What should a seller agree to before a data center buyer tests the land?

Before a data center buyer sends a crew to your property, agree on what the crew may do and who will put the property back in order. The signed purchase agreement for an industrial property sale in Yadkin County, North Carolina, gave the seller control over intrusive testing and addressed repair and reports if the agreement ended.

Could my land work?

Define which inspections the buyer may conduct and which need separate written approval. Set the areas, hours and required insurance evidence before the visit. Agree who repairs damage, which obligations survive closing or termination, and which reports the buyer must deliver if the transaction ends.

Define what an inspection allows

Section 4 of the Yadkin agreement let the buyer inspect at its own expense. If the buyer proceeded past the inspection period, access for continued inspections remained subject to the agreement through closing. The buyer or its agents needed the seller’s prior written consent for any soil disturbance or invasive testing, and the seller could withhold it in its sole discretion.

Ask for a written list of the people, activities and areas the buyer wants to include. Identify which visits are covered by the purchase agreement and which require further written consent. Put the inspection deadlines and any extension procedure on your calendar alongside the visit schedule.

Illustration of a land parcel and surrounding landscape

Protect existing use and confirm insurance

The Yadkin agreement put on-site inspections within regular business hours at times reasonably set by the seller so they would avoid unreasonable interference with its operations. Show the buyer which entrances, routes and work areas you and any occupants need to keep open. Agree who coordinates each visit and who approves a change in scope.

The buyer had to maintain the specified liability insurance at its expense, name the seller as an additional insured and provide a certificate. Before your visit, ask your broker and counsel to check the agreement and insurance evidence for the proposed activities, buyer and contractors.

Document the property’s condition and responsibilities for damage

Take dated photos of the areas the buyer will use and agree who will inspect them afterward. In Yadkin, the buyer agreed to repair damage caused by its access and inspection and promptly restore the property to its condition before the work.

The buyer also agreed to cover defined losses connected to its pre-closing activities. That indemnity excluded losses arising from seller-side negligence or intentional misconduct and losses from the buyer merely discovering a pre-existing condition. The repair, restoration and indemnity obligations survived either closing or termination. Ask counsel which claims and repairs your deal covers and how you would document them.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Agree what happens to the reports if the sale ends

If the Yadkin agreement had been terminated for any reason, the buyer was required to give the seller copies of the third-party reports, surveys and other reports it obtained during inspections at no charge, without making any representation or warranty about them. The parties ultimately closed the sale. For your deal, agree when reports would be due and ask the report provider and your counsel who can use or rely on them.

Sunland accepts data center property sale, lease and existing agreement inquiries from owners and authorized representatives across the United States. Share the general location, current use, work the buyer has proposed and any deadline. Keep reports and private property records for follow-up.

Questions landowners ask

Can a buyer start invasive testing after getting permission to visit?

Check the signed agreement and the approved scope. The Yadkin agreement required prior written seller consent for invasive testing or any soil disturbance even when access for inspections was already in place.

Who repairs inspection damage if the deal is terminated?

Check which duties survive termination. The Yadkin agreement kept its buyer repair, restoration and indemnity provisions in effect after termination.

Can the seller get the buyer’s reports if the agreement ends?

Check the report-delivery clause and any limits on use. The Yadkin agreement called for copies at no charge if the agreement was terminated, without a buyer warranty.

Sources & further reading

Sources checked November 20, 2026. The Yadkin example describes the signed inspection terms and reported sale. Check your own agreement for access, insurance, restoration and report delivery terms. Local rules and program details can change. Check the requirements for the actual project.