for both parties. The parties could agree to a reasonable closing extension for pending plat approval requirements. After good-faith efforts, either party could terminate by written notice if a required plat was denied or approval was delayed beyond the last permitted closing date.

Check which rights continue after the boundary changes
The agreement separately conditioned the buyer’s obligation to close on maintaining the parcels’ existing entitlements, including zoning, development rights, any existing permits and permitted uses. It gave the buyer a termination right if the parcel changes would cause the entitlements to be lost. The agreement handled the deposit differently if the loss was due to the buyer’s acts, omissions or failure to meet its obligations.
Ask counsel and the relevant authorities to match each existing approval or right to the new parcel description. Verify which rights stay in place, which need an assignment or consent, and which remain with the seller or another party. Give the closing team the approved plat, any recording confirmation and the documents that establish the status of each right.
Separate approval costs from physical work
The Yadkin agreement assigned the seller the costs of obtaining parcel approvals and preparing the plats. The buyer took responsibility for specified design and construction costs to physically separate the property. That buyer payment obligation survived closing or earlier termination.
Ask your closing team to identify any lender consents or subordinations, who obtains them and which evidence it needs before closing. Unifi and WhiteFiber reported that the Yadkin sale closed on October 28, 2026. Unifi’s signed credit amendment references a condominium plat. The reviewed filings leave the final approval or recording of plats and the continuation of individual entitlements unverified.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a sale that divides the property
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, what part of the property you may transfer and the next decision date. Keep surveys, permit records and agreements for private follow-up.
Questions landowners ask
Who paid for preparing the plats under the Yadkin agreement?
Section 12.2 assigned the seller the costs of creating the subdivision plats and obtaining the needed parcel approvals. It separately assigned specified physical separation work costs to the buyer.
What if a required plat is denied or arrives late?
After good-faith efforts, the Yadkin agreement allowed either party to terminate by written notice if an approval was denied or delayed beyond the last permitted closing date. Check any agreed extension and the applicable deposit terms.
Does an approved plat confirm that existing development rights continue?
Check each approval and right with counsel and the relevant authorities. The Yadkin agreement made continuing entitlements a separate condition of the buyer’s obligation to close.
Sources & further reading
Sources checked November 21, 2026. The sale was reported closed. The reviewed records leave the approved or recorded plats, recorded condominium declaration, status of individual rights and any related closing waiver unverified. Local rules and program details can change. Check the requirements for the actual project.