Milltown, New Jersey

Battery storage on Milltown property

Milltown has authorized a battery lease on borough land. A private offer needs its own terms, layout and connection review.

Could my land work?

Milltown adopted Ordinance 25-1570 in July 2025, authorizing a 15-year lease for a battery project on part of borough-owned property. It is a useful local example of land rights being documented separately from a services contract. The ordinance does not include the full lease or establish rent for privately owned property. Ask what a company wants from your site and what its written offer would pay you.

Read the authorization beside the actual lease

The adopted ordinance identifies an approximately 140-by-200-foot portion of borough property at Block 60, Lot 5.062. It authorizes the mayor and clerk to execute lease documents acceptable to the borough attorney. The document also refers to a separate contract for storage, dispatch and maintenance services.

The three-page ordinance does not attach the signed lease, rent schedule or complete operating terms. It does not establish here that the facility is operating. If a company refers to this project, ask which record supports the claim it is making.

For your own offer, request the complete agreement and every attached drawing or schedule before comparing prices. A summary might describe a monthly payment but leave out an extension right, an access corridor or a cost assigned to you. Make sure the documents describe the same property and proposal.

Ask for a short explanation of each document you would sign. Is it permission to study the site, an option, the lease itself or an agreement about electricity? Know which signature reserves your land and which starts a continuing obligation.

Reference: Milltown: adopted Ordinance 25-1570, authorization of a 15-year battery project lease

Model illustration of a landscaped community beside a battery storage site.

Separate payment for land from payment for services

A proposal that combines land use with battery operation can contain several financial arrangements. Ask the company to list each one separately: payments to you for the site, charges for services, savings on an electric bill and any payments tied to operating results.

Would you receive fixed rent regardless of how often the battery operates? If part of your compensation depends on dispatch or savings, ask who measures it, what records you receive and how a disagreement is resolved. Ask what happens when equipment is unavailable or the expected savings do not arrive.

If a tenant holds the electric account, establish which benefits and bills belong to that tenant and which belong to you. A lower tenant bill is not automatically income to the owner. Decide whether either party must remain in place for the arrangement to work.

Request the costs as well as the benefits. Who pays for electricity used to charge the battery, connection studies, upgrades, insurance and maintenance? Would any charge pass through your account? A projected saving is easier to assess when the proposal also identifies the costs you could bear.

Part of the offerWhat to ask
Land paymentWhat is fixed, when does it start and can it change?
Energy arrangementWhose bill or account is involved?
Operating paymentWhich results are measured and who reports them?
CostsWhich obligations could remain with the property owner?

Use the borough footprint as an example, not a sizing rule

The dimensions in Milltown’s ordinance describe its particular leased portion. They do not establish the space required for another design. Ask for your own drawing showing the equipment area and every right requested outside it.

Mark cables, gates, vehicle routes, drainage work and temporary construction space. Would a delivery cross a tenant entrance? Would the operator need access through a yard you use for storage? Would maintenance require parking or a work area beyond the fence?

If the developer wants the layout to remain flexible, ask how revisions will be presented and accepted. Identify changes that would require your agreement, such as occupying more land or moving an entrance. Make the payment and restoration arrangements clear for temporary areas too.

Walk through the drawing with the person who uses the property day to day. A plan can leave enough square footage while still disrupting deliveries, customer parking or access to a building. Explain those needs before the team settles on a layout.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Confirm the connection process for a municipal electric system

Milltown’s utility page says the borough owns and operates its electric distribution system. Confirm the provider for the actual property and the process for the proposed battery with the project team. A neighboring utility’s paperwork is not proof that the same route applies here.

Ask whether the proposal uses an existing building account or needs a separate connection. Identify the applicant and the party responsible for studies and upgrades. Request the connection drawing and any written findings rather than relying on the presence of nearby wires.

Find out whether the electrical work needs additional property rights. A cable route or new equipment could affect land outside the battery area. Compare that work with the lease drawing and ask who will obtain any third-party permission.

Keep permission to discuss a connection separate from permission to file in your name. Ask exactly what owner authorization the company needs and what it covers. Sending Sunland your property details does not authorize an electrical application.

Reference: Milltown: municipal electric distribution system and utility departments

Establish local review for the proposed use

Milltown’s Planning Board page explains that the board also performs Zoning Board of Adjustment responsibilities. It links site-plan and variance application resources. That page does not determine the approval route for every battery design.

Have the team identify the property’s zoning and explain the proposed use to the appropriate local officials. Ask which applications and decisions are needed for the equipment, access and associated construction. Keep copies of any decisions and the plans they cover.

A lease for borough land does not grant permission for a battery on a separate private parcel. If a company says the public project establishes a precedent, ask which current rule or decision supports its proposed route for your site.

Compare the remaining reviews with the period the company wants to reserve your property. Ask what happens if a design must change or a review takes longer than expected. Know what an extension costs and when the land is released if the project stops.

Reference: Milltown: combined Planning Board and Zoning Board responsibilities and application resources

Agree on the end of the arrangement before the beginning

Ask who will remove the batteries, foundations, cables and other improvements when the agreement ends. List any work you want retained and the condition in which the rest of the property should be returned. Include a way to confirm that restoration is complete.

Review those responsibilities alongside any services agreement. Could the land lease end while an electricity or maintenance obligation continues? Would early termination leave a bill or equipment on the property? Ask the company to explain how the documents work together.

If the project is sold, identify the company responsible for payments, repair and removal after the transfer. Ask how you will receive its contact details and what protection remains if that company cannot perform. Keep these commitments in the written documents.

For an occupied property, discuss what happens when the tenant leaves or the building changes use. Do not assume a battery agreement automatically follows a new tenant or that closing an electric account ends the lease.

Send your Milltown property location

Start with your contact details and the property location. Describe the present use, tenant or offer you are considering if known. Approximate acreage and a parcel number are optional.

Mention the provider shown on the electric bill if you have it handy. You do not need to commission a study or obtain a lease proposal before contacting Sunland. We can use the information supplied to identify questions for further review.

An inquiry does not reserve your property or commit you to a land or energy agreement. Suitability, connection, approvals and commercial terms still need to be established for the actual proposal.

Questions landowners ask

Does the Milltown ordinance include a rent I can use for comparison?

It does not include the rent schedule or full signed lease. Request the actual terms of any offer for your property.

Is every battery site the size described in the borough ordinance?

No. The dimensions concern one leased portion. Your design needs its own complete footprint and access drawing.

Does the municipal lease approve a battery on my land?

No. Establish the review and connection requirements for your own property and proposal.

Can a battery proposal involve both rent and electricity services?

It can. Ask for separate explanations of land payments, energy arrangements, operating payments and costs before comparing the offer.

Sources & further reading

Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in New Jersey?Tell us about your land