Ask whether the existing entrance covers the proposed use
An entrance used for a ranch or field may look suitable from the road. Ask the company to explain how it will handle equipment deliveries, construction traffic, routine visits and emergency access. Show it where you currently enter and how you use the rest of the property.
The posted county permit reserves the right to require a new driveway permit after a material land-use change or a change in traffic volume or vehicle types. The linked manual also addresses new, modified and replacement entrances. Ask the company to establish what review is needed for its proposed use instead of relying on the fact that a driveway already exists.
Identify the road and the authority responsible for it. The manual’s checklist addresses driveways outside city limits in La Salle County road right-of-way. Have the company confirm whether that is the actual situation, or whether city, state-road or private access questions belong with another authority.
Ask for the existing permission, the proposed changes and any new approval. If the entrance is shared with another owner or crosses land outside your tract, review those private rights as well. County permission for a road entrance does not provide every right needed to reach the battery site.
Reference: La Salle County: posted access driveway permit, approved April 13, 2015 · La Salle County: posted driveway process and Access Management Manual, dated April 13, 2015

Compare the entrance drawing with the land you will keep
The county’s posted checklist calls for a driveway drawing with location, dimensions, nearby entrances and intersections, and features such as buildings, fences, poles and landscaping. Ask the company to show its proposal clearly enough that you can see what would move or change.
The manual’s design discussion considers the vehicles using the entrance, sight distance, turning space and room near a gate. Have the project engineer account for the actual deliveries and traffic. A general ranch-driveway example is not a complete design for battery transport or emergency access.
Discuss gates, livestock, fields and access you expect to retain. Where would trucks wait? Could construction block your existing entrance? Would the company need a temporary entrance or additional land near the road? Make those areas part of the proposal you review.
The drainage section discusses maintaining flow in roadside ditches and county review of required structures. Ask who designs and pays for any culvert, grading or drainage changes and how the work affects your retained land. Keep that responsibility in the agreement rather than treating the entrance as a small detail outside the project.
Reference: La Salle County: posted driveway process and Access Management Manual, dated April 13, 2015
Know who holds the permit and who maintains the entrance
The standalone permit assigns maintenance of the constructed facilities to the permit holder. It also allows the county to require changes, repairs or maintenance for protection of life or property. Ask whether the owner, company or another party would be named as the permit holder.
If the company proposes to submit in your name or act as your representative, read the completed application and attached drawing. Understand the authority you are giving it and which changes would still need your agreement. Your private lease should explain how the company will perform and pay for obligations associated with the project.
The form includes a hold-harmless commitment to the county and its agents or employees for injury or property damage associated with exercising the permit. Review that language with your adviser alongside the company’s repair, insurance and responsibility provisions. Do not leave the public document and private agreement as unrelated conversations.
Plan beyond the initial construction. Who keeps the entrance usable, repairs damage, responds to a county request and takes over after the project changes owners? Ask what happens if the company stops work or the project ends while the entrance still serves your property.
Reference: La Salle County: posted access driveway permit, approved April 13, 2015
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeparate an application, an issued permit and a finished entrance
The posted process starts with submission and review, followed by approval, installation and inspection. Its manual says construction should not begin until the county has processed and approved the application. Ask the company to show the actual approval and conditions for work in the right-of-way.
The documents also address changes after review. The manual calls for a new application if construction materials change, and the form requires county approval of design changes. Ask how the company will handle a redesign and any resulting delay or cost without starting work outside the approved plan.
The posted permit has a six-month completion provision measured from issuance. Its notice language differs from the process sheets: the form gives twenty-four hours before work, while the process gives two days. Have the company confirm the current instructions and dates with the office; this guide does not resolve that difference.
Compare the construction schedule with the land-option period and any access permission you grant. A permit submitted for review is not the same as a completed entrance. Ask what remains before installation, how inspection issues will be corrected and who repairs incomplete work if the proposal is abandoned.
Reference: La Salle County: posted driveway process and Access Management Manual, dated April 13, 2015 · La Salle County: posted access driveway permit, approved April 13, 2015
| Reported progress | Owner question |
|---|---|
| We can use the ranch entrance | Has the proposed use and traffic been reviewed? |
| We filed the driveway application | Is there an issued permit and approved drawing? |
| The entrance is built | Has inspection passed and who handles corrections? |
| The county signed the service certificate | What separate battery connection work remains? |
Keep the county service certificate separate from battery connection approval
La Salle County’s permit directory also links a Certificate of Compliance packet. The dated packet describes a rural-property and subdivision process for new electric or gas service and proposed meters. Ask the company whether that process applies to the actual project and how it relates to other required reviews.
