Locate the proposed work, not just the mailing address
The Highlands region includes parts of Bergen, Hunterdon, Morris, Passaic, Somerset, Sussex and Warren counties. That does not put every property in those counties under the same review. NJDEP distinguishes the Preservation Area from the Planning Area. Start with the municipality, block and lot and ask the team to confirm where the proposed work falls.
Have the developer mark the batteries, entrance, electrical route, drainage work and temporary construction area on one drawing. Ask whether the review covers all of that work. An explanation about the equipment pad may leave out a road or cable route across another part of your property.
If a boundary crosses the land, ask how the project team checked it and which office can confirm the applicable process. Keep the dated map and written response with the drawing. A county name or a shaded regional map is a starting point for that question, rather than a property decision.

Ask what each letter or decision actually does
The Highlands Council’s project-review page states that the Council does not issue permits. It reviews certain proposals for consistency with the Highlands Act and Regional Master Plan. NJDEP is the permitting agency described on that page. Ask the developer to separate Council review, environmental permits and local land-use decisions when explaining its progress.
For major Highlands development in the Preservation Area, NJDEP describes an approval route or an applicability determination concerning an exemption. Ask which route is proposed for the actual battery design and request the written response. Do not accept an exemption claim without knowing the property and work it covers.
NJDEP also explains that an exempt project may still fall under other environmental rules. Ask the team what remains to be checked for wetlands, flood hazards and local zoning. A favorable answer to one question should come with a clear list of the unresolved ones.
Keep the document name, date, applicant, property identification and conditions together. If the company says a step is finished, ask for the document and the drawing it addresses. If it has only requested a decision, discuss how that uncertainty affects the time it wants to hold your land.
| What you are shown | What to ask |
|---|---|
| Regional review letter | Which proposal and drawing does it cover? |
| Applicability or exemption determination | What work was considered and what remains? |
| Resource-area determination | What resources were confirmed, and where? |
| Permit or local decision | What conditions affect my land and access? |
Understand a resource report before paying for more work
NJDEP describes a Highlands Resource Area Determination as a way to seek concurrence and verification of environmental resources on a property. It also describes pre-application conferences. Ask the developer whether either step is useful or required for its proposal, who would arrange it and what question it would resolve.
An older environmental report can help a first discussion, but ask whether its boundaries and proposed use match the new battery layout. A report for a former building plan should not quietly become an assurance about a new entrance, a larger disturbed area or electrical works.
Before anyone orders studies in your name, agree who pays, who receives the results and whether you would owe anything if the company stops. Request copies of work concerning your property. Discuss whether those records would be useful to you after the option ends.
Study access also needs an agreement. Ask who enters, what equipment they bring, whether vegetation is disturbed and how gates, tenants and working fields will be handled. Identify the repair process before drilling, excavation or clearing begins.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck how changes affect the land you keep
Ask which findings could move the battery area or change the entrance and drainage plan. Have the developer show the revised layout before you grant additional rights. The land you retain may still be affected by a route, an outfall or a restriction outside the fence.
Review existing recorded restrictions with your adviser. If another restriction is proposed, request its full text and a drawing of the affected land. Ask which uses it limits, who can enforce it and whether it continues after the battery project ends.
Explain your plans for the remainder of the property. A farm entrance, future building area or tenant’s parking may matter more to you than an unused corner. Mark those needs before comparing offers so that a later design change does not consume land you intended to keep.
If the company points to a redevelopment designation or another project as its example, ask how it applies to this parcel and this use. The relevant question is what the actual proposal still needs, not whether a different project received a favorable review.
Put the waiting period and payments in writing
Ask the developer to identify the work it expects to complete during the initial option period. Which agency response, study or connection decision could stop the project or change the requested area? Discuss the schedule alongside the payments for reserving the land.
Check every extension: how long it lasts, what it costs, how notice is delivered and when the reservation finally ends. If review takes longer than expected, your agreement should still explain what you receive while the company holds the rights.
Name the event that starts rent. A regional review, environmental approval, construction and operation are different milestones. Ask what payment applies between them and whether any payment depends on an event outside your control.
Agree how unused land is released and how study or construction damage is repaired if the project stops. Have your adviser review recorded rights and restoration duties together. You should know who is responsible for clearing those obligations, including after a project transfer.
Ask about the property information you already have
Start with your name, email and phone, then the property location and county. Add the municipality and block and lot if known. Acreage and a parcel number are optional. You can contact Sunland before you know which Highlands area applies or have a development plan.
Mention an offer, regional correspondence, environmental report or recorded restriction that you already have. Tell us which land you might consider making available and which uses you need to protect. An existing document is useful context; you do not need to commission a new study to make an inquiry.
Submitting the form begins a property discussion. It does not reserve land, grant entry or authorize an agency application. The actual design, applicable reviews, electrical connection and commercial terms still need to be established.
Questions landowners ask
Does being in a Highlands county settle the review route?
No. Locate the actual parcel and proposed work, including whether they fall in the Preservation Area or Planning Area.
Does a Highlands Council review replace permits?
No. The Council says it does not issue permits. Ask which environmental and local decisions the actual proposal needs.
Does an exemption settle every environmental question?
NJDEP says exempt projects may still be subject to other environmental rules. Ask for the determination and the remaining review list.
Is a resource-area determination permission to build batteries?
Ask what the document confirms. NJDEP describes this determination as verification of environmental resources; project approvals remain a separate question.
Can I inquire before ordering a study?
Yes. Start with contact information and the land’s location, and mention the records you already have.