Wisconsin landowner guide

What if a Wisconsin solar access notice affects land you plan to build on?

You are planning a barn when a neighboring solar project sends notice of a solar access permit application. The proposed restriction may affect where you can build or plant. Keep the notice and record when you received it so you can decide whether to ask for a hearing.

Could my land work?

Under Wis. Stat. §66.0403, a recipient may file a hearing request within 30 days after receiving the formal notice. Ask the agency for the application, the affected property description and the local ordinance. If you already have building plans, gather your dated permit application, design expenses or other evidence of substantial progress. Before a sale or lease, check the actual agency decision and any recorded restrictions.

Confirm which notice you received

Section 66.0403 allows eligible municipalities to provide for solar access permits. The process can protect sunlight by restricting development or planting on specified nearby property. Ask the agency named in the notice whether the municipality provides for this permit, whether your land is within its jurisdiction and which version of the application is on file.

After the agency finds the application satisfactorily completed, the applicant sends or delivers the notice to the owners of land it proposes to restrict, using certified mail or hand delivery. The applicant files signed receipts with the agency. Keep the notice, its attachments and your receipt or proof of delivery. A solar installation approval and any request for a private easement have their own documents and processes.

Illustration of a land parcel and surrounding landscape

Use your receipt date to check the hearing deadline

Section 66.0403(4) gives a notice recipient 30 days from receipt to file a hearing request. Follow the filing procedure shown on the notice and confirm receipt with the agency. The agency can also determine on its own that a hearing is needed.

When a hearing is requested or the agency finds one necessary, the statute calls for a hearing within 90 days of delivery of the last notice. The agency gives the applicant, notified owners and other hearing requesters at least 30 days’ notice of the hearing. Ask the agency to confirm both the dates in its file and how to submit any exhibits.

Date to findWhat it affects
When you received the noticeYour 30-day hearing request window and the timing of any building permit application you want the agency to consider.
When the last notice was mailed or deliveredTiming of the statutory exclusions for certain structures and previously planted vegetation.
When the last notice was deliveredThe agency’s 90-day period for a hearing if one is requested or needed.

Show the agency what you were planning

Section 66.0403(5) makes existing building plans part of the permit decision if the structure would create impermissible interference as the statute defines it. The statutory ways to show present plans include applying for a building permit before receiving the notice, spending at least $500 on planning or design, or providing other credible evidence of substantial planning or construction progress. The agency also considers local land-use plans and whether benefits exceed burdens.

For example, if a proposed barn appears in the area that could shade the panels, gather the dated drawings, dimensions, invoices and any application receipt for that barn. Compare the site and height with the collector location and ask the agency what it needs to evaluate the potential interference. Ask whether it can address the burden through a change in collector location, a condition or an exemption.

Tell the agency about any existing building, work already under construction, earlier permit application or established windbreak. The definition in §66.0403(1)(f) excludes certain structures based on their status before the last notice was mailed or delivered. It also generally excludes vegetation planted before that cutoff unless the local ordinance includes it. If the ordinance includes that vegetation, §66.0403(2)(b) places the trimming cost on the permit holder. Bring dated records and have counsel review the application and ordinance before changing the property. Section 66.0403(7) addresses damages for some interference associated with pending applications as well as granted permits.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Read the decision before committing the land

If the agency grants the permit, it identifies the restricted property and prepares a notice of the grant. The applicant records that notice with the county register of deeds for the specified properties and the land with the collector. Compare the permit and recorded notice, including all parcel descriptions and conditions, with the land you would sell, lease or retain.

Section 66.0403(11) preserves rights and duties under the statute and applicable ordinance when title transfers. Have counsel check whether a waiver or termination was recorded and what any pending application or open issue means for the sale, lease, access or construction timetable. Request an updated title review if the agency decision arrives before closing.

Discuss a solar land sale, lease or existing agreement

Sunland welcomes inquiries from landowners and authorized representatives across the United States about sales, leases and assignments of existing solar agreements. Share the general location and whether a solar access notice affects the property. Keep your notice, title records and building plans for private review.

Questions landowners ask

When does the 30-day hearing request period start?

Under §66.0403(4), the period starts when you receive the formal notice. Confirm the actual date and filing instructions with the agency.

Can I show plans for a barn if I do not have a building permit?

The statute also lists at least $500 spent on planning or design and other credible evidence of substantial progress toward planning or construction. Ask the agency how to submit your dated records and explain where the barn would sit.

What happens to a recorded solar access restriction when I sell?

The statute preserves the rights and duties when title transfers. Have the title company and counsel check the recorded notice, property description and any recorded waiver or termination before closing.

Sources & further reading

Wisconsin’s official current statute and certified Chapter 66 were checked November 20, 2026. Use the actual notice and current local ordinance to confirm the procedure, affected property and supporting records. Local rules and program details can change. Check the requirements for the actual project.