Find out which project the company is proposing
Ask for a short description of what would be built on your land. Is this a battery facility on its own, batteries alongside a solar installation, or land needed for utility work? Identify the company that would sign your agreement and the company expected to operate the equipment.
Blandford’s project directory lists Mission’s North Blandford Road storage proposal separately from the Peebles Brook and Gibbs Brook solar-associated projects and the Eversource proceedings. Keep those distinctions when discussing an offer. A reference to another project is useful only if the company explains how it relates to the proposal on your property.
If someone says your land is near an approved energy site, request the actual approval reference and a drawing. Check whether your parcel is included and what equipment or use the decision covers. Do not assume the name of a nearby facility settles the question for an adjoining tract.
Write down what interests you about the offer and what you need to keep available. You might consider part of a field but need the entrance for farming, or consider a road crossing without leasing land for equipment. Tell the project team that at the beginning.
Reference: Blandford: separate battery, solar and utility project records

Separate the town vote from permission for your parcel
Blandford’s certified June 1, 2026 minutes record votes to replace the battery and solar sections and add an energy overlay. The March 11 Attorney General letter concerns a different action: it disapproved the temporary moratorium adopted in November 2025. Those records should not be treated as the same decision.
Ask the Planning Board or project adviser for the final applicable battery text, its state-review and effective-date record, and the current map for your location. The Town’s linked August 2024 compilation predates the June votes. This guide does not establish the operative district permissions or dimensional rules for your parcel.
Have the company identify the process it expects to follow and what decisions remain. If it refers to a state proceeding, ask for that proceeding’s reference and proposed project description. If it refers to a local permit, ask which application and board it means.
Keep the response with the drawing and offer you are evaluating. A later change in equipment, occupied area or connection can change the questions. Ask the company to explain the effect before you approve a revised land commitment.
Reference: Blandford: certified June 1, 2026 town-meeting minutes · Massachusetts Attorney General: March 11, 2026 Blandford moratorium decision · Blandford: August 2024 zoning compilation, older battery provisions · Blandford Planning Board: current contact and posted resources
| What you receive | What to check |
|---|---|
| Town-meeting minutes | Which change voters approved |
| Final rules and map | What applies to the proposed location |
| Project decision | Which equipment, parcels and conditions it covers |
| Connection record | What is established for this proposal |
| Private agreement | What land and duties you would commit |
Walk the retained land on the project drawing
Ask the company to show more than the battery fence. Include access, cable routes, grading, drainage, planting, construction storage and areas reserved for emergency work. Identify which areas it would occupy and which it would restrict without occupying.
The Town’s older battery section asks for existing site features and proposed landscape changes, along with site-control and access information. Whatever final requirements apply, those are practical subjects to discuss before you reserve land. A container count cannot show how a project affects the rest of your property.
If you cut hay or keep livestock, mark the route you use between the road, field, barn and water supply. Check whether a new gate, ditch or work area would interrupt it. Ask how you would reach retained land during construction and what notice you would receive when a shared route is unavailable.
Identify any existing tenant or informal use of the land. Have your adviser examine how the proposed project interacts with those arrangements. Describe future plans too, such as dividing a parcel, expanding a building or selling the remaining land, so the proposed restrictions can be considered together.
Reference: Blandford: August 2024 zoning compilation, older battery provisions
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss winter and emergency access before agreeing on a road
Blandford’s July informational presentation identifies local emergency-response concerns, including mountainous terrain, water availability and reliance on mutual aid. It was an information session, not a permit decision. Ask the project team how the actual site plan and emergency review address the location being proposed.
For a road across your land, ask who keeps it usable throughout the year. Identify responsibility for plowing, ice, drainage, fallen trees, damaged surfaces and gates. If the road also serves your home or farm, discuss how maintenance and project traffic will affect your access.
Ask the company to explain the proposed emergency route and any water or working area it needs. Does that require rights over retained land or a neighbor’s property? Get those areas on the drawing rather than accepting an assurance that the details can be arranged later.
