Check the Phase 1 certificate and the Phase 2 permit plans
In its July 3, 2025 approval for 8050 Camino Arroyo, Gilroy included recycled-water requirements in Condition 53. The condition provides for temporary City domestic water for Phase 1. It requires the developer to submit the design documents to Gilroy and Valley Water before issuance of the last Phase 1 certificate of occupancy. Both agencies must approve and sign the documents before Phase 2 building permits are issued.
The Phase 2 permit plans must include the on-site work needed to convert both phases to recycled water for nonpotable uses. Condition 53 requires completion of that work within two years after issuance of the last Phase 1 certificate of occupancy or by issuance of the first Phase 2 certificate, whichever comes first. Get the certificate dates and ask Public Works which inspection or acceptance records show the on-site work is complete.

Confirm how the off-site work is being handled
If the developer elects to build the off-site upgrades, Condition 53 requires completion before the first Phase 2 certificate of occupancy, including a temporary one. If the developer elects to deposit funds with the City, the condition sets the amount at the estimate approved by Gilroy and Valley Water, including a 20% contingency. The deposit is due within 180 days after both agencies give final approval to the plans, specifications and estimates.
Once the on-site work is complete and the applicable off-site work or deposit is in place, Condition 53 can no longer be a basis for the City to deny Phase 2 occupancy. Other approval conditions still apply. Ask Public Works for written confirmation of which option applies and whether it has accepted the work or payment. The City announced in August 2026 that the Council approved agreements to advance recycled-water infrastructure, including a developer-funded reservoir and pump station. Review the signed agreements and ask the City which work and payments they cover.
Verify connection and match the evidence to the deal
Condition 53 calls for immediate connection once the off-site system is operational. Ask Public Works and Valley Water to confirm the status of the system and what will document connection at the site. If the buyer needs recycled water on its first day of operation, ask for confirmation of service for the intended uses as well as the occupancy certificate.
Have counsel compare the City’s written confirmation with the proposed sale closing, lease start or payment date. Agree who will finish and fund remaining work, who bears a delay, and who receives any refund under the applicable terms. For a different property, start with that site’s own approval and service agreements.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a sale, lease or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about a property sale, lease or existing project agreement. Share the general location, your role, the transaction you are considering and the affected phase. Arrange private follow-up for permit records and agreements.
Questions landowners ask
Could the first Phase 2 occupancy certificate come before recycled water is connected?
Under Condition 53’s deposit option, once the on-site work is complete and the qualifying deposit has been made, the City cannot use that condition to deny Phase 2 occupancy even if the off-site system is unfinished. Check the remaining conditions with the City and confirm the service connection date separately.
Which date starts the 180-day deposit period?
Condition 53 measures it from final approval of the off-site upgrade plans, specifications and estimates by Gilroy and Valley Water. Ask Public Works which dated approvals it uses to calculate the deadline and for written confirmation of any accepted deposit.
Sources & further reading
Sources checked November 22, 2026. Confirm the current approval conditions, executed agreements and status of the next certificate with Gilroy. Local rules and program details can change. Check the requirements for the actual project.