Find the boreholes and who relies on them
Ask the building owner, facilities manager or installer for the original permit and drawings, any as-built plan, the number and depths of the boreholes, and records of modifications or sealing. Ask the relevant health department for the permit file if the owner’s records are incomplete. Illinois’s closed-loop permit rule calls for a site plan, location and borehole count and depth. Have a qualified contractor reconcile those records with what is on the ground before relying on the map for excavation.
Ask which buildings still use the loops and where the connecting pipes, headers and service points run. If a former building has been removed, ask when the system was taken out of service and request the sealing records for that specific system. This guide concerns regulated closed-loop geothermal wells. Illinois law excludes horizontal closed-loop systems where neither law nor industry practice requires grouting. Ask the permit issuer to confirm how it classifies the system on your property.

Compare the full battery layout with the working system
Put the proposed equipment pads, electrical trenches, construction staging and access routes on the same plan as the boreholes and connecting pipes. A pad may fit between the boreholes while the cable trench cuts across pipes serving the building. Ask the project engineer and geothermal contractor to compare the proposed work with the mapped system and see whether a revised route would leave service and repair access.
If the owner will keep a building and sell or lease the yard, mark any retained equipment and access rights on the agreement exhibit. Decide who can enter, who pays for a damaged loop or lost heating and cooling during construction, and what work would require consent. If work on only part of a field could affect the rest, ask the contractor and permit issuer how the proposed change should be handled before agreeing to a final footprint.
Schedule sealing and collect the filed report
If the geothermal system will be retired, ask the Illinois Department of Public Health or the approved local authority how it applies the rules to the site. Section 920.180 requires abandoned closed-loop wells to be brought into compliance or sealed within 30 days after abandonment. Plan any shutdown with the contractor and permit issuer before setting a battery possession date.
Section 920.200 requires a permit before modifying or sealing a regulated system. For permitted work, the closed-loop well contractor must notify the appropriate authority at least two days before work starts. After the system is abandoned and sealed, the contractor has 30 days to submit the sealing report. Ask for the issued permit, a copy of the submitted report and evidence of filing. Have the contractor identify the sealed bores and any retained piping on the handover drawing so the project team can match the records to the area it will disturb.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landWrite the chosen approach into the land agreement
Ask counsel to record the agreed route or closure scope and say who obtains the permit, arranges the contractor and pays for work or a redesign. If sealing is the chosen path, agree whether delivery of the filed report and handover drawing is a condition of closing, possession or ground disturbance in the affected area. Set a date to revisit the layout or schedule if the contractor finds more bores than the records show.
If you own or represent a site you are considering for sale or lease, share its approximate location, the area you can offer and whether the geothermal system still serves a building. Sunland welcomes inquiries nationwide. Provide the borefield and proposed battery drawings privately when requested.
Questions landowners ask
Does offering the land for battery storage trigger the abandonment deadline?
Section 920.180 ties the 30-day period to abandonment of the closed-loop wells. If an old system is already out of service, ask the permit issuer to confirm its status and what action is due before any new excavation.
Can the borefield keep serving a building after part of the site is leased or sold?
Have the project engineer and geothermal contractor confirm the boreholes, pipes and service access the building needs. Show any retained rights and responsibilities in the land agreement, and confirm the applicable permit requirements if the work changes the system.
What should I request if a contractor says the system was sealed?
Ask for the permit, a copy of the sealing report and evidence of filing. Cross-check the addresses and borefield details with the actual area offered before the developer commits to excavation.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.
- Illinois Water Well Construction Code, 77 Ill. Adm. Code 920.180 and 920.200
- Illinois Department of Public Health, compiled Water Well Construction Code Act, § 3 definitions
- Illinois Department of Public Health private water and closed-loop wells program
- Illinois Department of Public Health closed-loop well system permit application