Separate the operator’s maintenance duties from your own. Ask which responsibilities appear in the project documents and which would be put on you by the land agreement. Review any obligation to provide access, maintain a feature or pay a cost that continues beyond the initial construction period.
Reference: Blandford Select Board: July 15, 2026 informational energy presentation
Keep connection studies and your reservation period together
Blandford’s directory includes substation work as well as generation and storage proposals. That helps identify relevant public records; it does not show that a new battery proposal has a usable connection. Ask where your proposed facility would connect and what has actually been studied or accepted.
Request the company’s project-specific reference, latest result and next expected milestone. Ask whether another road crossing, land agreement or utility improvement is needed. A feasible equipment area may depend on rights or work outside your ownership.
Before granting an option, compare its length with that schedule. What will the company do during the reservation, what information will it share with you, and what happens if studies take longer than expected? Discuss extension payments and the release of unused land with your adviser.
An owner should be able to distinguish money paid to hold land from money paid after the project starts using it. Ask for the trigger for each payment and what happens if the connection cannot be obtained. Evaluate the actual offer against your own plans for the property.
Reference: Blandford: separate battery, solar and utility project records
Identify who pays for each continuing obligation
Make a list of costs and duties discussed in the offer: damaged-road repairs, landscaping, drainage upkeep, insurance, property-related taxes, equipment removal and returning land to use. For each, identify the responsible company, the document that creates the duty and when it begins.
If your land is enrolled in a farm or other reduced-assessment program, have the proposed change reviewed for your property before agreeing to it. The Town’s July presentation raises agricultural classification and payments to the Town as separate topics. Neither should be treated as a promised private payment to you.
Ask for an explanation of the project’s removal plan and financial protection when available. The older battery provisions address removal, restoration and financial security. Compare the actual applicable requirements with the returned condition promised in your agreement, including roads, foundations and any improvement you want retained.
For a sale or operator change, ask how you learn who takes over payments and upkeep. Keep a contact for routine matters and an identified route for damage or nonperformance. Review whether the original company remains responsible and what evidence you receive when obligations are transferred.
Reference: Blandford Select Board: July 15, 2026 informational energy presentation · Blandford: August 2024 zoning compilation, older battery provisions
Start with the location and the land you would consider
Use the form to send your contact details and an identifiable property location. Massachusetts and Hampden County are selected for this page and can be changed. You can leave acreage and parcel number blank if you do not have them handy.
Mention whether the land is farmed, leased, wooded or already involved in an energy proposal. Tell us which part you would consider and any access or activity you need to keep. A road name, location description and what you know about the property are enough to begin a conversation.
You do not need to authorize a public filing or reserve land to ask Sunland about a property. Further discussion depends on the actual land, applicable review, connection evidence and commercial terms. An initial inquiry is a place to start those questions.
Questions landowners ask
Do Blandford’s June votes approve battery storage on my parcel?
The minutes record changes approved by town voters. Your proposal still needs its applicable rules, review route and project-specific decisions established.
Is the March Attorney General letter about the June replacement battery rules?
No. The March letter addresses the temporary moratorium adopted in November 2025. Ask for the separate record concerning the replacement rules.
Can I keep using land outside the battery fence?
Discuss the full restricted area, routes and construction space. Have the company explain how your farming, access and future plans would interact with the proposed agreement.
Who would maintain a shared project road in winter?
Get a written explanation of plowing, ice, repairs, gates and shared access. Compare the operator’s project duties with anything the land agreement asks you to do.
Do I need a parcel number to contact Sunland?
No. Send your contact information and an identifiable property location. Acreage and parcel number are optional for the initial inquiry.
Sources & further reading
Sources checked 2026-10-07. Local rules and program details can change. Check the requirements for the actual project.
- Blandford: separate battery, solar and utility project records
- Blandford: certified June 1, 2026 town-meeting minutes
- Massachusetts Attorney General: March 11, 2026 Blandford moratorium decision
- Blandford: August 2024 zoning compilation, older battery provisions
- Blandford Select Board: July 15, 2026 informational energy presentation
- Blandford Planning Board: current contact and posted resources