Confirm which application and ordinance apply
Ask the planning office for the application number, route, filing and acceptance records, and zoning ordinance provisions for the site. Section 15.2-2288.8 defines the solar projects it addresses as ground-mounted facilities of at least one megawatt designed to serve, or serving, electricity or thermal needs of other property. Ask whether the project is proceeding under a special exception, is permitted by right or is using a siting agreement.
Chapter 1068 applies to ground-mounted facilities of at least one megawatt with a local approval application filed on or after July 1, 2026. Applications received and accepted before July 1 remain subject to the applicable local ordinances in place when the initial application was filed. Have the planning office confirm which rules it is using for this application.

Compare the proposed distances on both plans
Request the dated plan showing the required setback and the revised plan showing the requested distance. Have the applicant label the affected equipment edge, parcel line and any building used to measure the setback. Subdivision A(1) measures from the nearest equipment edge. For an existing occupied dwelling on nonparticipating property, the reference is the nearest point on its outer wall. A shared line with nonparticipating property has its own setback criterion. Subdivision A(1) exempts internal boundaries between adjacent participating parcels from its setback requirement.
Ask the locality to confirm whether the affected parcel is treated as nonparticipating and to identify any separate road or wetland setback requirements. Check which part of the line or building the waiver would cover, and compare the drawings with your survey and current access or land use. If a drawing uses a fence or an approximate tax map line, ask for the actual reference points used for the application.
Check the signature and the final decision
Ask for the complete proposed agreement and every exhibit. Have counsel check the parcel description, distance, plan revision, duration and what happens if the design changes, the project is assigned or you sell. Check for separate access, screening or maintenance rights in the package so you can review those terms before signing.
Ask the planning office what written agreement it requires for any departure from the ordinance criteria, and who must sign. Obtain the locality’s written decision and the version of the plan it covers. Compare any conditions with the proposed waiver and ask what further review a later design change would require.
| Record | What to check |
|---|---|
| Application record and local ordinance | Filing and acceptance dates, review route and setback criterion. |
| Dated original and revised plans | Affected parcel, equipment edge, measurement point and proposed distance. |
| Written agreement and local decision | Required signatures, exact exhibit, conditions and scope of any approved change. |
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDescribe the proposed waiver when you inquire
Sunland welcomes nationwide inquiries from landowners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the general location, your role and whether a proposed waiver affects your land. Keep surveys and draft agreements for private review.
Questions landowners ask
Does every Virginia solar project use this waiver process?
Ask the locality how the facility is classified, when its application was filed and accepted, and which local approval route and ordinance apply.
What if the developer moves the panels after I sign?
Compare the new plan with the dated exhibit and terms in the written agreement. Ask the locality and counsel whether another signature or a revised local decision is needed.
Does a signed waiver settle whether the project is approved?
Check the locality’s written decision, the approved plan and any conditions. The waiver addresses the setback specified in the agreement.
Sources & further reading
The current Virginia Code and approved chapter were checked November 21, 2026. Confirm the actual application records, ordinance, plan and decision with the locality. Local rules and program details can change. Check the requirements for the actual project.