Illinois solar farm crossings of drainage district tile
Sources checked
When can solar cross a district drain?
A covered commercial solar project with county siting approval can cross a drainage district’s tile, ditch or culvert without prior district approval if the work follows the filed farmland drainage plan. Verify the county decision, the drain’s ownership or control, and the exact route before agreeing to construction access.
A cable trench can cut a buried drain, and a haul road can affect a shallow tile or change how water reaches a ditch. Use these checks to protect drainage on the acres you keep farming and to document who will repair damage.
When Illinois waives district sign-off
The crossing authority in 55 ILCS 5/5-12020(t) covers a facility owner with county siting approval for a qualifying project. It applies to systems owned or controlled by a district under the Illinois Drainage Code, including buried tiles, open ditches, culverts and water gathering vaults. Under subsection (j-5), the developer prepares the farmland drainage plan independently and the facility files it with the county and each affected district. If the county decision refers to a separate crossing condition or consent, ask county planning how that condition applies to the exact feature and route.
The Counties Code definition generally covers ground-mounted systems that generate electricity mainly for sale. It excludes utility-scale systems at sites eligible for a specific Illinois Power Agency procurement. Subsection (u) also lists exceptions to the 2023 amendments, including siting applications or agricultural impact mitigation agreements submitted to the relevant authority before January 27, 2023, a qualifying industrial site in a certified enterprise zone within four miles of the I-88 and I-39 interchange, and a defined area in Madison County bounded by portions of Drexelius, Fosterburg and Wolf roads. Ask county planning which rules and approval conditions apply to your parcel if the project is older or touches one of those areas.
Sources Illinois Counties Code, 55 ILCS 5/5-12020 · Property Tax Code definition of commercial solar, 35 ILCS 200/10-720
Find out who owns, controls and uses the drain
Start with the exact stretch the crew will cross. A farm lateral may run into a district main, and a private line may also serve adjoining farms. Even within district boundaries, verify ownership and control at the crossing. Ask the district whether the mapped location is approximate or verified in the field.
| What the crossing affects | What to check |
|---|---|
| District main, ditch or culvert | Request the district map or record and identify the feature on the filed farmland drainage plan. Confirm who can access it for inspection and maintenance. |
| Private tile serving your farm | Find installation or repair records and walk the route with the farm operator. Ask the developer to identify private tile on the construction drawings and show how the project AIMA and your land agreement cover it. |
| Shared private drain serving multiple properties | Identify the connected farms and records of shared use. Illinois law protects qualifying mutual drains with a perpetual easement and requires consent from all protected owners before impairing the drain. Have counsel check whether that rule applies. |
Sources Illinois Drainage Code, 70 ILCS 605/2-8 and 2-10 · Illinois Department of Agriculture, Standard Solar AIMA, § 6
Match the filed plan to the work on your farm
The filed plan must identify potentially affected district facilities to the extent the county or district makes that information publicly available. It must address surface drainage restoration during and after construction or deconstruction and use the project’s agricultural impact mitigation agreement, or AIMA, for subsurface repair procedures. Use the checklist below to review the contractor’s plans and your land agreement alongside the filed plan.
- County planning. Obtain the written siting decision and conditions, plus the farmland drainage plan and any revisions on file. Use the project name, zoning case number and parcel number in your request.
- Drainage district. Confirm the plan revision the district received and request relevant drain, outlet and maintenance records. Ask how the district wants to be contacted if a main or ditch is affected.
- Developer’s engineer. Request a dated drawing with the drain, cable or road alignment, temporary work limits and equipment access on the same sheet. For a buried crossing, ask for a profile showing the relative elevations of the cable and tile and how the crew will verify location and depth.
- Your option, lease, easement or access agreement. Check which areas the signed exhibit actually covers. Compare work limits, notice requirements and future access for inspection or repair with the construction drawing.
What if the crew needs to move the crossing?
Suppose the contractor finds a tile under the planned cable trench and wants to move the crossing into the field you still farm. Request a drawing that shows the old and new routes, where equipment would enter and how the change affects nearby outlets or laterals. Ask the county whether the move calls for an updated filing or approval and confirm with the district which plan it received. Check whether your agreement covers the new route and work area before signing any change or granting additional access.
For a project-specific example, Champaign County’s North Duncan Road Solar permit (Ordinance 2026-4) called for a tile investigation map and a revised site plan before approval of the zoning use permit. The permit also required future maintenance access and a 40-foot-wide no-construction area centered on mutual drains. Check your own county’s decision for the conditions that apply to your project.
Sources Champaign County Ordinance 2026-4, Case 184-S-25, condition F
Document repairs and crop losses
Under subsection (s-5), the facility owner must repair or pay for subsurface drainage damage caused by construction under the applicable AIMA procedures. The owner must repair or pay for surface drainage restoration caused by construction or deconstruction as soon as reasonably practicable. The section also requires compensation to landowners for crop losses or other agricultural damage resulting from construction-caused drainage damage. Subsection (j-5) calls for surface and subsurface damage to be repaired as soon as reasonably practicable.
Get the project AIMA and compare the drainage provisions with your signed land agreement. The state’s standard template calls for as-built drawings within 60 days after construction ends, showing tile lines found during construction, repair locations and underground cable. Section 6 also provides for correction of certain failed tile repairs made by the facility owner for one year following completion of construction or deconstruction. Check the project paperwork for the terms that apply to your land.
- Before work, record existing wet areas, working outlets and prior repairs with the person farming the ground. Get a named contact for reporting a drainage problem.
- If water starts standing after construction, record when it appeared, photograph the affected area and note rainfall, outlet flow and the location relative to the crossing. Send written notice promptly under the agreement and ask for the inspection and repair schedule.
- After repair, request the location, method and date, plus the updated as-built map. Keep records of affected acres, crop loss and repair expenses. If you rent out the field, confirm who documents losses and how payment is handled under both agreements.
Sources Illinois Counties Code, 55 ILCS 5/5-12020 · Illinois Department of Agriculture, Standard Solar AIMA, § 6 · Renewable Energy Facilities Agricultural Impact Mitigation Act, 505 ILCS 147/15
Common questions
Who gets a copy of the farmland drainage plan?
Under 55 ILCS 5/5-12020(j-5), the facility files the plan with the county and affected drainage districts. Ask for the version on file for your project and compare its date with the developer’s latest drawing.
Who pays if the solar contractor breaks a field tile?
For construction-caused subsurface drainage damage covered by 55 ILCS 5/5-12020(s-5), the facility owner must repair it or pay for the repair under the applicable AIMA drainage procedures. Get the facility owner’s reporting contact and check the project documents for how to request repairs.
When should an Illinois landowner receive the solar AIMA?
For facilities covered by 505 ILCS 147/15(c-5), the owner must give the landowner a copy of the agreement submitted to the state or the fully executed project-specific AIMA at least 30 days before construction starts. Ask for the executed copy and any exhibits or amendments that apply to the crossing.
Sources
- Illinois Counties Code, 55 ILCS 5/5-12020
- Illinois General Assembly, Public Act 104-0480, changes effective July 1, 2026
- Illinois Drainage Code, 70 ILCS 605/2-8 and 2-10
- Renewable Energy Facilities Agricultural Impact Mitigation Act, 505 ILCS 147/15
- Illinois Department of Agriculture, Standard Solar AIMA, § 6
- Champaign County Ordinance 2026-4, Case 184-S-25, condition F
- Champaign County Board minutes, February 19, 2026, adoption of Ordinance 2026-4