Mark the developed area, not just the parcel boundary
The county’s current questionnaire has separate spaces for total parcel acreage and acreage being developed. Use that distinction when talking with a company. A battery proposal may occupy only part of a tract, but its roads, drainage work and electrical route can affect a larger area.
Ask the company to show the equipment, construction access, permanent access, stockpiles and any trenching on one plan. The questionnaire specifically asks about clearing, excavation, trenching, demolition and material storage. Those activities deserve attention before you grant entry or agree to a land area.
Mark the land and uses you want to retain: existing entrances, buildings, fields, drainage routes and any planned use of the remaining property. Ask whether the company needs temporary use of an area that is outside the proposed permanent site, and when it would restore that area.
The form also asks whether the applicant owns the property and requests a concept plan if new tracts are being cut. Establish who may act for you and what they may submit. An authority to research requirements should not leave permission to divide the property or begin work unclear.
Reference: Kaufman County: posted 2026 project questionnaire
| Area or activity | Owner question |
|---|---|
| Permanent equipment area | What land rights would the company receive? |
| Temporary construction area | When is it restored and returned? |
| Entrance and electrical route | Whose easements or approvals are needed? |
| Retained property | How do I keep access and planned uses? |

Treat the county’s first response as information about next steps
Kaufman County offers a project questionnaire to help identify requirements for a proposed development. The webpage says Development Services requires it; the linked 2026 form calls it optional. Ask the office to confirm its current procedure for the actual proposal rather than relying on either statement alone.
The form expressly says providing information is not approval or permit issuance. If a company tells you the county has “looked at the project,” ask what was reviewed and what the response says. A report describing permits still needed is different from an issued authorization.
Section 14 of the posted development rules describes the information for a site-development application: the activity, proposed improvements, existing buildings, access and any related permits under review. It also describes written determinations and further information needed when an application is insufficient.
Have the company identify which process applies to its specific work and keep the resulting documents. Check the dates and expiration conditions of any authorization it relies on. If plans change during an option period, ask how that affects the reviews, your agreed area and the schedule.
Development Services currently lists (469) 376-4127. Its contact page separates engineering, land division, public works, addressing and stormwater questions. The company should route each issue to the appropriate department rather than present one inquiry as clearance for everything.
Reference: Kaufman County: project questionnaire guidance · Kaufman County: posted 2026 project questionnaire · Kaufman County: subdivision and land development regulations, December 2025 posting · Kaufman County: Development Services department contacts
Ask about the battery equipment and its supporting fire access
The county Fire Marshal page addresses unincorporated commercial establishments and public buildings and states that the county has adopted the 2024 International Fire Code with amendments. Confirm the municipality and authority for the actual tract. A Kaufman County mailing address alone does not establish who reviews the equipment.
The separate fire permit fee schedule lists energy storage under construction permits and under operational permits. Ask the Fire Marshal how those categories apply to the proposed equipment, its size and supporting facilities. This guide does not prescribe a battery clearance, fire-water supply or full technical design.
The reviewed amendments also discuss installing or modifying fire-apparatus and utility access roads, with an exception for roads included in site or civil plans submitted under a building permit. Ask the company how the complete entrance and route would be reviewed, including gates and any changes to a shared road.
The amendment provisions for construction documents describe the location, nature and extent of the proposed work and professional design review. Ask who prepares the plans, who answers review comments and who pays for any additional review. You should be able to compare the submitted plan with the land area you agreed to provide.
For fire-review questions, the current county page lists (469) 376-4122. Ask for guidance about the actual proposal; the posted general building and equipment pages should not be treated as a complete outdoor battery checklist.
Reference: Kaufman County: Fire Marshal permits and inspections · Kaufman County: construction permits · Kaufman County: posted 2024 fire-code amendments · Kaufman County Fire Marshal: separately posted permit fee schedule
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAssign the work that continues after installation
An installation permit does not answer every question about operating the equipment. Kaufman County publishes separate construction and operational permit pages. Its separate fee schedule lists an annual renewal category for energy storage, which makes ongoing responsibility a question to settle before signing.
Ask who keeps permits current, arranges inspections, responds to deficiencies and pays renewal or reinspection costs. The separately posted fee schedule and the fee tables appended to the amendment file show different treatment of some operational fees. Have the operator confirm current charges; neither table should be used here as a complete project cost estimate.
The reviewed fire amendments address reporting by licensed contractors performing inspection, testing and maintenance of fire-protection systems. Ask which systems the project would use and who would maintain and report on them. Avoid accepting a vague promise that a construction contractor will take care of everything indefinitely.
The land agreement should identify an operating contact and address repairs to access, gates, fences and drainage, as well as removal and restoration at the end. Discuss how those duties continue if the company assigns the agreement or the project changes hands.
Keep your right to use retained land and your own access practical. Ask how maintenance visits, later equipment replacement and any proposed expansion would be handled. Additional land or a changed route should be addressed before it becomes part of the operating plan.
Reference: Kaufman County: operational permits · Kaufman County Fire Marshal: separately posted permit fee schedule · Kaufman County: posted 2024 fire-code amendments
Clarify whether solar is part of the same proposal
A company may discuss batteries alone or batteries alongside solar. Ask it to state which equipment is proposed on your land and whether an existing or planned solar facility is involved. The answer changes the layout and the questions to take to the county.
