What the borough records tell an owner
The mayor’s message in the 2026 borough guide reports the first battery project operating and describes a second project expected that year. That statement is a dated update, not confirmation here of the second project’s current completion.
The adopted May 2024 minutes record a contract award for an additional battery system on borough property. A separate 2021 fence drawing is stamped for review, not construction. Those records establish different stages; none approves a battery on your private parcel.
Use a local project as a starting point for questions, rather than as a price comparison. A municipal project can have a different property arrangement, power contract and purpose from a developer’s offer to you. Ask what evidence supports the specific proposal you are being asked to consider.
Reference: South River: 2026 borough guide, mayor’s electric-utility update on PDF page 3 · South River: adopted May 13, 2024 minutes, Resolution 2024-200 on PDF pages 48–50 · South River: 2021 battery fence layout, issued for review—not construction

Identify who would connect the battery
South River publishes its own Electric Utility resources. Have the project team confirm the utility and connection process for the actual property. Do not select a neighboring utility’s application simply because another project uses it.
Ask where the battery would take power from and where it would send power. Would it use an existing building’s service, a separate connection or an arrangement involving the municipal system? Request a drawing that identifies the proposed connection point and any route outside your property.
Find out who would be the applicant, account holder and party paying for studies or upgrades. Ask which findings remain preliminary and whether connection work could change the area requested from you.
Permission to investigate a connection should have a stated scope. Ask what documents your name would appear on and what the developer needs you to sign. Providing property information to Sunland does not authorize a utility application or reserve the site.
Reference: South River: Electric Utility resources
Separate your compensation from energy savings
A project may be described as saving money on electricity. Ask whose bill or power costs it would reduce and whether any of those savings would belong to you. A payment for using your land and a credit on an electric bill are different promises.
For a lease offer, identify option payments, full rent, extension costs and the event that starts each payment. If compensation depends on performance or savings, ask how it is calculated, who supplies the records and what happens during an outage.
Consider a commercial property with a tenant paying the electric bill. The tenant might benefit from an energy arrangement while the owner provides land or access. Have each party’s rights, costs and approvals explained before treating the proposal as a benefit to both.
Do not estimate rent from the borough’s reported savings. Your price would depend on the actual rights requested and the commercial proposal. Ask for terms you can compare, including the period when land is reserved but no equipment is operating.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landShow the working site outside the fence
The borough’s published review drawing shows equipment, gates, property lines and surrounding streets together. It is a useful reminder to ask for a complete layout for your own proposal. Its dimensions are not a rule for your property.
Show loading areas, customer parking, tenant entrances, utility access and the route emergency vehicles would use. An equipment pad can look compact while its access arrangements interfere with a use you need every day.
Ask which routes would be shared, which areas would be restricted and where construction trucks would wait. If work temporarily removes parking or blocks a delivery route, agree on the timing, notice and replacement arrangements.
Distinguish permanent equipment rights from temporary construction space. Ask how pavement, fencing, drainage and landscaping would be repaired when work finishes. Price and document any continuing right to cross land you otherwise retain.
Reference: South River: 2021 battery fence layout, issued for review—not construction
Ask what local review remains
The borough’s forms directory links construction-code forms and site-plan, variance and technical-review application packages. The directory does not by itself decide which approvals a battery proposal needs.
Have the project team establish the review route with the appropriate officials for its design. Ask for the actual application, parcel identification and status when a filing exists. A drawing prepared for discussion is different from an approved plan.
Keep a copy of the layout you are considering and ask to receive revisions. If review moves the entrance or requires a different area, decide how that change would be accepted and compensated before it becomes part of the land agreement.
Compare public review milestones with the option deadlines. Know how long the developer can hold the site, whether an extension requires another payment and how recorded rights would be released if the project stops.
Keep responsibility clear after a transfer
Ask who would own the equipment, operate it and hold the agreement with you. Those parties may differ, and a project can change hands between early development and operation.
Request an operating contact for a blocked entrance, damaged fence, noise concern or maintenance problem. Ask how that contact would be updated and which company remains responsible for repair and payments.
Discuss removal before installation. Identify what would be taken away, what condition the land should be returned in and how the work would be funded. A municipal contract award does not establish removal protection for your private agreement.
If a tenant or business needs to remain on the property, have the transfer terms preserve the access and responsibilities that make the arrangement workable. Do not leave those details solely in conversations with the original project representative.
Send the property location to begin
Start with your contact details, then the property location. New Jersey and Middlesex County are selected in the form and can be changed. Approximate acreage and a parcel number are optional.
Mention the property’s current use, a tenant, the utility shown on a bill or an existing offer if known. You do not need a finished electrical study to contact Sunland.
We can review the information supplied and identify what needs to be checked next. An inquiry does not commit you to a lease, sale or energy contract.
Questions landowners ask
Does a municipal battery mean someone wants to lease my property?
No. Borough project records do not establish a private land offer. Your site needs its own commercial and connection review.
Can I use reported municipal savings to estimate my rent?
No. Energy savings and compensation for property rights are different arrangements. Ask for the payment terms of the actual offer.
Does the borough’s old site drawing approve my layout?
No. It concerns another site and is stamped for review. Establish the current review route for your proposal.
Can I inquire about a property that has tenants?
Yes. Describe the current use and access needs if known. Contact information and location come first; acreage and parcel details are optional.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- South River: 2026 borough guide, mayor’s electric-utility update on PDF page 3
- South River: adopted May 13, 2024 minutes, Resolution 2024-200 on PDF pages 48–50
- South River: 2021 battery fence layout, issued for review—not construction
- South River: Electric Utility resources
- South River: building and zoning forms directory