A new solicitation is separate from earlier project selections
The procurement team publishes a Round II RFP revised September 4, 2026. It includes both distribution and transmission projects. A future bid under that document is different from a selected project or a contract already filed for regulatory review.
Ask the developer which round and project it means. If it is still preparing a bid, ask which parts of the plan are settled and which depend on being selected. Do not treat a previous award to another project as evidence that the new proposal will receive the same terms or outcome.
Reference: Massachusetts procurement team: Round II documents and revisions · Massachusetts procurement team: September 4, 2026 revised Round II RFP

Site control is more than the equipment pad
The revised RFP requires documented site control or an irrevocable option to acquire it, including necessary additional land rights. Its site-control section calls for a plan and identification of the documents supporting the rights sought.
If asked for an option, have the developer show the battery area, access, cables and temporary construction space. Mark any land you want excluded. Ask whether the proposed agreement reserves more land than the final project is expected to occupy and when unused areas would be released.
Reference: Massachusetts procurement team: September 4, 2026 revised Round II RFP
| Part of the offer | Question for the developer |
|---|---|
| Equipment area | What would stay on the land during operation? |
| Reserved area | What else is held during investigation? |
| Access and cables | Which routes affect the rest of the property? |
| Bid dependency | What happens if the project is not selected? |
A bid deadline is not your inquiry deadline
DOER’s September 3 extension filing lists October 8, 2026 at noon Eastern as the revised proposal deadline and says the schedule can be revised. That is a bidder deadline in a dated filing, not a deadline for asking Sunland about your property.
If someone says an agreement must be signed quickly for a bid, ask which current notice it relies on and what work has already been completed. A short timetable does not remove the need to understand the document. Have the proposed option reviewed for your circumstances before signing.
Reference: Massachusetts DOER: September 3, 2026 solicitation timeline extension
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDistinguish a local-grid proposal from a transmission proposal
The RFP defines different electrical routes and proposal requirements for distribution and transmission projects. It also excludes ordinary associated on-site demand from its definition of a distribution project, apart from the storage system’s own operating needs.
Ask what the planned battery would serve and where charging and export would occur. A proposal to serve your business is not explained merely by citing this solicitation. Request the study or agreement references for the actual connection and ask what work remains. A nearby power line does not settle the route or costs.
Reference: Massachusetts procurement team: September 4, 2026 revised Round II RFP
Put the uncertain period into the agreement
Ask what is paid during the option, how long it lasts and who can extend it. Understand the work allowed on the property before a lease starts. If the developer needs a new bid after an unsuccessful round, ask whether that requires a new agreement or can keep the existing reservation in place.
Identify what starts operating rent and what ends the reservation. Ask how a reduced project footprint or delayed electrical study changes your payment and retained land. If you have tenants or planned construction, have those uses addressed before exclusivity is granted. The project’s revenue plan and your own payment schedule are separate matters.
Know who can use and transfer the rights
Find out which entity signs your agreement and whether the developer expects to sell the project before operation. Ask how you would be notified, who remains responsible for damage and payments, and how operating and removal responsibilities would pass to a new owner.
Keep the final drawing and contact details with the agreement. Ask how material changes would be presented for your review. A bid document should not leave you uncertain about which land may be entered or what may be said publicly about your property.
Start with the location and what you want to learn
Send Sunland your contact details and property location. Add the city or town, current use and any offer or project name you have. If someone has mentioned Round II, tell us whether you are considering a new option or already have a land agreement.
You do not need to submit a procurement bid or decide the electrical route yourself. We can begin with the information you know. Further work still needs to establish the rights, connection, design, approvals and commercial fit. An inquiry does not reserve your property or guarantee selection.
Questions landowners ask
Do I need to bid to ask about my land?
No. The project solicitation is separate from your initial property inquiry.
Does an option mean the project has been selected?
No. Ask about the bid dependency, payments and release terms.
Does the bidder deadline require me to sign immediately?
Have the current deadline and proposed agreement explained. A bidder timetable does not replace reviewing the rights you would grant.
Sources & further reading
Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.