Confirm which approval governs your parcel
Give Vacaville Community Development the project name, parcel number and approval number. Ask for the approval, any amendments and conditions, and confirmation that Chapter 14.09.271 applies. The chapter covers Tier 2 and Tier 3 front-of-the-meter systems permitted and installed in the city after the ordinance took effect. Behind-the-meter systems are outside its scope. The city chapter excludes Tier 2 and Tier 3 systems using lithium-ion batteries or technologies with documented thermal runaway events.
Ask which agency issued the approval. Eligible projects can choose the California Energy Commission’s Opt-In Certification process. If your project has a state certificate, get the certificate and its conditions and confirm which decommissioning requirements govern the site.

Check the net estimate against what was posted
Get the dated estimate from the tenant and ask for three figures on the same version. Start with the gross cost to remove the equipment and carry out the restoration in the plan. Identify the amount credited for salvage or recycling, then subtract that credit to find the net estimate. If the credit is large enough to change your assessment of the security, ask the estimator what supports it and whether transport, disposal and restoration costs are included. The code also calls for a battery disposal plan and assigns responsibility for recovering and recycling battery cells at an authorized facility to the facility owner.
Request the signed assurance instrument, any amendments and dated evidence of posting. The code lists a bond, a parent company guarantee or an irrevocable letter of credit and excludes cash. It lists those instruments in the provision that calls for bankruptcy-related evidence in the form of a bridge policy. Ask the city what it required under your approval and what it has on file. Match the project and tenant named in the records, compare the posted amount with the net estimate and check when the full amount was in place.
Ask the tenant for the record it uses to establish the start of full commercial operation, and ask the city which date and record it uses for the posting deadline. The code calls for submission of the decommissioning plan before permits for decommissioning work are issued. Use the full-commercial-operation deadline to check when the assurance had to be posted.
Decide what the records mean for your lease milestone
Read the lease definition of commercial operation and find the notice, evidence and deadlines for the rent or other milestone you are checking. If the date, amount or posting record is missing or inconsistent, ask the tenant to reconcile it in writing. Have counsel confirm what is due under the lease, including any notice or cure period, before you acknowledge the milestone or respond to a request for more time.
Have counsel read the instrument to identify the beneficiary, who can make a claim or draw and what conditions apply. Check your lease for who must keep security in place, when replacement evidence is due and who covers a shortfall or an expired instrument. If you are relying on bankruptcy coverage, have your insurance adviser review the actual policy and terms for the loss you are concerned about.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your battery storage land or lease
Sunland America reviews battery storage land sale and lease opportunities and potential assignments of existing agreements nationwide. Share your general location, your role and the lease milestone you are checking. Keep signed agreements and financial records for private review.
Questions landowners ask
Does the instrument need to cover the gross removal estimate?
The city’s minimum uses the third-party estimate after deducting salvage or recycling value. Ask for the three figures and compare the net amount with the instrument and any additional requirements in the approval or lease.
What if the lease uses a different commercial-operation date?
Use the date the city recognizes for the posting check. Apply the definition, notice and payment provisions in your lease to determine the private milestone.
Can I draw on the assurance as the property owner?
Check the instrument for its named beneficiary and draw conditions, and have counsel review those terms alongside the approval and your lease. Ask what security the lease gives you directly.
Sources & further reading
The city code and ordinance materials were checked November 21, 2026 Pacific time. Confirm the governing approval, full-commercial-operation date and posting record for your project with the tenant and permitting agency. Local rules and program details can change. Check the requirements for the actual project.