Start with the service provider and the proposed use
Confirm who would serve the proposed battery, including a separate new service if one is needed. A postal address, existing building account or line alongside the road may not tell you the connection arrangement for new equipment.
Ask the company to describe the project in a few sentences. Would the battery support an existing business, operate as a separate facility, or accompany solar equipment? Where would it charge and discharge? You should not need to infer the answer from a picture.
HG&E’s resource page links its DG policy and several storage wiring examples. These are useful starting documents, not a completed design for a leased-land battery. Have the team obtain the utility’s response to the actual configuration.
If a company is discussing land outside Holyoke, have it establish the applicable provider and process for that location. This guide concerns HG&E; it does not assign every nearby parcel to its service or approval route.
Reference: HG&E: connection documents and storage wiring resources

Make a list of the people and companies involved
Put the property owner, current electric account holder, project company, equipment owner, operator and utility on one list. Ask which roles belong to the same entity and which require separate agreements.
The posted policy, dated November 8, 2023, separates the customer from the interconnecting customer and calls for proof of site control. Ask HG&E which current documents apply to the proposal. Do not sign a technical application merely because you own the address.
For a tenanted property, discuss who can consent to work on the premises. Does the tenant control the proposed space or hold the electric account? Would a new project require changes to its lease or access? Resolve those questions before promising the space twice.
Ask your adviser to compare the names on the proposed land and utility documents. If you are expected to sign in more than one role, find out what each signature commits you to and whether the project company should hold that responsibility instead.
Reference: Holyoke Gas & Electric: posted DG policy, updated November 8, 2023
Keep electricity compensation separate from the land offer
Ask for a written schedule of the payments owed to you: any reservation payment, extension payment, construction-period payment, rent or purchase price. Identify the payer and the event that starts each payment.
HG&E’s policy describes separate electricity-compensation arrangements, including power-purchase and wholesale-market routes. Those describe the project’s electrical business. They do not state the rent a private property owner will receive.
If the offer depends on the company securing an electricity buyer, ask how much time it has and what you receive while it waits. Does failure to secure that contract end the land hold, permit another extension, or change the proposed payment?
If a bill credit is discussed, identify the account receiving it. An occupied building may have a tenant’s account while its owner receives rent. Put those benefits in separate columns so a savings example does not obscure the actual land offer.
Ask whether rent is fixed or depends on operations, revenue or another contract. Have any deductions and payment conditions explained in plain language. A forecast of project income is different from an enforceable promise to pay you.
Reference: Holyoke Gas & Electric: posted DG policy, updated November 8, 2023
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landName the party responsible for connection costs
Request the connection drawing and a list of studies, meters, electrical equipment and outside work still needed. Ask who orders the work and who pays the bills, including changes to an initial estimate.
The posted policy assigns study, metering and system-modification costs to the interconnecting customer in relevant circumstances. Compare that role with the proposed signatories and land terms rather than assuming every cost belongs to the property owner.
Would the company be allowed to recover connection expenses from your rent, ask you to finance equipment or expand the land reservation if the route changes? If so, ask for the limits before agreeing.
If the connection proves too expensive, find out how the project ends. Identify the deadline for releasing recorded rights, repairing investigation damage and returning areas temporarily occupied. Keep the question separate from whether an application was accepted.
Reference: Holyoke Gas & Electric: posted DG policy, updated November 8, 2023
Show meters, the disconnect and access on the property map
The policy discusses utility access to the disconnect switch. Ask the designer to mark that equipment and its access route alongside the battery area, meters and cables. A fence around the batteries may not describe every right the project needs.
Would utility or maintenance visits pass through a tenant’s yard, parking area or farm entrance? Discuss gates, keys, notice for routine visits and what happens during an emergency. Keep access to your remaining property usable.
Identify temporary construction routes and permanent rights separately. A crew may need turning or storage space during installation that the operator does not need afterward. Agree how and when that space is restored.
If the project shares an existing electrical service, ask who maintains the shared equipment and how work or an outage affects the building. Request an explanation of what changes if the tenant leaves or you sell the rest of the property.
Reference: Holyoke Gas & Electric: posted DG policy, updated November 8, 2023
Compare utility milestones with permits and land deadlines
Ask the team to distinguish an application, permission to install and permission to operate. Request the actual dated document for the stage it claims. A blank utility form is not evidence that a project has reached that stage.
Holyoke’s Planning Department publishes zoning and application resources. Ask the appropriate officials to identify the current permitting route for the actual parcel and battery design. Utility review does not resolve the public land-use question.
Compare those remaining steps with your option period. What payments are due during review, what permits an extension and when does the reservation finally end? If you are selling, identify the conditions and closing deadline separately.
If the equipment company changes, ask how the successor assumes utility and land obligations. A transfer of a connection agreement should not leave rent, insurance, repairs or removal without an identified responsible company.
Before signing, keep the dated map, payment schedule, access description and supporting approval records together. You can then see whether later changes alter the land or duties you originally considered.
Reference: City of Holyoke: planning contacts, zoning and application resources
Send the location and the arrangement you are considering
Start with your contact information and property location. Massachusetts and Hampden County are selected on this page and can be changed. Acreage and a parcel number are optional; include the electric provider if you know it.
Mention an existing business, tenant or solar system, and whether the offer is for a lease, sale or simply a period of investigation. If you already have documents, describe the signature request or deadline. You do not need a finished electrical plan to start a conversation.
Sunland can review the information and discuss the next questions. Sending this form does not apply to HG&E, grant site control, authorize entry or commit you to a project.
Questions landowners ask
Does HG&E’s published DG policy include storage?
Yes. Its posted policy includes energy storage. Ask the utility to confirm the current documents and route for the actual battery configuration.
Is an electricity payment the same as rent for my land?
No. Identify the project’s electrical revenue separately from the payments owed to you under the land agreement.
Should I sign the utility application because I own the parcel?
First establish the role you would be signing in and its obligations. Compare it with the project company’s role and ask your adviser to review the documents.
Does a utility application approve the land use?
No. Have the team establish both the connection stage and the applicable public permits for the parcel.
Do I need a project drawing to contact Sunland?
No. Send your contact details, the property location and what you are considering. Acreage and a parcel number are optional.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.