Duquesne Light / Pennsylvania

Battery storage land in Duquesne Light’s service area

If a company says your property has electric service available, ask what has actually been checked for its proposed battery.

Could my land work?

A general service-availability letter is an early planning document. Duquesne Light says its letter does not specify service design, construction needs, timing or cost. For a battery proposal, ask the project team to explain charging and export separately, identify the current application route and show what remains unresolved before your land is reserved.

Find out what the letter actually covers

Duquesne Light describes its Letter of Availability as general confirmation that it can provide power to an address or parcel. It is for planning and information; the utility expressly leaves construction requirements, service design, project timing and cost estimates out of that letter.

If a developer presents one, request the complete letter and the description of the project used to obtain it. Does it identify your parcel? Does the proposed battery match what the company described? Ask which further documents support any claim about the size or cost of the connection.

Keep the letter with the proposal, but ask for the missing answers before treating the electric work as settled. The presence of a line, meter or nearby substation also needs a project-specific explanation. None tells you by itself how the intended battery would connect.

Model landscape illustration of battery storage sites and an electrical substation connected by roads and power lines.

Ask about electricity coming in and going out

Have the company explain the battery’s purpose in ordinary language. Would it serve an existing business, supply backup power or discharge to the grid? Who would control its operation, and whose electric account would be involved?

Then ask how it would charge and how it would discharge. Those are separate questions worth putting in writing. Ask the team to identify the current review process for its actual configuration and the work needed before it can operate.

Duquesne Light’s service-request page separates new, upgraded and temporary service and links separately to interconnection resources. A work-order number or a service request should be described by the step it records. Ask for the specific approval behind a claim that the battery connection is ready.

You do not need to select the electrical arrangement yourself. An owner can provide the property location and existing utility information while the project team establishes the applicable route. Do not submit an application or authorize use of an account simply because a land proposal includes a form.

Put electrical work and land rights on the same drawing

Ask for one plan showing the battery equipment, entrance, electrical route and temporary work areas. Mark buildings, deliveries, farm access and land you want to keep using. The space affected may extend beyond the proposed battery fence.

Find out whether a new service route, equipment replacement or utility access would require additional rights. Who asks you to sign those documents? Who pays for the work and repairs disturbed ground? Ask the company to show which rights belong in the battery agreement and which would be requested separately.

If the route is still being studied, ask how the reserved area can change and when it will be narrowed. Discuss whether a cable would cross retained land or a neighbor’s property. The plan should identify who secures those rights and what happens if a necessary route cannot be obtained.

For an occupied property, identify the account holder and existing tenant commitments early. Ask how investigation and construction would be scheduled, whether electrical interruptions are expected and who coordinates with the people using the site.

What you are shownWhat to ask next
Availability letterWhat design, cost and schedule work remains?
Existing electric serviceHow would this particular battery charge and discharge?
A proposed cable routeWhat additional land rights does it require?
A target start dateWhich approvals and construction steps support it?

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Compare unresolved work with the option terms

Request a short list of the remaining steps, their dependencies and who is responsible. Separate utility work, local permits, property rights and the commercial arrangement that supports the project. A target date is more useful when you can see what must happen first.

Ask which electrical costs are preliminary and what happens if further review requires a different design or expensive work. Does the company have a decision deadline? Could it reduce the leased area, seek more land or stop the project?

Compare those answers with the time the option holds your property. Identify the initial term, extension rights, payments during investigation and the conditions that start later rent. The agreement should explain release of the land if the project ends; a planning letter should not substitute for those terms.

If more than one company is involved, identify the entity that owes you money and handles damage, access and eventual removal. Ask what happens if the project is transferred. Have the actual documents reviewed together before you agree.

Start with your contact details and location

Send your name, email and phone first, then the property address or road, municipality and county. Pennsylvania is an editable starting selection on this guide. Acreage and a parcel number are optional.

Add Duquesne Light as the electric utility if known, or say that service needs confirmation. Mention the property’s current use, a tenant or an existing offer. If you have a service letter or application reference, you can tell us about it without having a finished battery plan.

The inquiry gives Sunland a starting point for follow-up. It does not authorize entry, reserve the property, apply for utility service or commit you to a lease or sale. The proposed connection, layout, permissions and commercial fit still need review.

Questions landowners ask

Does a Letter of Availability establish the battery’s connection cost?

No. Duquesne Light expressly excludes cost estimates, service design, construction needs and timing from that general letter.

Should I apply for service before asking about my land?

You can inquire with the location and information you have. Have the project team confirm its actual arrangement and application requirements before authorizing an application.

What should I ask if my property already has a meter?

Ask how the proposed battery would charge and discharge, whose account it would use and what additional review or work is needed.

Can the electrical route affect land outside the battery fence?

Ask for a drawing of the entrance, cable route and utility equipment, including any temporary or continuing rights across retained land.

Do I need an acreage figure or parcel number to inquire?

No. Start with contact details and the property location; those property details are optional.

Sources & further reading

Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.