Louisiana landowner guide

Has your Louisiana parish opted out of the state solar siting standards?

A developer says the parish’s solar ordinance sets the setbacks for the project on your land. Before you agree to the option map, ask for the adopted opt-out resolution, its submission record and the dated site plan. Those records help you check which parts of your property the project would need for equipment, roads and screening.

Could my land work?

A Louisiana parish that has adopted solar ordinances can opt out of the statewide siting standards by passing a resolution and submitting it to the Louisiana Department of Conservation and Energy (C&E). The statewide siting standards cease to apply in that parish upon submission. The state permit requirement under Act 279 still applies to facilities with a footprint of 75 acres or more.

Verify the parish’s ordinance and opt-out filing

Ask the parish clerk for the current solar ordinance, including amendments, and the signed resolution that identifies the ordinance. C&E directs parishes to send both records to the department. Ask for the dated transmittal or agency acknowledgment and have C&E confirm how it applies the opt-out to the project’s current layout.

The Pointe Coupee Parish Council’s November 4, 2025 minutes show the council adopting its resolution and directing staff to send it to C&E. Look for a separate record of submission. If the layout crosses a parish line, show both parishes on the map and ask C&E and the local offices which siting standards and permits apply to the mapped portions.

Illustration of a land parcel and surrounding landscape

Check the state permit and the standards used on the map

Louisiana Revised Statutes § 30:1143(A) requires a C&E permit to construct, install or operate a solar facility with a footprint of at least 75 acres. Ask for the acreage calculation for the whole facility and the issued permit or current application status. For projects of that size beginning construction after January 1, 2026, C&E uses the Solar Siting Permit. It uses an Immediate Solar Permit for covered projects that began construction on or before that date. C&E also administers a separate solar decommissioning permit with its own acreage threshold.

The state siting standards in § 30:1144 apply to facilities at or above 75 acres that begin construction after January 1, 2026, subject to the parish opt-out and the exception for facilities located wholly within an industrial-zoned area or a Louisiana Economic Development certified site. If the developer relies on either site designation, ask for the designation record and a map of its limits. Ask C&E to confirm the permit and standards for the current layout.

Where the state siting standards apply, have the engineer mark the points used to measure the setbacks. For example, the statute calls for 300 feet from a residential property line to the nearest solar device unless a written agreement between the property owner and facility operator provides otherwise. Check the applicable vegetative barriers on the landscape plan. Where the parish has opted out, ask the parish which local setbacks, screening conditions and plan version apply to your parcels.

RecordWhat to compare
Parish solar ordinance, resolution and submission recordThe ordinance and amendments, the date the parish passed the resolution and when it submitted it to C&E.
C&E permit or application and local decisionProject name, parcel locations, construction start date, state permit status and approved local exhibits.
Engineer’s site plan and acreage calculationWhole facility footprint, parish and property lines, equipment, applicable setbacks and screening.
Option exhibitAcres held for the project, access and work areas, and the land you intend to keep available.

Match the land option to the dated site plan

Ask the developer to overlay the engineer’s plan and screening areas on the option exhibit. Check whether access roads, temporary work areas or vegetation needed for screening would occupy land you planned to farm, sell or retain. Identify the plan by date and revision number and agree which acres and rights the developer needs if the layout changes.

Have Louisiana counsel review when the developer can revise the exhibit, whether the change requires your agreement, and how the parties handle rent, access and releases if the permitted project uses fewer acres. If part of your decision depends on a permit or siting determination, identify the record the developer should deliver and the deadline for delivery.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss a solar land proposal

Sunland welcomes inquiries from landowners and authorized representatives across the United States about land sales, leases and assignments of existing solar agreements. Share the general location and whether the developer is asking you to sign an option or revise its site plan. Keep signed documents and detailed plans for private follow-up.

Questions landowners ask

Is adopting a parish solar ordinance enough to opt out?

The parish must also adopt an opt-out resolution and submit it to C&E. Ask for the ordinance, resolution and dated submission record.

Does a parish opt-out eliminate the state solar permit?

The state permit requirement under § 30:1143(A) still applies at a facility footprint of 75 acres or more. Ask C&E which permit applies to the project’s construction date and confirm its status.

Should I use the acreage in my option to check the 75-acre threshold?

Use the footprint of the entire solar facility. Ask the developer for its engineer’s acreage calculation, including any land in other ownerships or parishes that forms part of the facility, and ask C&E to confirm the applicable footprint.

Sources & further reading

Louisiana’s statutes, C&E permitting materials and the parish council minutes were checked November 22, 2026. Confirm the current ordinance and local decisions with the parish and the state permit and siting status with C&E. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Louisiana?Tell us about your land