Identify the connection before discussing a lease
Ask where the proposed battery would connect and what it would do. Would it serve an existing building, export through a distribution connection or connect to a transmission line? Also identify where its charging power would come from. A description such as “TEP project” does not answer those questions.
TEP’s generation directory separates transmission and distribution routes. Have the developer identify the route that applies to its design and explain how the utility has confirmed it. Do not select a route for the company based on the capacity mentioned in an offer.
If you have a building on the property, an electric bill can help identify the existing service. It is not proof that the same service can support a separate battery facility. Ask whether the project needs a new account, different service equipment or a different connection point.
Put the developer’s explanation beside the site drawing. The proposed connection might require a cable route, access or utility work beyond the battery area. Those rights should be described before you reserve a broad part of the property.
Reference: TEP: generation interconnection routes

Check which storage document the proposal relies on
TEP’s electric-service directory links SR-710, titled as requirements for distributed energy storage systems on single-phase service. Its applicability section specifies single-phase, 120/240-volt, three-wire services. It should not be presented as the complete application route for a large transmission-connected facility.
The standard includes a section called “Stand Alone Energy Storage Systems.” In that section, the system is connected to a service without a distributed-generation system. That wording does not turn the document into a universal approval for a battery development on vacant land.
If a company shows you this standard, ask which service and design it is applying it to. If the proposal is larger or uses a different electrical arrangement, request the requirements that actually cover that arrangement. The utility response should address the battery’s charging, export and controls.
The directory also warns that the annual printed service book does not include later revisions. Ask for the applicable current standards and a dated utility response rather than relying on a saved book alone.
Reference: TEP: SR-710 single-phase energy storage requirements; selected pages 1, 4, 5 and 15 · TEP: electric service requirements and revision directory
Request findings, not just a study number
TEP’s large-generation overview describes application review, site-control evidence and a study process. An application or study queue number identifies a stage; it does not, by itself, show that the connection has been approved or that a company has committed to build.
Its system-impact overview describes reliability analysis and high-level estimates of cost responsibility and construction time. If the developer says that study is complete, ask what it found for this project. What work is needed, what conditions remain and does the studied design match the current proposal?
A useful update names the record, its date and the next unresolved step. You do not need to interpret engineering calculations to ask whether the proposed charging and discharge were covered, whether the connection point changed or whether another study is needed.
The linked tariff could not be read during this source check. This guide therefore does not quote deposit amounts or fixed study deadlines from the overview. Get current requirements and project-specific dates from the responsible team and utility.
Reference: TEP: large transmission-generation application and studies overview · TEP: system impact study overview
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMap the connection work outside the battery area
TEP describes a facility study as estimating the equipment, engineering, procurement and construction needed for interconnection facilities and network equipment. It also includes an estimate of the work’s duration. Ask which parts of that work would affect your land.
Request a drawing that separates permanent equipment, cable or overhead routes, construction access and temporary work areas. Identify gates, tenants, farm entrances and delivery routes that must remain usable. If other land is needed, ask who is arranging those rights.
Compare the drawing with the agreement. Would a route remain as a recorded right after the battery lease ends? Could construction occupy land outside the rent area? Who restores damaged surfaces, drainage and fencing? Explain any land you need to keep available.
If the utility work changes the design or cost, ask whether the developer can change the reserved area, extend the option or stop the project. Read those provisions before assuming that a small battery footprint means a small effect on the rest of the property.
Reference: TEP: facility study overview
Keep utility milestones separate from your payment dates
TEP’s agreement overview describes an interconnection agreement following study work. Request the actual signed record and its conditions if a company says that stage has been reached. A connection agreement does not explain what the developer owes you under a private land option or lease.
List your payments for the initial reservation, renewals, construction and operation. Identify the exact event that starts each one. If rent begins only after energization or commercial operation, ask how long the company can hold the property while construction or utility work remains outstanding.
Ask who pays for studies, service changes and connection construction. Would any account or payment obligation be in your name? Does your offer allow costs to be deducted from land payments? Have the proposed documents explain those duties rather than relying on an informal estimate.
If the team withdraws or changes the project, request an explanation of how reserved land and separate rights are released. Keep payment, notice, repair and removal provisions together so you can see what remains after development stops.
Reference: TEP: transmission interconnection agreement overview · TEP: large transmission-generation application and studies overview
For a customer battery, clarify account authority and later changes
If the batteries would be tied to your building, identify the customer account, equipment owner and person responsible for operations. Separate any promised bill benefit from payment for the space occupied. Ask what happens if a tenant leaves or the building’s electricity use changes.
The selected SR-710 review section requires plans and utility approval for covered installations and addresses later changes to equipment and system design. For a proposal using that standard, ask who prepares the plans, obtains written approval and handles a later change. An existing solar approval should not be assumed to cover added storage.
The same standard addresses isolation from the utility during backup operation and customer operating responsibilities. Ask the team what the actual design can supply during an outage and what it cannot. Equipment on the property does not alone establish that your building will receive backup power.
Before giving account authority, understand what the company may request or change and how that authority ends. If a later owner takes over the equipment, ask which account, maintenance and property duties transfer with it.
Reference: TEP: SR-710 single-phase energy storage requirements; selected pages 1, 4, 5 and 15
Tell us about the property and any existing proposal
Start with your contact details and the property’s address or nearby road, county and state. Acreage and parcel number are optional. Include the utility name if you know it, and say whether you could consider a lease, sale or a limited area.
Describe the uses you need to keep: tenant access, farming, parking, deliveries or a planned building. Mention known easements and any existing agreement or deadline. You can summarize another proposal without sending private utility applications or account credentials.
Sunland may follow up for more information. A property inquiry does not reserve your land, submit a TEP application or establish a connection or utility contract. The actual project, site review and private terms still need investigation.
Questions landowners ask
Does TEP’s single-phase storage standard cover every battery project?
No. SR-710 specifies single-phase customer service. Ask for the utility requirements and response covering the actual larger or differently connected proposal.
Does “standalone” in SR-710 mean a large battery on vacant land?
The selected section concerns storage connected to a service without distributed generation. It is not a universal transmission-project approval.
What should I ask when the developer says a study is complete?
Request the dated findings, the design and connection point studied, required work and remaining conditions. Compare those with the current drawing and option timetable.
Would a signed interconnection agreement start my rent?
Your private agreement determines the rent trigger. Ask which event starts payment and how long the land can be reserved while other work remains.
Will batteries on my property provide power during an outage?
Ask about the actual design, isolation and loads served. A grid project or a battery’s presence does not alone establish backup service to your building.
Do I need a TEP application to contact Sunland?
No. Send your contact details and the land’s location. Acreage and parcel number are optional; mention any existing offer or agreement.
Sources & further reading
TEP generation, study, agreement and electric-service directory bodies read October 7, 2026. SR-710 physical pages 1, 4, 5 and 15 text-read; page 1 visually reviewed. The document has page-specific 2019 and 2024 revision dates and is limited to single-phase service. Linked transmission tariff download did not respond; no current tariff, deposit, queue window or fixed study deadline is represented as verified. Confirm the route and current requirements for the actual battery with TEP. Local rules and program details can change. Check the requirements for the actual project.
- TEP: generation interconnection routes
- TEP: large transmission-generation application and studies overview
- TEP: system impact study overview
- TEP: facility study overview
- TEP: transmission interconnection agreement overview
- TEP: electric service requirements and revision directory
- TEP: SR-710 single-phase energy storage requirements; selected pages 1, 4, 5 and 15