Confirm that the ordinance covers your site
City Ordinance O-281 took effect October 9, 2026. It added principal data centers as special land uses in the light and general industrial districts. The ordinance also sets four conditions for a facility to qualify as accessory. It must serve only the on-site owner or tenant’s enterprise functions, provide no leased data storage or processing services to off-site or third parties, occupy at most 10% of the building footprint and be housed within another building.
Give the City Planning and Zoning Division the parcel address, current or proposed use and site plan. Ask whether §153-4.34 applies, which approvals or conditions govern the facility and how the city treats existing operations or separate phases.

Get the reports and the dates behind them
For a covered facility, §153-4.34(E)(4)(c) and (E)(5)(c) require annual compliance reporting with any required Chapter 110 renewal. Both provisions call for updates on the assessments submitted with the application. Start with the water and wastewater assessments, ask the city which other materials it expects, and get copies of the latest reports and the city’s filing acknowledgments.
The operator must have a third-party acoustic engineer study sound within 30 days after the city issues the certificate of occupancy or certificate of completion, whichever it issues first. Third-party studies are required annually for five years after completion of that post-construction study. Both the post-construction and annual studies measure sound during peak routine equipment operation. The city requires the annual results with any required Chapter 110 renewal. Under §153-4.34(G)(4), the city withholds that renewal until the required assessment reports and annual sound results are submitted as required.
Check who holds the license and who files the reports
For the assessment updates and annual sound-study reporting, the ordinance treats the colocation property owner or their designee as the operator. Ask the City Clerk what designation it expects and who is recorded as the licensee for the facility. For a phased campus, ask which certificates, study dates and licenses apply to the space you are leasing or buying.
A general business license under §110.37 expires on the May 30 following issuance. The section prohibits assignment or transfer of the license and requires the applicant or licensee to notify the City Clerk when application information changes. Before a sale or operator change, ask the clerk which filings are required, whether a new license is needed and what written record will show the license is current on your closing date.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landGive the reporting party access before you sign
Have counsel check that the lease gives the reporting party timely access to the tenant’s water and wastewater records, the equipment and areas needed for sound studies, and evidence of each filing. Set internal deadlines, decide who pays for studies and updates, and specify who must fix missing records or respond to a city request. On a sale, arrange delivery of the reporting file and ask who can complete any filing due as ownership changes.
Sunland accepts data center land sale, lease and existing-agreement inquiries from owners and authorized representatives nationwide. Sunland may contract for a property and assign the agreement to a specialist developer. Share the general location, the transaction you are considering and any upcoming decision date. Arrange private follow-up for licenses, studies and signed agreements.
Questions landowners ask
Can the property owner designate the tenant to file reports?
The ordinance allows a colocation property owner to designate someone for the specified assessment updates and annual sound-study reporting. Ask the City Clerk what documentation it expects. Confirm who holds the applicable business license and make sure the designee can obtain the records and access needed to report.
What should I request before buying the landlord’s interest?
Request the current license, a copy of the reporting designation if there is one, the application assessments, the relevant certificates, the latest annual reports and sound studies, and the city’s submission or renewal correspondence. Ask the clerk about any filings or a new license that may be needed for the change.
When do the annual sound studies start?
The ordinance calls for annual studies for five years after completion of the initial post-construction study. The initial post-construction study is due within 30 days after the certificate of occupancy or certificate of completion is issued, whichever comes first. Ask the city to confirm the schedule for your building or phase.
Sources & further reading
Sources checked November 22, 2026. Confirm ordinance coverage, reporting dates and the applicable license for the facility with City Planning and Zoning and the City Clerk. Local rules and program details can change. Check the requirements for the actual project.