What Pennsylvania asked developers to supply
DEP’s April 2026 announcement requested information about generation and storage projects that could enter service quickly. It gave a June 5 response date and discussed possible state sponsorship for PJM’s expedited track. That dated information request does not establish selection, financing or permission to build a particular battery.
If an offer cites the announcement, ask for the developer’s response and any later decision applying to its project. An expression of interest is a starting record. Find out what action followed before accepting a claimed fast schedule.
Reference: Pennsylvania DEP: April 2026 generation and storage request for information

A limited track is not a general promise
PJM’s June 2026 announcement describes a temporary expedited process for up to ten qualifying interconnection requests per year, with state involvement and a minimum 250 MW of unforced capacity among its requirements. It is aimed at large, ready-to-proceed resources, not every proposed battery site.
Do not compare that capacity requirement directly with the nameplate rating on a sales presentation. Ask the project team to explain eligibility under the current tariff and produce the relevant application or acceptance record. A nearby substation and an available field do not establish entry to the track.
Reference: PJM: June 2026 expedited interconnection track announcement
Ask for evidence of the stage being claimed
Have the developer identify whether it is investigating eligibility, applying, accepted for study or working under a completed connection agreement. Write down the reference and date. Each stage leaves different work and uncertainty.
Ask which connection point and project design the evidence concerns. If the developer later moves the site or changes the project, find out whether the old record still applies. A faster process for another design may not support the offer now in front of you.
- Name of the actual review track
- Project reference and current stage
- Connection point and proposed design
- Remaining work and responsible parties
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landElectrical timing is only part of your reservation period
A study schedule does not include every task needed to build a project. Ask about land-use review, environmental investigation, financing, equipment and access. Identify which steps can run together and which depend on an earlier result.
Compare that explanation with the option term. Find out how extensions work, what is paid during each stage and what releases the property if the schedule slips. An optimistic grid timeline should not leave you guessing how long other plans must wait.
Keep the local property questions in the discussion
Include the township, borough or city, not only the county or mailing address. Explain the area you could make available and the uses you want to retain. Ask for a drawing that includes cables, roads and temporary construction areas.
If a shared lane, drainage feature or another parcel is involved, say so early. A regional study process does not secure those private rights. Ask who investigates them and what happens if the final route cannot be obtained.
You can inquire without choosing an interconnection track
Send the property location and contact details to Sunland. Add the current use and available area if known. If you received a fast-track claim, mention the project name and the record used to support it.
You do not need to determine eligibility yourself before asking about the property. Further review must establish the correct connection route, approvals and commercial fit. A public initiative can guide the questions without guaranteeing a deal or construction date.
Questions landowners ask
Does the DEP information request award a battery project?
No. It requested information. Ask for subsequent project-specific decisions.
Can any small battery use the expedited track described by PJM?
No. The cited process has substantial project eligibility requirements. Confirm the actual current route.
Does an expedited connection process remove local site review?
Do not assume that. Ask which site and construction decisions remain for the actual proposal.
Sources & further reading
Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.