Confirm the county review and the receiving sewer
Give the Jefferson County Planning Division the parcel numbers and the proposed project map. The Unified Development Order applies in the unincorporated county. Article X covers new data centers, including accessory uses, and defines a major expansion as an increase of at least 10% in building area or utility demand. If there is a prior approval or the project straddles a city boundary, ask the county which application and rules apply to the proposed work.
The county requires covered projects to connect to public water and sewer. Ask which public wastewater district would receive the proposed discharge and where the connection would be. Request the district’s written response identifying the flows it reviewed, any remaining capacity or connection review, and any discharge approvals or operating conditions the project still needs. Check which phase and layout the response covers.

Read the wastewater assessment alongside the site plan
Section 400.3750(B) requires a qualified Missouri-licensed engineer with wastewater expertise to prepare the assessment. Ask for the version submitted with the application. It must address expected daily and peak flows, wastewater composition and temperature, effects on the receiving sewer and proposed pretreatment. Ask which wastewater streams and phases are included if the buyer’s cooling design or buildout schedule has changed.
Process wastewater must meet applicable pretreatment standards. The county sets conditions for cooling tower blowdown and water-softening brine and can require measures such as tanks that reduce peak discharge rates. Ask the engineer to mark the proposed sewer route, the space needed for treatment and monitoring, and access for maintenance. If the proposed connection crosses land you would keep, ask for the easement width, the access route and who would repair the line or restore the ground.
Ask which operating records the project will need
Section 400.3750 requires the facility to install flow meters, temperature sensors and electronic monitoring equipment. The facility provides the county with a copy of the valid wastewater operating permit each year and supplies discharge monitoring reports on request. It also reports discharge volumes, chemical analyses, temperature and treatment performance twice a year to the county and the public wastewater district.
Ask the project team to identify the proposed applicant and operator, confirm the permit issuer with the district and county, and name the party that will maintain the equipment and submit records. If you plan to keep ownership and lease the site, have counsel check which duties may apply to you under the county rules. For a site that already has approvals, ask the issuing authority what paperwork or confirmation an operator or design change would require.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the reviewed design and costs into the land agreement
Have your advisers compare the same dated site plan and wastewater assessment with the sale, lease or option exhibit. Identify who pays for pretreatment, the connection, any sewer upgrades and ongoing access or maintenance. Specify which written county and district responses you need before the next deadline, and how the agreement handles a revised layout or an approval that takes longer than expected.
Sunland welcomes data center sale, lease and existing agreement inquiries from owners and authorized representatives nationwide. Sunland may contract for a property and assign the agreement to a specialist developer. Share the general location, proposed transaction and the decision you face. Arrange private follow-up for detailed plans, permits and agreements.
Questions landowners ask
Which data center projects does the county rule cover?
The Unified Development Order applies in unincorporated Jefferson County, Missouri. Article X covers new principal and accessory data centers and major expansions. Ask the Planning Division to confirm jurisdiction and coverage for your parcel and proposal.
What should I ask for if the developer already has a sewer map?
Ask for the district’s written response for the proposed phase and discharge, including the connection point, conditions and remaining approvals. Compare that response and the engineer’s assessment with the current site plan.
What if the proposed sewer route crosses acreage I plan to keep?
Ask for a surveyed easement exhibit and a written allocation of access, maintenance, repair, restoration and costs before agreeing to the crossing.
Sources & further reading
Sources checked November 22, 2026. Confirm the applicable county review and the proposed connection and discharge conditions with the Planning Division and the receiving public wastewater district. Local rules and program details can change. Check the requirements for the actual project.