Confirm the plan and the permit with the Town
Give Sahuarita’s Planning and Zoning Division the parcel number and a site or phase plan. Ask whether the parcel is in the Park Industrial area covered by §IV.E.8 of the Rancho Sahuarita Specific Plan. The Town describes its August 2025 interpretation as applying to that area. The Town’s work on its standard industrial zoning regulations is a separate proceeding.
Ask the Town’s Building Safety Division which building permit covers the facility or associated equipment you are tracking and what it will accept to satisfy §IV.E.8.e.1. If the developer points to a minor deviation under §IV.E.8.e.8, ask for the Town’s written decision and which standards it covers. It allows approval of minor deviations from §IV.E.8.e.1 through e.7 as administrative changes when the Zoning Administrator reasonably determines they are consistent with the standards’ intent.

Read each utility’s statement against the project plans
The electric statement must identify the intended power provider and confirm sufficient power for the site without harm to other users or the existing grid. Ask the utility or developer which phase, load in megawatts and equipment the statement covers, and which upgrades, if any, affect the target service date.
The water statement must identify the intended provider and confirm that water resources are sufficient for the site without harm to other users. Ask which phase, cooling design and water demand the utility evaluated. Under §IV.E.8.e.2, the Town may enter a development agreement with the developer or end user to define reclaimed-water infrastructure and use. If the design relies on reclaimed water, ask whether there is such an agreement and who will build and pay for the infrastructure.
Match the records to your option, closing or rent date
Put the relevant permit and the two statements alongside the milestone in your agreement. For example, if a buyer asks for an option extension to get the building permit, ask whether both statements have been issued, whether the Town has accepted each statement for that phase, and the expected date for any outstanding submission. If rent starts at construction, check the lease’s actual trigger and ask for the permit and project schedule that support the forecast.
A will-serve statement serves as evidence for the building permit. For an expected service date, request the relevant utility agreements or schedules and check any upgrades, deposits or easements those documents identify. If the campus changes its electric load, cooling design, water demand or phase schedule, agree who will ask the utilities and the Town whether either statement needs to be refreshed and who will provide the updated records before your next deadline.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landShare your property or existing agreement
Sunland accepts data center land sale, lease and existing-agreement inquiries from owners and authorized representatives anywhere in the United States. Sunland may put a property under contract and assign the agreement to a specialist developer. Share the general location, your role, the transaction you are considering and any upcoming decision date. Arrange private follow-up for utility correspondence and transaction documents.
Questions landowners ask
Does the rule apply to every industrial parcel in Sahuarita?
Section IV.E.8.e applies in the Rancho Sahuarita Specific Plan’s Park Industrial area. Give the Town the parcel number and ask which plan and standards govern it before using this permit checklist.
When does the Town need both statements?
Section IV.E.8.e.1 requires the statements before the Town issues building permits for a data center or associated equipment. Ask the Town which permits and phases the current statements cover and whether it requires an update for the proposed work.
Can I use the statements to set a utility delivery date in my agreement?
Check the service schedule and the commitments in the utility documents for the project. Ask which work, approvals or payments still affect delivery, then compare that timeline with the decision or payment date in your land agreement.
Sources & further reading
Sources checked November 22, 2026. Confirm the parcel’s plan designation, the permit phase and the Town’s acceptance of each utility statement for the current proposal. Local rules and program details can change. Check the requirements for the actual project.
- Town of Sahuarita, Rancho Sahuarita Specific Plan, §IV.E.8.e.1–2 and §IV.E.8.e.8
- Town of Sahuarita, data center FAQ and August 2025 interpretation
- Town of Sahuarita, industrial zones code amendment project
- Town of Sahuarita, zoning verification
- Town of Sahuarita, Planning and Zoning and Building Safety divisions