Start with the proposal for your property
Haddy’s developer describes a 300 MW / 1,200 MWh facility near existing transmission infrastructure. This is a named project with its own site and design. Its scale is not a minimum for Winslow land, and its proximity to substations does not establish spare connection capacity for a neighbor.
Ask what the company approaching you intends to build. Is it a standalone battery, storage serving an existing business or batteries paired with solar? Request the power rating, energy capacity and intended operation in writing.
Share the block and lot if you know them, the current use and any existing utility or access rights. Ask the reviewing office to identify the route for that parcel and proposal, including whether Pinelands review applies.
A property inquiry can begin without a completed engineering design. The next useful step is an understandable sketch and a list of the work needed, rather than a claim that every site near a line will qualify.
Reference: Haddy Energy Storage: developer’s project overview · Winslow: published site-plan review chapter

Read a variance record separately from construction permission
The December 10, 2025 township packet includes Haddy resolutions describing use and height relief for 519 Erial Road, Block 2101, Lot 36. The posted variance copy leaves its certification signatures blank and requires site-plan review before construction or operations. Request the current certified decision and later approvals for any proposal you are evaluating.
A decision should identify the actual property, applicant and relief. Ask which conditions are complete and which remain. A hearing, application listing or plan presentation is not enough to explain what the company may build today.
If someone sends you a decision for a different site, ask why it is relevant. It may help illustrate a review question, but it does not grant your property the same rights.
Keep public approval authority separate from private permission. Ask your adviser what an application signature authorizes and which entry, testing, reservation or long-term rights require their own agreement.
Reference: Winslow December 10 packet: Haddy variance resolution ZR2025-036 · Winslow: official agenda and minutes directory
An approval extension does not explain your option payments
The posted Haddy extension resolution describes three consecutive one-year extensions, tied to publication of the approval notice, while retaining site-plan requirements. Its certification signatures are also blank. Confirm the operative record and dates rather than relying on this packet copy alone.
For your offer, ask a different question: what does the company pay to keep your property reserved? Have your adviser explain the option’s original term, extension rights, required notices and payments. Do not assume a public extension changes your agreement.
Put the dates side by side. If a review takes longer than the original hold, can the company extend automatically, must it pay, or does it need your agreement? Is there a final outside date after which the reservation ends?
Ask what evidence of progress you receive during the wait. Agree on a practical update schedule and identify who answers questions. A plan to begin construction several years away should be reflected in clear private terms.
Reference: Winslow December 10 packet: Haddy extension resolution ZR2025-036A · Haddy Energy Storage: developer’s planned timeline
| Date or event | Question for your agreement |
|---|---|
| Initial reservation ends | When must the company act or release the land? |
| Extension is requested | What notice, payment and consent are needed? |
| Approvals or studies change | Does the private term change, and how? |
| Long-term rent starts | Which clearly defined event triggers payment? |
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUnderstand what you can do during the wait
List the activities you want to continue: farming, renting a building, using an entrance, making repairs or marketing retained land. Ask which ones the proposed reservation would limit.
If the company wants exclusivity over the entire parcel, ask why that area is needed. Could unused portions be released after the layout is established? Discuss whether access, cables or screening would still restrict the land outside the equipment fence.
For site visits and testing, decide how much notice you receive, where vehicles may go and which activities are permitted. Who repairs a rut, damaged fence or disturbed field if the project does not proceed?
Ask how the reservation is released when it ends. If any document will be recorded against the property, have your adviser explain the release process and who pays for it. An unanswered expiration question can complicate a later sale or financing.
Use a complete drawing to compare the land commitment
Winslow’s published site-plan details call for existing and proposed easements, rights-of-way, encumbrances and the full lot, even when only part is involved. Ask the company to explain those areas alongside the lease or purchase description.
Identify the equipment area, road, cable route, drainage features, screening and temporary work space. Is each area leased, purchased, covered by an easement or subject to a temporary right? What payment covers each?