Section 12.06 of the posted subdivision and land development rules specifically addresses solar farms. It calls for an infrastructure development plan showing facilities, fire access and drainage, with review by Development Services and the Fire Marshal. Do not assume that this solar-farm procedure establishes every requirement for a standalone battery.
For a proposal that includes solar, the section also addresses screening, reclamation agreements and road agreements where the county commissioner determines they are needed. Ask the company which provisions apply and what additional land, work or obligations they would involve.
The section requires a drainage design and discusses preventing increased flow to downstream areas. Ask for the full proposed drainage footprint and its maintenance responsibilities, rather than looking only at the area occupied by panels or battery containers.
Even when county documents address reclamation or roads, settle the company’s obligations to you in the agreement. Identify what would be removed, what would be restored, who pays and how the work would be funded. A county requirement does not by itself explain every promise the company makes to the owner.
Reference: Kaufman County: subdivision and land development regulations, December 2025 posting
Keep a meter release separate from a battery grid connection
The county’s utility meter release form asks for the property location, utility provider, residential or commercial project type and a temporary, conditional or permanent release. It also asks for contractor details, licenses and inspection certifications.
If a company says it has a meter release, ask what work that release covers and which type it is. The form concerns inspected electrical or gas work; it does not establish available capacity for the proposed battery or approval to charge and export at the requested size.
Ask which utility serves the proposal and where it would connect. Establish what studies, agreements, line routes or station work remain outstanding. An existing meter, a county permit and a nearby power line each leave the project connection question unresolved.
Discuss how that uncertainty affects your option period, extension payments and committed land. If connection studies call for additional easements or a different layout, the company should explain those changes before asking you to accept them.
Reference: Kaufman County: utility meter release form
Start with the property location and what you already know
Use this page’s form to send Sunland your contact details and Kaufman County property location. An address, parcel reference or map location is useful. Tell us whether you are interested in a lease or sale and whether you have a particular area in mind.
Mention existing access arrangements, known easements, drainage concerns, another company’s agreement or a solar proposal already under discussion. Tell us what land and uses you want to keep. You do not need a county application, engineering plan or permit to make this initial inquiry.
Submitting information starts a conversation about the property. It gives no permission to enter, construct or obtain exclusive rights. A later proposal would need review of its actual scope, commercial terms, local requirements and grid connection.
Reference: Kaufman County: Development Services department contacts
Questions landowners ask
Does a county questionnaire response approve the project?
No. The posted 2026 form says the information does not constitute approval or permit issuance. Ask the company what the response identifies as still required and which authorizations have actually been issued.
Is the county questionnaire required or optional?
The current webpage says required, while its linked 2026 form says optional. Confirm the current procedure with Development Services for the actual proposal. Neither statement makes the questionnaire a project approval.
Are battery permits the same as solar-farm approval?
The posted fire fee schedule lists energy storage separately, and the subdivision rules have a solar-farm section. Ask the county which steps apply to batteries alone or to the complete proposal if solar is included.
Who handles inspections and renewals after construction?
Set that responsibility out with the company. The county has separate operational-permit guidance and a posted annual energy-storage renewal category. Ask who maintains applicable systems, responds to deficiencies and pays ongoing costs.
Does a county meter release prove the battery can connect?
No. The release form addresses the type of utility release, contractor licensing and inspected work. The proposed battery needs its own utility connection review, studies and agreements.
Can the project use land outside the equipment fence?
Ask for a plan showing construction areas, entrances, drainage and the electrical route. Establish what is temporary, what rights would be permanent and how your retained land remains usable.
What do I need before contacting Sunland?
Send your contact details and property location, along with any known access, drainage or agreement issues. A permit application or engineered project plan is not needed for this initial conversation.
Sources & further reading
County webpages, official county-linked fire portal and posted documents reviewed October 8, 2026. The 2026 questionnaire was read fully as text and a rendered page. The December 2025 subdivision posting is 169 pages: selected opening and related provisions were read as text; solar-farm section 12.06 (physical pages 127–128) and site-authorization section 14 (134–137) were also read visually. The 35-page fire amendment file was reviewed selectively, with physical pages 5–8 read as text and rendered pages; the separate six-page fee schedule construction and operation tables (3–4) were also read both ways. Full subdivision and fire-code review, underlying technical standards, current fee reconciliation, actual parcel jurisdiction, grid capacity and active project land needs remain unverified. Questionnaire page and form differ on optional versus required status; separately posted fire fee tables also differ. Confirm current project requirements with the responsible office. Local rules and program details can change. Check the requirements for the actual project.
- Kaufman County: project questionnaire guidance
- Kaufman County: posted 2026 project questionnaire
- Kaufman County: subdivision and land development regulations, December 2025 posting
- Kaufman County: Fire Marshal permits and inspections
- Kaufman County: posted 2024 fire-code amendments
- Kaufman County Fire Marshal: separately posted permit fee schedule
- Kaufman County: construction permits
- Kaufman County: operational permits
- Kaufman County: utility meter release form
- Kaufman County: Development Services department contacts