Texas landowner guide

Can a data center tax abatement transfer with a sale or lease?

If a data center sale or lease depends on an existing county tax abatement, confirm which property and obligations the buyer or tenant can take over before setting a price or closing date. Scurry County’s signed agreement with SE DC Gen distinguishes a transfer of an interest in the project company from an assignment of all or part of its abatement agreement.

Could my land work?

Get the signed agreement and any amendments. Match the land, buildings and equipment in the deal to the agreement’s phase records. Ask the County which notices, joinders or approvals the transaction requires, then have counsel confirm which payments and other obligations the seller would keep.

Identify who holds the agreement and what is changing hands

In the Cavender Road agreement, the defined Owner is SE DC Gen, LLC, the entity holding the real property interests and owning the eligible improvements. A landowner dealing with a separate developer should start by comparing the names on the deed, ground lease and signed abatement agreement. Identify the party that can give notice and sign an assignment.

Article XIII(A) allows SE DC Gen to assign the agreement in whole or in part to one or more assignees or permitted occupants. Article XIII(B) treats a sale of interests in SE DC Gen itself as outside the agreement’s assignment and County consent requirements. The company still has to notify the County if its corporate name or the name the project is known by locally changes after that sale. Ask counsel to compare the transaction documents with the actual clause for your project.

Illustration of a landowner reviewing property plans

Put the notice and joinder on the closing schedule

The signed agreement says an assignment takes effect no earlier than 20 days after the Owner gives the County written notice. The assignee or permitted occupant must execute a joinder and deliver it to the County. Article XIV calls for certified or registered mail and treats notice as received three days after mailing. Ask the County Judge’s office which date it will use for the proposed transfer, and put the written confirmation and signed joinder on the closing checklist.

For an eligible occupant seeking the abatement on property it owns, Article IV(J) provides for prospective participation through a joinder. Exhibit D supplies the form. Scurry County’s October 2026 guidelines for property outside city limits allow transfers by Commissioners Court resolution or under the terms of the signed agreement. For your deal, ask the County which process applies and whether outstanding taxes or other obligations need to be cleared.

Match the transferred interest to the phase records

The Cavender Road agreement tracks each phase through real property descriptions, personal property certificates and abatement commencement records. Ask for the filed certificates for the affected phase. Compare the real property survey and equipment list with the scope of the proposed deed, lease or bill of sale. Ask which property qualifies and how much time remains in its abatement period.

Article XIII(A) ends the current Owner’s rights and duties only to the extent they apply to the interest the assignee acquires once it takes the assignment and assumes it. For a partial transfer, write down who will make the payments in lieu of taxes, provide annual compliance records and respond to any open notices. Ask the County and your advisers to confirm what stays with the seller, including any exposure to repayment of previously abated taxes.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Confirm the tax treatment before you close

The County’s compliance certification and the appraisal district’s exemption application are separate filings. The Texas Comptroller’s Form 50-116 calls for an annual application to the appraisal district. Ask the Scurry County Appraisal District who should file for the affected tax year, what proof it needs after the transfer and how the sale or lease date affects the filing.

Agree what happens if the County documentation or other closing evidence arrives late. If you want to discuss a U.S. sale, lease or existing project agreement with Sunland, share the property location, the part of the project involved, and any notice or closing date you already know.

Questions landowners ask

Will a ground lease give my tenant the existing abatement?

Check which party owns the property eligible for the abatement and which party signed the agreement. In the Cavender Road example an eligible occupant can join for prospective benefits by signing and delivering a joinder. Ask the County what your tenant needs to file or sign.

Can a buyer take over only one phase?

Article XIII(A) permits partial assignment. Ask the County to confirm which assets and obligations the proposed transfer covers, and compare its response with the phase certificates and the assignment.

Does the county abatement also cover state sales tax?

The Cavender Road agreement covers specified county property taxes. Scurry County’s guidelines say that local approval by itself establishes no eligibility for a state tax exemption or incentive.

Sources & further reading

Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.