The application requests property and owner information, existing and proposed structures, service providers, plat information and whether a current deed is available. It includes a signature accepting stated conditions and certifying the information. If you are asked to sign it, have the preparer explain the entries and what you are accepting.
A county certificate concerning service and property compliance does not establish the utility study for a battery’s charging and export. Ask which utility is reviewing the connection, the proposed power levels, what has been submitted and what remains before an agreement or construction.
Keep the scope of each document clear. A named provider or work-order field is not evidence that the provider will accept the battery at the proposed capacity. The packet’s general service and subdivision discussion also does not establish that every battery proposal must follow the same application or residential meter rules.
Reference: La Salle County: posted service Certificate of Compliance and application, dated March 8, 2016
Confirm versions, charges and responsibilities before signing
The linked driveway documents state a 2015 approval or adoption date, and the certificate packet is dated 2016. They are currently linked by the county, but that does not settle whether later instructions, charges or project-specific conditions apply. Have the company confirm the version it will use.
Ask the office and preparer to resolve the notice-period difference and identify the appropriate use classification. The reviewed forms include several ordinary driveway and service categories. Do not choose a ranch category merely because the land is currently a ranch if the proposed use would change.
Assign the costs in the private agreement: engineering, applications, resubmissions, construction, inspections, repairs and ongoing maintenance. Discuss work that affects retained land and who deals with the county if the project company changes.
Keep copies of the signed documents, approved drawings, conditions and completion records. Ask your adviser to compare any commitments you make publicly with the company’s promises to you. Complete project approval still requires the actual development, fire, floodplain and electrical review for the site.
Reference: La Salle County: current links to permits and applications · La Salle County: posted driveway process and Access Management Manual, dated April 13, 2015 · La Salle County: posted access driveway permit, approved April 13, 2015 · La Salle County: posted service Certificate of Compliance and application, dated March 8, 2016
Tell Sunland about the land and its access
Start with your contact details and then the location. The form selects La Salle County and Texas; change them if necessary. Acreage and parcel number are optional. This guide concerns the Texas county around Cotulla.
Describe the entrance, road, current land use and whether you would consider a lease, sale or use of only part of the property. Mention a shared route, ditch, livestock gate or existing offer that you want discussed.
If someone has asked you to sign a driveway permit or service certificate, explain which document and who would be listed on it. You can begin the conversation without filing public paperwork or arranging engineering work.
Sunland may follow up to learn more. An inquiry does not approve an entrance change, authorize construction or site access, file an application, reserve the land or commit you to a transaction.
Questions landowners ask
Can the project simply use my existing ranch entrance?
Ask the company to confirm the actual permission and proposed use. The posted county permit allows a new permit to be required after changes in land use, traffic volume or vehicle types. Private access rights and project design need separate review.
Who maintains a county-road driveway after it is built?
The posted form assigns maintenance to the permit holder and allows county-required changes or repairs. Establish who would hold the permit and how the private land agreement assigns performance and costs.
Does a submitted driveway application mean construction can start?
The posted manual separates submission, approval, installation and inspection. Ask for the issued permission and conditions for the work rather than treating application submission as approval.
How much notice must the company give before driveway work?
The posted permit gives twenty-four hours while its process sheets give two days. Have the company confirm the current instructions with the office. The difference is not resolved by this guide.
Does a Certificate of Compliance prove the battery can connect to the grid?
No. The dated packet describes a property and utility-service process. It does not establish a utility agreement or capacity for battery charging and export. Ask for the separate connection review and its status.
Do I need county permits before contacting Sunland?
No. Start with contact details and location, then describe the property and any questions. Acreage and parcel number are optional, and you are not committing to a lease or sale.
Sources & further reading
Official permit-directory links rechecked October 8, 2026. The twenty-two-page driveway process was fully text-read; nine selected physical pages were visually checked. The two-page standalone driveway permit and seven image-only certificate/application pages were fully visually read. Driveway documents state April 13, 2015 and the certificate is dated March 8, 2016; latest adoption and complete current governing rules were not established. Process pages give two days of work notice while the permit says twenty-four hours. Confirm current versions, fees, notice, actual road/parcel authority and project classification. Underlying subdivision ordinance and statutory references were not independently reviewed; no universal battery certificate, dimension or grid-capacity conclusion follows from these documents. Local rules and program details can change. Check the requirements for the actual project.
- La Salle County: current links to permits and applications
- La Salle County: posted driveway process and Access Management Manual, dated April 13, 2015
- La Salle County: posted access driveway permit, approved April 13, 2015
- La Salle County: posted service Certificate of Compliance and application, dated March 8, 2016