If an area is described as future expansion space, ask when the company may use it, how you would be notified and whether the payment changes. Decide whether you can use it beforehand and what condition it must be in when released.
Compare the drawing with your plans for the remaining property. A boundary that leaves a building outside the project can still affect its entrance, utility access or room for future improvements.
Reference: Winslow: published site-plan review chapter
Ask what the environmental record actually establishes
The February 4, 2026 NJDEP Bulletin lists Haddy’s freshwater-wetlands letter-of-interpretation verification application as administratively complete on January 15. That dated milestone does not establish a final wetlands decision or construction permission.
For your land, ask which environmental studies and decisions exist and what each covers. Request the actual document and its drawing. Are the equipment, road, drainage work and cable route all within the area reviewed?
Discuss what happens if a study reduces the usable area or requires a different route. Does the company need more of your property? Can you review a revised drawing and terms before granting added rights?
Identify who pays for investigation and any proposed mitigation. Avoid letting a broad promise to handle development leave responsibility for off-site land, testing damage or later restoration unclear.
Reference: NJDEP February 4, 2026 Bulletin: Haddy application milestones on page 36
Connection evidence needs its own timetable
Ask the company to identify the proposed connection point and the utility or system operator reviewing it. What has been requested, what study results have been received and which agreements remain?
Have the developer explain any outstanding upgrades and costs in plain language. If the connection route crosses another property, ask who secures the rights and what happens if that route is unavailable.
Compare the connection schedule with the paid hold and expected rent start. A completed local review does not explain an unfinished electrical connection, financing or construction step.
Another project’s plan or nearby infrastructure can be useful context. Your offer still needs evidence for its own proposed connection and an agreed way to handle delay.
Keep maintenance and removal obligations clear through a transfer
Ask which company signs the agreement, which one would operate the site and whether a transfer is expected. Decide how you receive updated contacts and confirmation of responsibility.
Discuss who maintains access roads, screening and drainage and who handles damage or a noise concern. Compare those private duties with any public approval conditions; neither should be assumed to cover every owner concern.
For the end of the project, identify what must be removed or retained: batteries, foundations, cables, roads, fences and plantings. Agree on the condition you expect and the timing of restoration.
Have your adviser review the protection supporting those obligations if operations stop, the company fails or the project changes owners. Ask who can claim against that protection and what costs it actually covers.
Tell Sunland about your Winslow property
Start with your contact details, then the property location. New Jersey and Camden County are selected and can be corrected. Acreage and parcel number are optional.
Mention the current use, any offer or drawing and what you want to keep doing on the land. If the proposal involves a long hold, include the dates you have been given and your priorities for payment and continued use.
Sending the form does not reserve the property, grant access or authorize a permit application. It gives Sunland a starting point for discussing the land with you. Sunland is not presenting the Haddy project as its own development.
Questions landowners ask
Does Haddy’s schedule apply to another property?
No. It is the developer’s plan for its named project. Another proposal needs its own review, connection and land-agreement timetable.
Does a public approval extension mean my option extends?
Do not assume that. Have your adviser explain the private agreement’s term, notices, extension rights and payments.
Should I include land outside the battery fence in the review?
Yes. Roads, cables, screening, drainage and temporary work can affect the area you keep. Ask for all requested rights on one drawing.
Do I need acreage or a parcel number to inquire?
No. Start with the location and what you know; both fields are optional.
Sources & further reading
Sources checked 2026-10-07. Local rules and program details can change. Check the requirements for the actual project.
- Haddy Energy Storage: developer’s project overview
- Haddy Energy Storage: developer’s planned timeline
- Winslow December 10 packet: Haddy variance resolution ZR2025-036
- Winslow December 10 packet: Haddy extension resolution ZR2025-036A
- Winslow: official agenda and minutes directory
- Winslow: published site-plan review chapter
- NJDEP February 4, 2026 Bulletin: Haddy application milestones on page 36