Ohio · Solar

Is your Licking County land in a restricted area for large solar projects?

Sources checked

Check the proposed footprint against the county’s current records

Licking County adopted Resolution 124-76 to restrict large solar facilities in unincorporated parts of Hanover, Licking, St. Albans, Union and Washington townships. Before granting or extending a solar option, give the county commissioners’ office your parcel numbers and the developer’s dated site map. Ask which restrictions apply to that footprint today and whether the developer is relying on an earlier project filing or certificate.

A farm near a village boundary can have the same mailing address as land inside the village. The proposed panels, access road and power lines can also occupy different parts of the farm. Check the land the project would actually use before agreeing to tie up acreage.

Find the township and the municipal boundary

Look up each parcel by its auditor’s number in the Licking County Tax Parcel Viewer. Compare the county’s parcel, township and municipal boundary layers with your survey or recorded deed and the developer’s drawing. If the parcel is near a city or village line, ask the county planning office to confirm which side the proposed project components fall on and whether an annexation changed the line.

Resolution 124-76 was adopted August 29, 2024. Section 1 and Exhibit A describe five township areas. Section 2 addresses amendments, rescission and land becoming incorporated. This is one county resolution, so ask the commissioners’ office for every applicable resolution, current boundary exhibit and effective date. Ask the recorder for the filed copies. Ohio generally makes a designation effective 30 days after adoption unless a qualifying referendum petition is presented. If the clerk identifies a referendum, ask for its certified result as well.

Sources Licking County Tax Parcel Viewer · Licking County parcel, township and municipal boundary maps · Licking County Resolution 124-76, §§ 1–4 and Exhibit A · Licking County Board of Commissioners office · Licking County commissioners’ resolutions and minutes · Licking County Recorder’s Office · Ohio Revised Code § 303.59, effective date and referendum

Ask how much the entire facility could generate

Ohio defines a large solar facility by the generating plant and associated facilities, a single grid interconnection, and the major utility facility threshold. For a generating plant, that threshold is a design or operating capability of at least 50 megawatts. Ask for the total project capacity and the proposed interconnection point. The portion of the project on your parcel can be much smaller than the full project.

For a covered new project, or a covered material amendment, Ohio law bars filing and acceptance of an application to build the prohibited type of facility in an effective restricted area. If the proposal falls outside that rule because of its size or location, ask the township or municipality that governs the site which other approvals it requires. Request the developer’s written explanation of the approvals it expects for the panels, access and electrical facilities on your land.

Sources Ohio Revised Code § 4906.01(B)(1)(a) and (G), large solar facility · Ohio Revised Code § 303.57, material amendment · Ohio Revised Code § 303.60, restricted-area filing rule · Licking County township and zoning contacts

Tell the area restriction from the project decision

For a project subject to Ohio Revised Code § 303.61, the developer holds a public meeting in each county where the facility would be located, 90 to 300 days before applying. The developer presents its maximum nameplate capacity and a map of the proposed boundaries in that county. The county commissioners then have up to 90 days after the meeting to prohibit the specific proposal or limit it to a smaller area within the original boundaries. If the county takes no such action within that time, the application can proceed to state review.

Record you’re shownWhat to compare with your offer
County restricted-area resolutionThe effective designation, its mapped limits and any amendments. Compare those limits with each project component on your survey.
Public-meeting map and county decision on the projectThe date of the meeting and any county resolution that removes acreage or prohibits the proposal. Request a revised map if the county narrows the area.
Ohio Power Siting Board certificateThe case number, the approved boundary drawing, conditions and later amendment orders. Confirm that the current plans include the specific part of your parcel in the offer.

Sources Ohio Revised Code § 303.58, restricted-area boundaries and earlier proposals · Ohio Revised Code § 303.61, public meeting and project map · Ohio Revised Code § 303.62, project-specific county resolution · Ohio Senate Bill 52, § 4, transition rules for earlier solar filings

Check an earlier approval against the exact acreage

Ohio preserves construction under § 303.58(E) for a facility presented to the county under § 303.61 when the commissioners did not prohibit it within the time allowed under § 303.62. There are also separate transition rules for certain projects already in the state approval process when Senate Bill 52 took effect. If either rule is cited, ask for the dated meeting and county records or the state case documents that support it. Have counsel confirm how that record applies to the layout now proposed, especially if the county limited the original footprint.

Harvey Solar shows why the location and case number matter. The Ohio Power Siting Board approved that 350-megawatt project in Hartford and Bennington townships in 2022, and the Supreme Court of Ohio affirmed its certificate in 2025. The approval concerns that project area. If a developer says your acreage can join an existing project, ask it to mark your acreage on the approved plan and identify any later order covering the change.

An increase in nameplate capacity or a boundary expansion with aboveground components can make a change material under § 303.57. A boundary change alone falls outside that definition if the new boundary stays wholly inside the previous one or all components outside it are underground. Section 303.57 also excludes adding a battery storage system to a utility facility from this definition. If an existing project wants to move a fenced equipment pad onto your land, ask which drawing covers the pad and have the state board or your attorney confirm which approval or filing the move requires.

Sources Ohio Revised Code § 303.58, restricted-area boundaries and earlier proposals · Ohio Revised Code § 303.57, material amendment · Ohio Revised Code § 303.60, restricted-area filing rule · Ohio Senate Bill 52, § 4, transition rules for earlier solar filings · Ohio Power Siting Board, October 20, 2022 Harvey Solar decision minutes · Supreme Court of Ohio, Harvey Solar, 2025-Ohio-1503

Set the option acreage after you check the map

Suppose a proposed option would cover two fields, one inside a village and one in an unincorporated township. The first drawing shows panels on the village side and an entrance and equipment pad on the township side. Ask the developer to mark any component affected by a restriction and show how a different layout would change the driveway, working acreage and rights it wants. Ask the county and the relevant municipality to review the specific footprint before relying on that layout.

Review the revised drawing with your attorney. Ask which land the option would hold during siting review, what written approval or revised plan would trigger an extension, and when any unused acreage or corridor would be released. If there is no usable layout, ask what happens to any access rights or recorded option memorandum and who pays to document their release.

Sources Licking County Resolution 124-76, §§ 1–4 and Exhibit A · Licking County parcel, township and municipal boundary maps · Ohio Revised Code § 303.60, restricted-area filing rule

Common questions

Does a Hanover mailing address tell me whether my land is in the restricted area?

Use the auditor’s parcel number and check the current municipal boundary with the county. Resolution 124-76 describes the unincorporated part of Hanover Township. Ask the relevant village or city about its own rules if the footprint is inside municipal limits.

Does being outside the five township areas mean I can sign a lease?

Ask the commissioners’ office for any other resolution that covers your parcel or project, and have the developer identify the approvals it still needs. Compare the approval boundaries with the lease exhibit before agreeing to give possession.

Does a 90-day period without a county objection give the developer permission to build?

The application can proceed to the Ohio Power Siting Board when the county adopts no project prohibition or limitation within the statutory period. Ask for the state case number and the actual certificate and approved plans before treating the site as authorized.